Lazy F RD(CR101)
0916-26-024 · let Jun 3, 2026 · Goliad, Corpus Christi · Bridge Replacement
$825,295Low bid: J. CARROLL WEAVER, INC.-36.1% vs estimate $1,292,158
$144,092Left on the table17.5% gap to the second bid
10BiddersSpread 68% low to high
58Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | J. CARROLL WEAVER, INC. | $825,295 | -36.1% | $144,092 | 8+$80,541 | 5-$614,721 | |
| 2 | ACME BRIDGE COMPANY, INC. | $969,387 | +17.5% | -25.0% | $85 | 4+$29,187 | 3-$539,370 |
| 3 | PRESIDIO CONTRACTING, LLC | $969,472 | +17.5% | -25.0% | $2,565 | 7+$70,296 | 2-$510,246 |
| 4 | LUCANIA CONTRACTORS LLC | $972,037 | +17.8% | -24.8% | $44,610 | 10+$92,851 | 3-$543,110 |
| 5 | C & W SOUTHERN LLC | $1,016,647 | +23.2% | -21.3% | $59,167 | 9+$154,454 | 3-$508,205 |
| 6 | TREVWAY, INC. | $1,075,813 | +30.4% | -16.7% | $3,516 | ||
| 7 | STX CIVIL | $1,079,330 | +30.8% | -16.5% | $6,564 | ||
| 8 | E-Z BEL CONSTRUCTION, LLC | $1,085,893 | +31.6% | -16.0% | $16,944 | ||
| 9 | CK NEWBERRY, LLC | $1,102,837 | +33.6% | -14.7% | $282,449 | ||
| 10 | FOREMOST PAVING, INC. | $1,385,286 | +67.9% | 7.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
J. CARROLL WEAVER, INC. vs ACME BRIDGE COMPANY, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 508-7001 CONSTRUCTING DETOURS | 960 SY | $26.97 | $115.00 | $83.58 | $84,509 |
| 422-7001 REINF CONC SLAB | 1,820 SF | $29.04 | $41.50 | $24.45 | $22,677 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $49,111.43 | $26,500.00 | $28,021.15 | -$22,611 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 224 CY | $132.27 | $232.00 | $179.97 | $22,340 |
| 425-7001 PRESTR CONC GIRDER (TX28) | 278 LF | $261.34 | $326.00 | $217.69 | $17,975 |
| 545-7006 CRASH CUSH ATTEN (INSTL)(L)(N)(TL3) | 4 EA | $30,651.45 | $35,100.00 | $26,188.60 | $17,794 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $545.00 | $7,690.00 | $9,253.78 | $14,290 |
| 552-7003 WIRE FENCE (TY C) | 1,024 LF | $10.90 | $21.20 | $12.12 | $10,547 |
| 403-7001 TEMPORARY SPL SHORING | 252 SF | $59.95 | $21.20 | $25.56 | -$9,765 |
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $83,200.00 | $523,850.32 | $8,200 |
| 400-7010 CEM STABIL BKFL | 38 CY | $152.45 | $349.00 | $138.14 | $7,469 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 495 CY | $45.53 | $30.90 | $13.19 | -$7,242 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 2,290 SY | $3.65 | $1.50 | $1.43 | -$4,924 |
| 316-7209 AGGR (TY-PB, GR-3 OR 3S)(SAC-B) | 12 CY | $875.12 | $523.00 | $88.78 | -$4,225 |
| 512-7057 PORT CTB (REMOVE)(LOW PROF)(TY 1) | 240 LF | $44.59 | $27.10 | $11.18 | -$4,198 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 1,200 LF | $6.54 | $3.20 | $0.2770 | -$4,008 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 240 LF | $44.59 | $27.90 | $43.56 | -$4,006 |
| 506-7011 ROCK FILTER DAMS (REMOVE) | 60 LF | $80.50 | $13.90 | $12.47 | -$3,996 |
| 110-7002 EXCAV (CHANNEL) | 157 CY | $9.09 | $33.30 | $16.69 | $3,801 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 19 LF | $218.00 | $26.60 | $13.72 | -$3,637 |
Positive: the low bidder was cheaper on that item. These 20 items account for $140,991 of the $144,092 gap.
J. CARROLL WEAVER, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $49,111.43 | $28,021.15 | 1.75x | $21,090 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 495 CY | $45.53 | $13.19 | 3.45x | $16,007 |
| 316-7209 AGGR (TY-PB, GR-3 OR 3S)(SAC-B) | 12 CY | $875.12 | $88.78 | 9.86x | $9,436 |
| 403-7001 TEMPORARY SPL SHORING | 252 SF | $59.95 | $25.56 | 2.35x | $8,666 |
| 512-7057 PORT CTB (REMOVE)(LOW PROF)(TY 1) | 240 LF | $44.59 | $11.18 | 3.99x | $8,017 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 1,200 LF | $6.54 | $0.2770 | 23.61x | $7,516 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 2,290 SY | $3.65 | $1.43 | 2.55x | $5,085 |
| 105-7001 RMV (0"-4") TRT/UNTRT BASE & ASPH PAV | 726 SY | $9.09 | $2.58 | 3.52x | $4,723 |
| 500-7001 MOBILIZATION | 1 LS | $75,000.00 | $523,850.32 | 0.14x | -$448,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $2,180.00 | $11,585.04 | 0.19x | -$84,645 |
| 508-7001 CONSTRUCTING DETOURS | 960 SY | $26.97 | $83.58 | 0.32x | -$54,350 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $545.00 | $9,253.78 | 0.06x | -$17,418 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $59.95 | $217.57 | 0.28x | -$9,457 |
ACME BRIDGE COMPANY, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7006 EMBANK (FNL)(DC)(TY C) | 495 CY | $30.90 | $13.19 | 2.34x | $8,766 |
| 400-7010 CEM STABIL BKFL | 38 CY | $349.00 | $138.14 | 2.53x | $8,013 |
| 105-7001 RMV (0"-4") TRT/UNTRT BASE & ASPH PAV | 726 SY | $12.50 | $2.58 | 4.84x | $7,199 |
| 316-7209 AGGR (TY-PB, GR-3 OR 3S)(SAC-B) | 12 CY | $523.00 | $88.78 | 5.89x | $5,211 |
| 500-7001 MOBILIZATION | 1 LS | $83,200.00 | $523,850.32 | 0.16x | -$440,650 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $2,000.00 | $11,585.04 | 0.17x | -$86,265 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $10.00 | $217.57 | 0.05x | -$12,454 |
PRESIDIO CONTRACTING, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7001 PREPARING ROW | 0.34 AC | $62,800.00 | $3,995.94 | 15.72x | $19,993 |
| 316-7209 AGGR (TY-PB, GR-3 OR 3S)(SAC-B) | 12 CY | $1,010.00 | $88.78 | 11.38x | $11,055 |
| 316-7212 AGGR (TY-PB, GR-4S OR 4)(SAC-B) | 10 CY | $1,190.00 | $125.13 | 9.51x | $10,649 |
| 506-7021 CONSTRUCTION EXITS (INSTALL) (TY 2) | 156 SY | $86.90 | $26.75 | 3.25x | $9,383 |
| 400-7010 CEM STABIL BKFL | 38 CY | $350.00 | $138.14 | 2.53x | $8,051 |
| 403-7001 TEMPORARY SPL SHORING | 252 SF | $50.00 | $25.56 | 1.96x | $6,159 |
| 316-7070 ASPH(AC-15P, HFRS-2P OR CRS-2P) | 411 GAL | $15.50 | $3.32 | 4.67x | $5,007 |
| 500-7001 MOBILIZATION | 1 LS | $96,000.00 | $523,850.32 | 0.18x | -$427,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $2,430.00 | $11,585.04 | 0.21x | -$82,395 |
LUCANIA CONTRACTORS LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 403-7001 TEMPORARY SPL SHORING | 252 SF | $100.00 | $25.56 | 3.91x | $18,759 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 240 LF | $90.00 | $43.56 | 2.07x | $11,145 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 2,290 SY | $6.00 | $1.43 | 4.20x | $10,467 |
| 100-7001 PREPARING ROW | 0.34 AC | $30,000.00 | $3,995.94 | 7.51x | $8,841 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 1,200 LF | $7.50 | $0.2770 | 27.08x | $8,668 |
| 100-7010 PREP ROW (TREE PRUNE AND TRIM) | 4.7 STA | $3,000.00 | $1,185.58 | 2.53x | $8,528 |
| 132-7006 EMBANK (FNL)(DC)(TY C) | 495 CY | $30.00 | $13.19 | 2.27x | $8,320 |
| 506-7021 CONSTRUCTION EXITS (INSTALL) (TY 2) | 156 SY | $70.00 | $26.75 | 2.62x | $6,747 |
| 100-7004 PREP ROW (TREE REMOVE) (12"-24" DIA) | 9 EA | $1,500.00 | $834.16 | 1.80x | $5,993 |
| 105-7001 RMV (0"-4") TRT/UNTRT BASE & ASPH PAV | 726 SY | $10.00 | $2.58 | 3.87x | $5,384 |
| 500-7001 MOBILIZATION | 1 LS | $93,500.00 | $523,850.32 | 0.18x | -$430,350 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $500.00 | $11,585.04 | 0.04x | -$99,765 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $1.00 | $217.57 | 0.00x | -$12,994 |
C & W SOUTHERN LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 508-7001 CONSTRUCTING DETOURS | 960 SY | $160.00 | $83.58 | 1.91x | $73,358 |
| 403-7001 TEMPORARY SPL SHORING | 252 SF | $100.00 | $25.56 | 3.91x | $18,759 |
| 316-7209 AGGR (TY-PB, GR-3 OR 3S)(SAC-B) | 12 CY | $1,310.00 | $88.78 | 14.76x | $14,655 |
| 316-7212 AGGR (TY-PB, GR-4S OR 4)(SAC-B) | 10 CY | $1,572.00 | $125.13 | 12.56x | $14,469 |
| 100-7001 PREPARING ROW | 0.34 AC | $30,000.00 | $3,995.94 | 7.51x | $8,841 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 1,200 LF | $6.00 | $0.2770 | 21.66x | $6,868 |
| 169-7006 SOIL RET BLKT(SL_STEEP_CLAY_LONG) | 495 SY | $15.00 | $1.40 | 10.70x | $6,731 |
| 400-7010 CEM STABIL BKFL | 38 CY | $280.00 | $138.14 | 2.03x | $5,391 |
| 105-7001 RMV (0"-4") TRT/UNTRT BASE & ASPH PAV | 726 SY | $10.00 | $2.58 | 3.87x | $5,384 |
| 500-7001 MOBILIZATION | 1 LS | $120,000.00 | $523,850.32 | 0.23x | -$403,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $800.00 | $11,585.04 | 0.07x | -$97,065 |
| 552-7003 WIRE FENCE (TY C) | 1,024 LF | $5.00 | $12.12 | 0.41x | -$7,289 |