SL 8(N): Hardy St to Aldine Westfield
3256-02-121 · let May 7, 2026 · Harris, Houston · Overlay
$2,254,486Low bid: ENVIRONMENTAL ALLIES, INC.-1.4% vs estimate $2,286,187
$22,073Left on the table1.0% gap to the second bid
5BiddersSpread 47% low to high
66Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ENVIRONMENTAL ALLIES, INC. | $2,254,486 | -1.4% | $22,073 | 2+$103,313 | 1-$423,612 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $2,276,558 | +1.0% | -0.4% | $481,974 | 4+$164,759 | 3-$542,337 |
| 3 | HAYDEN PAVING, INC. | $2,758,532 | +22.4% | 20.7% | $454,413 | 8+$469,374 | 1-$428,850 |
| 4 | ISI CONTRACTING, INC. | $3,212,945 | +42.5% | 40.5% | $104,833 | 9+$646,169 | 0 |
| 5 | DURWOOD GREENE CONSTRUCTION CO. | $3,317,778 | +47.2% | 45.1% | 8+$547,361 | 1-$273,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ENVIRONMENTAL ALLIES, INC. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7064 SP MIXES SP-D SAC-A PG76-22 | 7,544 TON | $140.00 | $153.00 | $129.17 | $98,072 |
| 529-7007 CONC CURB (MONO) (TY II) | 401 LF | $9.00 | $211.00 | $6.85 | $81,002 |
| 500-7001 MOBILIZATION | 1 LS | $100,238.09 | $47,000.00 | $523,850.32 | -$53,238 |
| 361-7036 FULL - DEPTH REPAIR CPJR (8") | 175 CY | $1,500.00 | $1,200.00 | $994.40 | -$52,500 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 528 CY | $305.00 | $225.00 | $133.09 | -$42,240 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 2,357 SY | $72.50 | $88.00 | $60.19 | $36,534 |
| 354-7066 PLANE CONC PAV(0" TO 2") | 2,549.37 SY | $7.85 | $20.00 | $4.21 | $30,975 |
| 104-7016 REMOV CONC (CURB) | 401 LF | $4.00 | $78.00 | $6.82 | $29,674 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $8,000.00 | $1,150.00 | $11,585.04 | -$27,400 |
| 344-7077 TACK COAT | 7,544 GAL | $3.65 | $0.1000 | $3.25 | -$26,781 |
| 316-7067 ASPH (AC-20-5TR OR AC-20XP) | 24,691 GAL | $4.50 | $3.50 | $3.44 | -$24,691 |
| 134-7004 BACKFILL (TY A OR B) | 160 STA | $315.00 | $175.00 | $211.21 | -$22,400 |
| 505-7001 TMA (STATIONARY) | 62 DAY | $250.00 | $445.00 | $217.57 | $12,090 |
| 720-7001 SPALLING REPAIR (HYDRAULIC CEMENT) | 34 CF | $575.00 | $243.00 | $206.00 | -$11,288 |
| 531-7003 CONC SIDEWALKS (6") | 10 SY | $175.00 | $896.00 | $88.84 | $7,210 |
| 104-7005 REMOV CONC (MOWSTRIP) | 1,000 LF | $20.00 | $13.00 | $9.49 | -$7,000 |
| 432-7009 RIPRAP (CONC) (CL B) (6 IN) | 10 CY | $525.00 | $865.00 | $533.30 | $3,400 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 3,006 EA | $1.40 | $0.7000 | $1.03 | -$2,104 |
| 666-7309 ALL-WTHER PM TY I (W)6"(SLD)(100MIL) | 13,989 LF | $0.9000 | $0.7500 | $0.6917 | -$2,098 |
| 540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION | 5 EA | $1,300.00 | $1,635.00 | $1,297.32 | $1,675 |
Positive: the low bidder was cheaper on that item. These 20 items account for $28,891 of the $22,073 gap.
ENVIRONMENTAL ALLIES, INC.: unbalanced items
Placed 1TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 529-7007 CONC CURB (MONO) (TY II) | 401 LF | $211.00 | $6.85 | 30.82x | $81,865 |
| 354-7066 PLANE CONC PAV(0" TO 2") | 2,549.37 SY | $20.00 | $4.21 | 4.75x | $40,248 |
| 104-7016 REMOV CONC (CURB) | 401 LF | $78.00 | $6.82 | 11.44x | $28,545 |
| 505-7001 TMA (STATIONARY) | 62 DAY | $445.00 | $217.57 | 2.05x | $14,101 |
| 500-7001 MOBILIZATION | 1 LS | $47,000.00 | $523,850.32 | 0.09x | -$476,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $1,150.00 | $11,585.04 | 0.10x | -$41,740 |
| 344-7077 TACK COAT | 7,544 GAL | $0.1000 | $3.25 | 0.03x | -$23,747 |
HAYDEN PAVING, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 2,357 SY | $120.00 | $60.19 | 1.99x | $140,969 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 528 CY | $350.00 | $133.09 | 2.63x | $114,528 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $26,000.00 | $11,585.04 | 2.24x | $57,660 |
| 529-7007 CONC CURB (MONO) (TY II) | 401 LF | $150.00 | $6.85 | 21.91x | $57,404 |
| 505-7001 TMA (STATIONARY) | 62 DAY | $750.00 | $217.57 | 3.45x | $33,011 |
| 104-7016 REMOV CONC (CURB) | 401 LF | $70.00 | $6.82 | 10.27x | $25,337 |
| 354-7066 PLANE CONC PAV(0" TO 2") | 2,549.37 SY | $14.00 | $4.21 | 3.32x | $24,952 |
| 104-7005 REMOV CONC (MOWSTRIP) | 1,000 LF | $25.00 | $9.49 | 2.64x | $15,513 |
| 500-7001 MOBILIZATION | 1 LS | $95,000.00 | $523,850.32 | 0.18x | -$428,850 |
ISI CONTRACTING, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 134-7004 BACKFILL (TY A OR B) | 160 STA | $1,800.00 | $211.21 | 8.52x | $254,206 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 2,357 SY | $108.49 | $60.19 | 1.80x | $113,840 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $32,420.68 | $11,585.04 | 2.80x | $83,343 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 528 CY | $283.84 | $133.09 | 2.13x | $79,595 |
| 104-7016 REMOV CONC (CURB) | 401 LF | $74.00 | $6.82 | 10.86x | $26,941 |
| 354-7066 PLANE CONC PAV(0" TO 2") | 2,549.37 SY | $13.95 | $4.21 | 3.31x | $24,825 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 42 CY | $1,161.00 | $616.83 | 1.88x | $22,855 |
| 505-7001 TMA (STATIONARY) | 62 DAY | $550.00 | $217.57 | 2.53x | $20,611 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 666 SY | $32.09 | $2.13 | 15.06x | $19,953 |
DURWOOD GREENE CONSTRUCTION CO.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 361-7036 FULL - DEPTH REPAIR CPJR (8") | 175 CY | $2,500.00 | $994.40 | 2.51x | $263,479 |
| 354-7066 PLANE CONC PAV(0" TO 2") | 2,549.37 SY | $35.00 | $4.21 | 8.31x | $78,489 |
| 316-7211 AGGR (TY-PB, GR-4)(SAC-B) | 528 CY | $275.00 | $133.09 | 2.07x | $74,928 |
| 529-7007 CONC CURB (MONO) (TY II) | 401 LF | $90.00 | $6.85 | 13.15x | $33,344 |
| 134-7004 BACKFILL (TY A OR B) | 160 STA | $400.00 | $211.21 | 1.89x | $30,206 |
| 104-7005 REMOV CONC (MOWSTRIP) | 1,000 LF | $35.00 | $9.49 | 3.69x | $25,513 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 42 CY | $1,200.00 | $616.83 | 1.95x | $24,493 |
| 438-7001 CLEANING AND SEALING EXISTING JOINTS | 100 LF | $185.00 | $15.92 | 11.62x | $16,908 |
| 500-7001 MOBILIZATION | 1 LS | $250,000.00 | $523,850.32 | 0.48x | -$273,850 |