VA: 0915-00-285: TCD
0915-00-285 · let Jun 2, 2026 · Bexar, San Antonio · Traffic Control Devices
$2,418,380Low bid: CENTERLINE TECHNOLOGIES, LLC-22.8% vs estimate $3,134,330
$249,804Left on the table10.3% gap to the second bid
9BiddersSpread 44% low to high
11Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CENTERLINE TECHNOLOGIES, LLC | $2,418,380 | -22.8% | $249,804 | 0 | 3-$624,900 | |
| 2 | L&L COMPANY | $2,668,183 | +10.3% | -14.9% | $4,500 | 0 | 3-$624,900 |
| 3 | STRIPE-A-ZONE, LLC | $2,672,684 | +10.5% | -14.7% | $243,259 | 0 | 3-$619,901 |
| 4 | VIZCAINO, L.P. | $2,915,943 | +20.6% | -7.0% | $2,973 | 0 | 3-$624,900 |
| 5 | TRP INFRASTRUCTURE SERVICES, LLC | $2,918,916 | +20.7% | -6.9% | $145,591 | 1+$106,316 | 2-$572,361 |
| 6 | STRIPE LINES, INC. | $3,064,507 | +26.7% | -2.2% | $190,038 | ||
| 7 | D. I. J. CONSTRUCTION, INC. | $3,254,544 | +34.6% | 3.8% | $3,694 | ||
| 8 | PAVEMENT MARKINGS INC. | $3,258,239 | +34.7% | 4.0% | $221,468 | ||
| 9 | INTERSTATE BARRICADES & MARKINGS, INC. | $3,479,706 | +43.9% | 11.0% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
CENTERLINE TECHNOLOGIES, LLC vs L&L COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 2,201,362 LF | $0.5400 | $0.6000 | $0.6515 | $132,082 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 1,637,513 LF | $0.5400 | $0.6000 | $0.6629 | $98,251 |
| 666-7274 RE PROFILE PM TY I(Y)6"(BRK)(100MIL) | 126,825 LF | $0.5500 | $0.6000 | $0.6738 | $6,341 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 211,880 LF | $0.4600 | $0.4800 | $0.4986 | $4,238 |
| 666-7024 REFL PAV MRK TY I (W)8"(SLD)(100MIL) | 66,257 LF | $0.7500 | $0.8000 | $0.9489 | $3,313 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 125,400 LF | $0.4600 | $0.4800 | $0.4757 | $2,508 |
| 666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL) | 100,400 LF | $0.4600 | $0.4800 | $0.5627 | $2,008 |
| 666-7420 REFL PAV MRK TY I (Y)6"(BRK)(100MIL) | 53,180 LF | $0.4600 | $0.4800 | $0.4829 | $1,064 |
| 505-7003 TMA (MOBILE OPERATION) | 138 DAY | $1.00 | $1.00 | $229.60 | $0 |
| 500-7001 MOBILIZATION | 1 LS | $1.00 | $1.00 | $523,850.32 | $0 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1.00 | $1.00 | $11,585.04 | $0 |
Positive: the low bidder was cheaper on that item. These 11 items account for $249,804 of the $249,804 gap.