SH 174; Wicker Hill to Elk Dr
0019-01-146 · let Jun 2, 2026 · Johnson, Fort Worth · Widen Non-Freeway
$19,812,334Low bid: REYES TX, INC.-1.2% vs estimate $20,058,072
$326,998Left on the table1.7% gap to the second bid
8BiddersSpread 23% low to high
208Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | REYES TX, INC. | $19,812,334 | -1.2% | $326,998 | 10+$3,683,071 | 2-$363,956 | |
| 2 | JAY MILLS CONTRACTING, INCORPORATED | $20,139,332 | +1.7% | 0.4% | $391,620 | 6+$2,788,055 | 2-$319,699 |
| 3 | FOUTSCO PAVING COMPANY, LLC | $20,530,953 | +3.6% | 2.4% | $524,678 | 7+$3,471,103 | 3-$501,341 |
| 4 | RAGLE CONSTRUCTION, INC. | $21,055,631 | +6.3% | 5.0% | $753,135 | 6+$5,317,203 | 2-$408,175 |
| 5 | OVERLAND CORPORATION | $21,808,766 | +10.1% | 8.7% | $26,639 | 8+$3,977,768 | 1-$228,280 |
| 6 | TEXAS MATERIALS GROUP, INC. | $21,835,404 | +10.2% | 8.9% | $952,012 | ||
| 7 | ED BELL CONSTRUCTION COMPANY | $22,787,417 | +15.0% | 13.6% | $1,650,525 | ||
| 8 | COPASA INC | $24,437,942 | +23.3% | 21.8% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
REYES TX, INC. vs JAY MILLS CONTRACTING, INCORPORATED, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 105 STA | $14,147.81 | $5,000.00 | $6,072.92 | -$960,520 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 16,880 LF | $36.00 | $80.00 | $43.56 | $742,720 |
| 505-7003 TMA (MOBILE OPERATION) | 230 DAY | $2,610.00 | $400.00 | $229.60 | -$508,300 |
| 465-7195 INLET (COMPL)(CU)(20 FT)(FTW) | 6 EA | $71,020.00 | $16,000.00 | $52,346.67 | -$330,120 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 3,685 SY | $16.00 | $94.00 | $60.19 | $287,430 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $3,850.00 | $12,000.00 | $11,585.04 | $211,900 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 19,200 CY | $28.00 | $18.00 | $16.96 | -$192,000 |
| 442-7008 STR STEEL (MISCELLANEOUS BRIDGE) | 112 LB | $1,760.00 | $56.00 | $6.21 | -$190,848 |
| 110-7001 EXCAV (ROADWAY) | 14,600 CY | $11.00 | $23.50 | $11.68 | $182,500 |
| 500-7001 MOBILIZATION | 1 LS | $1,826,000.00 | $2,000,000.00 | $523,850.32 | $174,000 |
| 530-7006 DRIVEWAYS (CONC) | 3,488 SY | $85.00 | $133.00 | $109.20 | $167,424 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 22,530 SY | $2.80 | $9.75 | $3.93 | $156,584 |
| 464-7009 RC PIPE (CL III)(36 IN) | 908 LF | $359.00 | $190.00 | $183.45 | -$153,452 |
| 344-7024 SP MIXES SP-C SAC-A PG70-28 | 13,905 TON | $165.00 | $176.00 | $156.36 | $152,955 |
| 247-7113 FL BS (CMP IN PLC)(TY A GR 1-2) (12") | 38,230 SY | $23.00 | $27.00 | $34.64 | $152,920 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 55,957 SY | $3.30 | $6.00 | $1.43 | $151,084 |
| 344-7077 TACK COAT | 18,861 GAL | $7.50 | $0.0100 | $3.25 | -$141,269 |
| 275-7001 CEMENT | 490 TON | $499.00 | $250.00 | $224.93 | -$122,010 |
| 464-7005 RC PIPE (CL III)(24 IN) | 816 LF | $261.00 | $126.00 | $108.34 | -$110,160 |
| 344-7055 SP MIXES SP-D SAC-B PG70-22 (LEVEL-UP) | 3,600 TON | $147.00 | $176.00 | $145.60 | $104,400 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$224,763 of the $326,998 gap.
REYES TX, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,826,000.00 | $523,850.32 | 3.49x | $1,302,150 |
| 100-7002 PREPARING ROW | 105 STA | $14,147.81 | $6,072.92 | 2.33x | $847,863 |
| 505-7003 TMA (MOBILE OPERATION) | 230 DAY | $2,610.00 | $229.60 | 11.37x | $547,493 |
| 442-7008 STR STEEL (MISCELLANEOUS BRIDGE) | 112 LB | $1,760.00 | $6.21 | 283.26x | $196,424 |
| 464-7009 RC PIPE (CL III)(36 IN) | 908 LF | $359.00 | $183.45 | 1.96x | $159,403 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 4 EA | $47,420.00 | $8,031.16 | 5.90x | $157,555 |
| 275-7001 CEMENT | 490 TON | $499.00 | $224.93 | 2.22x | $134,292 |
| 464-7005 RC PIPE (CL III)(24 IN) | 816 LF | $261.00 | $108.34 | 2.41x | $124,573 |
| 420-7023 CL C CONC (CAP)(HPC) | 8 CY | $15,000.00 | $1,420.15 | 10.56x | $108,639 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 55,957 SY | $3.30 | $1.43 | 2.31x | $104,679 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $3,850.00 | $11,585.04 | 0.33x | -$201,111 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 3,685 SY | $16.00 | $60.19 | 0.27x | -$162,845 |
JAY MILLS CONTRACTING, INCORPORATED: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,000,000.00 | $523,850.32 | 3.82x | $1,476,150 |
| 512-7009 PORT CTB (FUR & INST)(LOW PROF)(TY 1) | 16,880 LF | $80.00 | $43.56 | 1.84x | $615,094 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 55,957 SY | $6.00 | $1.43 | 4.20x | $255,763 |
| 110-7001 EXCAV (ROADWAY) | 14,600 CY | $23.50 | $11.68 | 2.01x | $172,540 |
| 530-7010 DRIVEWAYS (ACP) | 842 SY | $218.00 | $54.96 | 3.97x | $137,283 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 22,530 SY | $9.75 | $3.93 | 2.48x | $131,226 |
| 465-7195 INLET (COMPL)(CU)(20 FT)(FTW) | 6 EA | $16,000.00 | $52,346.67 | 0.31x | -$218,080 |
| 6008-7001 RVDS (PRESENCE DETECTION ONLY) | 15 EA | $1,955.00 | $8,729.59 | 0.22x | -$101,619 |
FOUTSCO PAVING COMPANY, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $76,000.00 | $11,585.04 | 6.56x | $1,674,789 |
| 500-7001 MOBILIZATION | 1 LS | $1,200,000.00 | $523,850.32 | 2.29x | $676,150 |
| 100-7002 PREPARING ROW | 105 STA | $12,000.00 | $6,072.92 | 1.98x | $622,343 |
| 110-7001 EXCAV (ROADWAY) | 14,600 CY | $22.00 | $11.68 | 1.88x | $150,640 |
| 527-7001 COLORED TEXTURED CONC (4") | 1,440 SY | $185.00 | $92.06 | 2.01x | $133,836 |
| 275-7001 CEMENT | 490 TON | $450.00 | $224.93 | 2.00x | $110,282 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 22,530 SY | $8.50 | $3.93 | 2.17x | $103,063 |
| 465-7195 INLET (COMPL)(CU)(20 FT)(FTW) | 6 EA | $12,000.00 | $52,346.67 | 0.23x | -$242,080 |
| 354-7032 PLANE ASPH CONC PAV(0" TO 2") | 122,085 SY | $1.00 | $2.13 | 0.47x | -$137,980 |
| 505-7001 TMA (STATIONARY) | 560 DAY | $1.00 | $217.57 | 0.00x | -$121,280 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,200,000.00 | $523,850.32 | 4.20x | $1,676,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $72,400.00 | $11,585.04 | 6.25x | $1,581,189 |
| 100-7002 PREPARING ROW | 105 STA | $19,000.00 | $6,072.92 | 3.13x | $1,357,343 |
| 110-7001 EXCAV (ROADWAY) | 14,600 CY | $29.00 | $11.68 | 2.48x | $252,840 |
| 351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8") | 3,685 SY | $128.00 | $60.19 | 2.13x | $249,875 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 55,957 SY | $5.00 | $1.43 | 3.50x | $199,806 |
| 465-7195 INLET (COMPL)(CU)(20 FT)(FTW) | 6 EA | $13,000.00 | $52,346.67 | 0.25x | -$236,080 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 19,200 CY | $8.00 | $16.96 | 0.47x | -$172,095 |
OVERLAND CORPORATION: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $2,154,759.00 | $523,850.32 | 4.11x | $1,630,909 |
| 100-7002 PREPARING ROW | 105 STA | $17,900.00 | $6,072.92 | 2.95x | $1,241,843 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 26 MO | $25,000.00 | $11,585.04 | 2.16x | $348,789 |
| 110-7001 EXCAV (ROADWAY) | 14,600 CY | $25.00 | $11.68 | 2.14x | $194,440 |
| 505-7001 TMA (STATIONARY) | 560 DAY | $502.00 | $217.57 | 2.31x | $159,280 |
| 505-7003 TMA (MOBILE OPERATION) | 230 DAY | $900.00 | $229.60 | 3.92x | $154,193 |
| 508-7001 CONSTRUCTING DETOURS | 1,193 SY | $200.00 | $83.58 | 2.39x | $138,883 |
| 680-7011 INSTALL HWY TRF SIG (UPGRADE) | 4 EA | $35,389.00 | $8,031.16 | 4.41x | $109,431 |
| 465-7195 INLET (COMPL)(CU)(20 FT)(FTW) | 6 EA | $14,300.00 | $52,346.67 | 0.27x | -$228,280 |