SS 366 Deck Plaza Structure Extension
0196-07-034 · let Jun 2, 2026 · Dallas, Dallas · Bridge Widening or Rehabilitation
$93,868,232Low bid: ARCHER WESTERN-5.5% vs estimate $99,373,372
$2,936,916Left on the table3.1% gap to the second bid
6BiddersSpread 35% low to high
348Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | ARCHER WESTERN | $93,868,232 | -5.5% | $2,936,916 | 5+$25,701,136 | 0 | |
| 2 | RAGLE CONSTRUCTION, INC. | $96,805,148 | +3.1% | -2.6% | $8,602,326 | 8+$31,479,813 | 1-$1,830,491 |
| 3 | WEBBER, LLC | $105,407,474 | +12.3% | 6.1% | $752,119 | 7+$40,211,660 | 0 |
| 4 | HARPER BROTHERS CONSTRUCTION LLC | $106,159,593 | +13.1% | 6.8% | $14,445,807 | 16+$34,162,277 | 3-$4,136,238 |
| 5 | BALFOUR BEATTY INFRASTRUCTURE, INC. | $120,605,400 | +28.5% | 21.4% | $6,561,521 | 16+$48,211,288 | 3-$4,346,468 |
| 6 | INDUS ROAD & BRIDGE, INC. | $127,166,921 | +35.5% | 28.0% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
ARCHER WESTERN vs RAGLE CONSTRUCTION, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $317,392.67 | $2,500,000.00 | $136,676.66 | $2,182,607 |
| 4043-7001 ELECTRICAL SERVICE BUILDING | 1 LS | $385,926.46 | $2,500,000.00 | $385,926.46 | $2,114,074 |
| 6116-7001 ELECTRIC UNDERGROUND VAULT | 1 EA | $936,883.39 | $2,800,000.00 | $936,883.39 | $1,863,117 |
| 5062-7001 FIRE STANDPIPE | 2,410 LF | $1,092.68 | $333.14 | $1,092.68 | -$1,830,491 |
| 425-7060 TRENCH PANEL | 1,137.44 LF | $536.41 | $2,060.00 | $536.41 | $1,732,992 |
| 425-7006 PRESTR CONC GIRDER (TX62) | 4,338.91 LF | $866.82 | $489.00 | $189.94 | -$1,639,327 |
| 425-7058 PRESTR CONC BOX BEAM (B54) | 2,157.43 LF | $1,204.68 | $1,902.00 | $1,204.68 | $1,504,419 |
| 423-7019 RETAINING WALL (DRILL SHAFT) (FASCIA) | 6,830 SF | $263.60 | $87.00 | $103.21 | -$1,206,178 |
| 6141-7001 JET FAN ASSEMBLIES | 12 EA | $119,522.27 | $193,330.00 | $119,522.27 | $885,693 |
| 5059-7001 FIREPROOFING | 238,245 SF | $26.66 | $23.00 | $26.66 | -$871,977 |
| 425-7059 PRESTR CONC BOX BEAM (B78) | 1,523.45 LF | $1,296.04 | $1,840.00 | $1,296.04 | $828,696 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $145,640.00 | $170,000.00 | $11,585.04 | $633,360 |
| 6137-7001 CONCRETE ENCASED DUCT BANK | 4,793 LF | $893.67 | $784.10 | $893.67 | -$525,169 |
| 6135-7001 CV PWR CBL (3C #14 PTFE RTD EXT) | 51,552 LF | $48.67 | $38.70 | $48.67 | -$513,973 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 21 EA | $6,510.46 | $30,000.00 | $9,253.78 | $493,280 |
| 100-7002 PREPARING ROW | 10.9 STA | $861,170.00 | $823,850.00 | $6,072.92 | -$406,788 |
| 6130-7001 MCC WITH VFD MOTOR CONTROLLERS | 3 EA | $531,664.81 | $422,570.00 | $531,664.81 | -$327,284 |
| 420-7158 CL C CONC (BENT)(HPC) | 475.5 CY | $1,760.92 | $1,082.00 | $1,760.92 | -$322,826 |
| 420-7159 CL F CONC (BENT)(HPC) | 695.3 CY | $1,553.75 | $1,157.00 | $1,284.14 | -$275,860 |
| 6142-7001 PROCESS CONTROL SYSTEMS | 1 LS | $2,148,876.52 | $1,923,240.00 | $2,148,876.52 | -$225,637 |
Positive: the low bidder was cheaper on that item. These 20 items account for $4,092,727 of the $2,936,916 gap.
ARCHER WESTERN: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 10.9 STA | $861,170.00 | $6,072.92 | 141.80x | $9,320,558 |
| 500-7001 MOBILIZATION | 1 LS | $9,386,586.00 | $523,850.32 | 17.92x | $8,862,736 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $145,640.00 | $11,585.04 | 12.57x | $3,485,429 |
| 425-7006 PRESTR CONC GIRDER (TX62) | 4,338.91 LF | $866.82 | $189.94 | 4.56x | $2,936,926 |
| 423-7019 RETAINING WALL (DRILL SHAFT) (FASCIA) | 6,830 SF | $263.60 | $103.21 | 2.55x | $1,095,488 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $9,600,000.00 | $523,850.32 | 18.33x | $9,076,150 |
| 100-7002 PREPARING ROW | 10.9 STA | $823,850.00 | $6,072.92 | 135.66x | $8,913,770 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $170,000.00 | $11,585.04 | 14.67x | $4,118,789 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $2,500,000.00 | $136,676.66 | 18.29x | $2,363,323 |
| 4043-7001 ELECTRICAL SERVICE BUILDING | 1 LS | $2,500,000.00 | $385,926.46 | 6.48x | $2,114,074 |
| 6116-7001 ELECTRIC UNDERGROUND VAULT | 1 EA | $2,800,000.00 | $936,883.39 | 2.99x | $1,863,117 |
| 425-7060 TRENCH PANEL | 1,137.44 LF | $2,060.00 | $536.41 | 3.84x | $1,732,992 |
| 425-7006 PRESTR CONC GIRDER (TX62) | 4,338.91 LF | $489.00 | $189.94 | 2.57x | $1,297,599 |
| 5062-7001 FIRE STANDPIPE | 2,410 LF | $333.14 | $1,092.68 | 0.30x | -$1,830,491 |
WEBBER, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 10.9 STA | $928,486.00 | $6,072.92 | 152.89x | $10,054,303 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $390,727.00 | $11,585.04 | 33.73x | $9,857,691 |
| 500-7001 MOBILIZATION | 1 LS | $10,242,700.00 | $523,850.32 | 19.55x | $9,718,850 |
| 6141-7001 JET FAN ASSEMBLIES | 12 EA | $441,650.00 | $119,522.27 | 3.70x | $3,865,533 |
| 425-7006 PRESTR CONC GIRDER (TX62) | 4,338.91 LF | $820.00 | $189.94 | 4.32x | $2,733,778 |
| 425-7058 PRESTR CONC BOX BEAM (B54) | 2,157.43 LF | $2,200.00 | $1,204.68 | 1.83x | $2,147,333 |
| 425-7059 PRESTR CONC BOX BEAM (B78) | 1,523.45 LF | $2,500.00 | $1,296.04 | 1.93x | $1,834,173 |
HARPER BROTHERS CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $10,400,000.00 | $523,850.32 | 19.85x | $9,876,150 |
| 425-7006 PRESTR CONC GIRDER (TX62) | 4,338.91 LF | $925.00 | $189.94 | 4.87x | $3,189,364 |
| 100-7002 PREPARING ROW | 10.9 STA | $279,000.00 | $6,072.92 | 45.94x | $2,974,905 |
| 442-7007 STR STEEL (MISC NON-BRIDGE) | 73,355 LB | $50.25 | $11.11 | 4.52x | $2,871,012 |
| 6128-7003 FR CABLE & CONDUIT (RTRC 2-1/2") | 4,854 LF | $667.08 | $150.33 | 4.44x | $2,508,305 |
| 6142-7001 PROCESS CONTROL SYSTEMS | 1 LS | $3,987,250.00 | $2,148,876.52 | 1.86x | $1,838,373 |
| 6128-7002 FR CABLE & CONDUIT (RTRC 2") | 7,345 LF | $367.26 | $121.72 | 3.02x | $1,803,491 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $75,000.00 | $11,585.04 | 6.47x | $1,648,789 |
| 6117-7001 WALL MOUNTED ILLUMINATION FIXTURE | 462 EA | $5,565.00 | $2,461.83 | 2.26x | $1,433,665 |
| 423-7019 RETAINING WALL (DRILL SHAFT) (FASCIA) | 6,830 SF | $300.00 | $103.21 | 2.91x | $1,344,100 |
| 6137-7001 CONCRETE ENCASED DUCT BANK | 4,793 LF | $308.80 | $893.67 | 0.35x | -$2,803,282 |
| 6114-7001 LINEAR HEAT SENSING CABLE | 35,700 LF | $11.10 | $31.38 | 0.35x | -$723,996 |
| 6124-7001 SWITCHBOARD | 3 EA | $138,205.00 | $341,191.86 | 0.41x | -$608,961 |
BALFOUR BEATTY INFRASTRUCTURE, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 10.9 STA | $1,102,528.91 | $6,072.92 | 181.55x | $11,951,370 |
| 500-7001 MOBILIZATION | 1 LS | $12,017,565.14 | $523,850.32 | 22.94x | $11,493,715 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $246,610.00 | $11,585.04 | 21.29x | $6,110,649 |
| 425-7006 PRESTR CONC GIRDER (TX62) | 4,338.91 LF | $800.00 | $189.94 | 4.21x | $2,647,000 |
| 6128-7003 FR CABLE & CONDUIT (RTRC 2-1/2") | 4,854 LF | $633.73 | $150.33 | 4.22x | $2,346,424 |
| 425-7058 PRESTR CONC BOX BEAM (B54) | 2,157.43 LF | $2,200.00 | $1,204.68 | 1.83x | $2,147,333 |
| 6116-7001 ELECTRIC UNDERGROUND VAULT | 1 EA | $3,000,000.00 | $936,883.39 | 3.20x | $2,063,117 |
| 6128-7002 FR CABLE & CONDUIT (RTRC 2") | 7,345 LF | $348.90 | $121.72 | 2.87x | $1,668,637 |
| 4043-7001 ELECTRICAL SERVICE BUILDING | 1 LS | $2,000,000.00 | $385,926.46 | 5.18x | $1,614,074 |
| 6117-7001 WALL MOUNTED ILLUMINATION FIXTURE | 462 EA | $5,286.75 | $2,461.83 | 2.15x | $1,305,113 |
| 6137-7001 CONCRETE ENCASED DUCT BANK | 4,793 LF | $273.36 | $893.67 | 0.31x | -$2,973,146 |
| 6114-7001 LINEAR HEAT SENSING CABLE | 35,700 LF | $10.55 | $31.38 | 0.34x | -$743,631 |
| 6124-7001 SWITCHBOARD | 3 EA | $131,294.75 | $341,191.86 | 0.38x | -$629,691 |