SH 70 US 82
0105-06-023 · let Jun 3, 2026 · Dickens, Childress · Overlay
$4,016,029Low bid: A. L. HELMCAMP, INC.+7.6% vs estimate $3,732,460
$72,003Left on the table1.8% gap to the second bid
6BiddersSpread 24% low to high
41Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | A. L. HELMCAMP, INC. | $4,016,029 | 7.6% | $72,003 | 0 | 0 | |
| 2 | J. LEE MILLIGAN, INC. | $4,088,032 | +1.8% | 9.5% | $99,152 | 2+$122,451 | 0 |
| 3 | ZACK BURKETT CO. | $4,187,184 | +4.3% | 12.2% | $244,240 | 1+$32,796 | 2-$299,532 |
| 4 | DUININCK, INC. | $4,431,424 | +10.3% | 18.7% | $258,727 | 3+$100,071 | 0 |
| 5 | OVERLAND CORPORATION | $4,690,151 | +16.8% | 25.7% | $280,245 | 1+$45,260 | 0 |
| 6 | GILVIN-TERRILL, LTD. | $4,970,395 | +23.8% | 33.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
A. L. HELMCAMP, INC. vs J. LEE MILLIGAN, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 341-7053 D-GR HMA TY-D SAC-A PG70-28 | 20,174 TON | $154.00 | $136.40 | $133.62 | -$355,062 |
| 500-7001 MOBILIZATION | 1 LS | $280,000.00 | $439,000.00 | $523,850.32 | $159,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $8,700.00 | $35,000.00 | $11,585.04 | $105,200 |
| 134-7001 BACKFILL (TY A) | 356 STA | $145.00 | $310.00 | $224.26 | $58,740 |
| 168-7001 VEGETATIVE WATERING | 1,335 TGL | $10.00 | $30.00 | $8.43 | $26,700 |
| 341-7082 TACK COAT | 18,339 GAL | $3.90 | $5.00 | $3.93 | $20,173 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 4,356 SY | $3.25 | $6.00 | $2.13 | $11,979 |
| 505-7001 TMA (STATIONARY) | 65 DAY | $200.00 | $375.00 | $217.57 | $11,375 |
| 506-7045 BIODEG EROSN CONT LOGS (INSTL) (18") | 2,820 LF | $5.00 | $8.50 | $8.31 | $9,870 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 72,313 LF | $0.5500 | $0.6500 | $0.4757 | $7,231 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 43,930 LF | $0.5500 | $0.6500 | $0.4986 | $4,393 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 4,431 EA | $0.8000 | $1.50 | $0.5715 | $3,102 |
| 505-7003 TMA (MOBILE OPERATION) | 4 DAY | $150.00 | $895.00 | $229.60 | $2,980 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 72 CY | $100.00 | $75.00 | $16.96 | -$1,800 |
| 672-7004 REFL PAV MRKR TY II-A-A | 1,538 EA | $4.20 | $5.25 | $3.97 | $1,615 |
| 314-7009 EMULS ASPH (EROSN CONT)(SS-1H) | 15,857 GAL | $3.90 | $4.00 | $3.90 | $1,586 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 105 CY | $660.00 | $670.00 | $616.83 | $1,050 |
| 540-7002 MTL W-BEAM GD FEN (STEEL POST) | 750 LF | $35.00 | $36.00 | $30.74 | $750 |
| 540-7018 MTL W - BEAM GD FEN (LOW FILL CULVERT) | 150 LF | $80.00 | $85.00 | $90.29 | $750 |
| 533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR) | 68,576 LF | $0.2900 | $0.3000 | $0.2040 | $686 |
Positive: the low bidder was cheaper on that item. These 20 items account for $70,317 of the $72,003 gap.
J. LEE MILLIGAN, INC.: unbalanced items
Placed 2ZACK BURKETT CO.: unbalanced items
Placed 3DUININCK, INC.: unbalanced items
Placed 4OVERLAND CORPORATION: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $22,900.00 | $11,585.04 | 1.98x | $45,260 |