FM 2090 Base Repair and Overlay
6499-84-001 · let Jun 10, 2026 · Liberty, Beaumont · Routine Maintenance Project - Sealed
$726,406Low bid: CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.+4.7% vs estimate $693,481
$145,395Left on the table20.0% gap to the second bid
3BiddersSpread 22% low to high
37Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | $726,406 | 4.7% | $145,395 | 1+$12,397 | 2-$484,105 | |
| 2 | FORDE CONSTRUCTION COMPANY, INC. | $871,802 | +20.0% | 25.7% | $17,362 | 6+$108,024 | 2-$483,605 |
| 3 | TEXAS MATERIALS GROUP, INC. | $889,163 | +22.4% | 28.2% | 10+$123,743 | 2-$464,005 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. vs FORDE CONSTRUCTION COMPANY, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7030 SP MIXES SP-C SAC-A PG76-22 | 2,198 TON | $142.70 | $160.00 | $138.38 | $38,025 |
| 530-7010 DRIVEWAYS (ACP) | 1,262 SY | $38.60 | $56.00 | $54.96 | $21,959 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 859 SY | $71.15 | $92.00 | $49.06 | $17,910 |
| 354-7083 PLANE ASPH CONC PAV (0" TO 2-1/2") | 1,288 SY | $3.10 | $14.00 | $2.98 | $14,039 |
| 666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL) | 10,470 LF | $0.7800 | $2.10 | $0.4886 | $13,820 |
| 134-7004 BACKFILL (TY A OR B) | 49 STA | $320.00 | $530.00 | $211.21 | $10,290 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 64 CY | $800.00 | $920.00 | $616.83 | $7,680 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $2,500.00 | $5,000.00 | $11,585.04 | $7,500 |
| 500-7001 MOBILIZATION | 1 LS | $67,000.00 | $60,000.00 | $523,850.32 | -$7,000 |
| 505-7001 TMA (STATIONARY) | 43 DAY | $275.00 | $170.00 | $217.57 | -$4,515 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 45 DAY | $75.00 | $170.00 | $87.82 | $4,275 |
| 530-7015 DRIVEWAYS (BASE) | 391 SY | $43.15 | $54.00 | $27.85 | $4,242 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 4,950 LF | $0.3200 | $1.00 | $0.2394 | $3,366 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 2,600 LF | $0.6000 | $1.80 | $0.2040 | $3,120 |
| 164-7005 BROADCAST SEED (TEMP_WARM) | 5,093 SY | $0.5000 | $1.00 | $0.1968 | $2,547 |
| 540-7005 MTL BEAM GD FEN TRANS (THRIE-BEAM) | 4 EA | $2,100.00 | $1,520.00 | $2,218.70 | -$2,320 |
| 354-7082 PLANE ASPH CONC PAV (2.5") | 1,525 SY | $10.80 | $12.00 | $2.67 | $1,830 |
| 540-7001 MTL W-BEAM GD FEN (TIM POST) | 1,300 LF | $22.75 | $24.00 | $25.60 | $1,625 |
| 505-7003 TMA (MOBILE OPERATION) | 2 DAY | $125.00 | $750.00 | $229.60 | $1,250 |
| 344-7077 TACK COAT | 1,600 GAL | $4.50 | $5.25 | $3.25 | $1,200 |
Positive: the low bidder was cheaper on that item. These 20 items account for $140,844 of the $145,395 gap.
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.: unbalanced items
Placed 1FORDE CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 859 SY | $92.00 | $49.06 | 1.88x | $36,881 |
| 666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL) | 10,470 LF | $2.10 | $0.4886 | 4.30x | $16,871 |
| 134-7004 BACKFILL (TY A OR B) | 49 STA | $530.00 | $211.21 | 2.51x | $15,621 |
| 354-7082 PLANE ASPH CONC PAV (2.5") | 1,525 SY | $12.00 | $2.67 | 4.49x | $14,227 |
| 354-7083 PLANE ASPH CONC PAV (0" TO 2-1/2") | 1,288 SY | $14.00 | $2.98 | 4.70x | $14,198 |
| 530-7015 DRIVEWAYS (BASE) | 391 SY | $54.00 | $27.85 | 1.94x | $10,226 |
| 500-7001 MOBILIZATION | 1 LS | $60,000.00 | $523,850.32 | 0.11x | -$463,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,000.00 | $11,585.04 | 0.43x | -$19,755 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 859 SY | $112.25 | $49.06 | 2.29x | $54,276 |
| 530-7015 DRIVEWAYS (BASE) | 391 SY | $63.50 | $27.85 | 2.28x | $13,940 |
| 134-7004 BACKFILL (TY A OR B) | 49 STA | $398.75 | $211.21 | 1.89x | $9,189 |
| 354-7083 PLANE ASPH CONC PAV (0" TO 2-1/2") | 1,288 SY | $9.75 | $2.98 | 3.28x | $8,724 |
| 505-7001 TMA (STATIONARY) | 43 DAY | $403.50 | $217.57 | 1.85x | $7,995 |
| 666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL) | 10,470 LF | $1.25 | $0.4886 | 2.56x | $7,972 |
| 666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL) | 8,195 LF | $1.25 | $0.5014 | 2.49x | $6,135 |
| 354-7082 PLANE ASPH CONC PAV (2.5") | 1,525 SY | $6.50 | $2.67 | 2.43x | $5,840 |
| 533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE) | 4,950 LF | $1.25 | $0.2394 | 5.22x | $5,002 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 2,600 LF | $2.00 | $0.2040 | 9.80x | $4,670 |
| 500-7001 MOBILIZATION | 1 LS | $88,000.00 | $523,850.32 | 0.17x | -$435,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $2,200.00 | $11,585.04 | 0.19x | -$28,155 |