Bid Tab X-ray: 6468-45-001

Jun 3, 2026 · Potter Sign up free
Set your company to personalize scores

BPM FY 2027

6468-45-001 · let Jun 3, 2026 · Potter, Amarillo · Bridge Preventative Maintenance - Sealed

$1,256,310Low bid: GIBSON & ASSOCIATES, INC.-27.0% vs estimate $1,720,012
$128,603Left on the table10.2% gap to the second bid
10BiddersSpread 39% low to high
29Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1GIBSON & ASSOCIATES, INC. $1,256,310-27.0% $128,603 6+$127,172 3-$433,898
2RAGLE CONSTRUCTION, INC. $1,384,913+10.2%-19.5% $3,905 7+$452,732 2-$426,068
3PATHFIELD INVESTMENTS LLC $1,388,818+10.5%-19.3% $86,288 7+$175,619 2-$411,101
4BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC $1,475,106+17.4%-14.2% $48,417 9+$298,069 1-$448,850
5THE TRUESDELL CORPORATION $1,523,523+21.3%-11.4% $107,072 6+$113,900 1-$12,116
6CROSS PLUS CONSTRUCTION, LLC $1,630,595+29.8%-5.2% $5,444
7REAR CONTRACTORS LLC $1,636,039+30.2%-4.9% $71,093
8BLACKSMITH VENTURES LLC $1,707,132+35.9%-0.7% $10,585
9TI-ZACK CONCRETE, LLC $1,717,717+36.7%-0.1% $28,405
10PBX BRIDGE COMPANY $1,746,122+39.0%1.5%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

GIBSON & ASSOCIATES, INC. vs RAGLE CONSTRUCTION, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
502-7004 BARRICADES, SIGNS AND TRAFFIC HANDLING11 EA $6,700.00$35,000.00$3,068.24 $311,300
439-7014 MULTI-LAYER POLYMER OVERLAY14,605 SY $37.00$30.00$40.32 -$102,235
429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD)662 SF $217.00$125.00$150.68 -$60,904
483-7016 SHOT BLASTING14,605 SY $6.50$2.50$5.25 -$58,420
500-7001 MOBILIZATION1 LS $114,500.00$138,000.00$523,850.32 $23,500
438-7008 CLEANING EXISTING JOINTS760 LF $5.00$30.00$16.75 $19,000
438-7007 CLEANING AND SEALING EXIST JOINTS (CL7)446 LF $67.00$30.00$38.57 -$16,502
788-7001 CONCRETE BEAM REPAIR5 EA $1,500.00$4,500.00$4,623.25 $15,000
2005-7001 TIED-CONCRETE BLOCK EROSION CONTROL MAT225 SF $40.00$100.00$14.65 $13,500
427-7005 EPOXY WATERPROOF FINISH (TY X)6,454 SF $8.80$7.40$9.61 -$9,036
429-7002 CONC STR REPAIR (EPOXY MORTAR)256 SF $97.00$125.00$151.82 $7,168
788-7002 CONCRETE BEAM REPAIR (CFRP)2 EA $4,275.00$7,500.00$6,492.05 $6,450
132-7001 EMBANK (FNL)(OC)(TY A)46 CY $170.00$90.00$22.62 -$3,680
540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION4 EA $1,650.00$2,500.00$1,297.32 $3,400
429-7003 CONC STR REPAIR(DECK REP(PART DEPTH))107 SF $102.00$75.00$95.74 -$2,889
401-7001 FLOWABLE BACKFILL5 CY $1,200.00$650.00$298.77 -$2,750
666-7347 PAVEMENT SLER 6"12,329 LF $2.20$2.00$0.1841 -$2,466
677-7002 ELIM EXT PM & MRKS (6")7,516 LF $3.30$3.00$0.2755 -$2,255
666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL)6,694 LF $3.30$3.00$0.4886 -$2,008
662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W1,899 EA $2.00$1.00$1.03 -$1,899

Positive: the low bidder was cheaper on that item. These 20 items account for $134,275 of the $128,603 gap.

GIBSON & ASSOCIATES, INC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
502-7004 BARRICADES, SIGNS AND TRAFFIC HANDLING11 EA $6,700.00$3,068.242.18x$39,949
666-7347 PAVEMENT SLER 6"12,329 LF $2.20$0.184111.95x$24,854
677-7002 ELIM EXT PM & MRKS (6")7,516 LF $3.30$0.275511.98x$22,732
666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL)6,694 LF $3.30$0.48866.75x$18,820
666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL)5,016 LF $3.30$0.50146.58x$14,038
132-7001 EMBANK (FNL)(OC)(TY A)46 CY $170.00$22.627.52x$6,780
500-7001 MOBILIZATION1 LS $114,500.00$523,850.320.22x-$409,350
788-7001 CONCRETE BEAM REPAIR5 EA $1,500.00$4,623.250.32x-$15,616
438-7008 CLEANING EXISTING JOINTS760 LF $5.00$16.750.30x-$8,931

RAGLE CONSTRUCTION, INC.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
502-7004 BARRICADES, SIGNS AND TRAFFIC HANDLING11 EA $35,000.00$3,068.2411.41x$351,249
666-7347 PAVEMENT SLER 6"12,329 LF $2.00$0.184110.86x$22,388
677-7002 ELIM EXT PM & MRKS (6")7,516 LF $3.00$0.275510.89x$20,477
2005-7001 TIED-CONCRETE BLOCK EROSION CONTROL MAT225 SF $100.00$14.656.83x$19,204
666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL)6,694 LF $3.00$0.48866.14x$16,811
666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL)5,016 LF $3.00$0.50145.98x$12,533
438-7008 CLEANING EXISTING JOINTS760 LF $30.00$16.751.79x$10,069
500-7001 MOBILIZATION1 LS $138,000.00$523,850.320.26x-$385,850
483-7016 SHOT BLASTING14,605 SY $2.50$5.250.48x-$40,218

PATHFIELD INVESTMENTS LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
483-7016 SHOT BLASTING14,605 SY $10.00$5.251.90x$69,320
2005-7001 TIED-CONCRETE BLOCK EROSION CONTROL MAT225 SF $160.00$14.6510.92x$32,704
438-7007 CLEANING AND SEALING EXIST JOINTS (CL7)446 LF $80.00$38.572.07x$18,477
438-7008 CLEANING EXISTING JOINTS760 LF $40.00$16.752.39x$17,669
666-7347 PAVEMENT SLER 6"12,329 LF $1.50$0.18418.15x$16,224
429-7003 CONC STR REPAIR(DECK REP(PART DEPTH))107 SF $220.00$95.742.30x$13,295
132-7001 EMBANK (FNL)(OC)(TY A)46 CY $195.00$22.628.62x$7,930
500-7001 MOBILIZATION1 LS $130,000.00$523,850.320.25x-$393,850
502-7004 BARRICADES, SIGNS AND TRAFFIC HANDLING11 EA $1,500.00$3,068.240.49x-$17,251

BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD)662 SF $300.00$150.681.99x$98,850
438-7008 CLEANING EXISTING JOINTS760 LF $75.00$16.754.48x$44,269
429-7002 CONC STR REPAIR (EPOXY MORTAR)256 SF $275.00$151.821.81x$31,535
666-7347 PAVEMENT SLER 6"12,329 LF $2.50$0.184113.58x$28,553
677-7002 ELIM EXT PM & MRKS (6")7,516 LF $3.50$0.275512.70x$24,235
666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL)6,694 LF $3.50$0.48867.16x$20,158
429-7003 CONC STR REPAIR(DECK REP(PART DEPTH))107 SF $275.00$95.742.87x$19,180
438-7007 CLEANING AND SEALING EXIST JOINTS (CL7)446 LF $75.00$38.571.94x$16,247
666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL)5,016 LF $3.50$0.50146.98x$15,041
500-7001 MOBILIZATION1 LS $75,000.00$523,850.320.14x-$448,850

THE TRUESDELL CORPORATION: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
502-7004 BARRICADES, SIGNS AND TRAFFIC HANDLING11 EA $5,500.00$3,068.241.79x$26,749
666-7347 PAVEMENT SLER 6"12,329 LF $2.20$0.184111.95x$24,854
677-7002 ELIM EXT PM & MRKS (6")7,516 LF $3.20$0.275511.62x$21,981
666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL)6,694 LF $3.20$0.48866.55x$18,150
666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL)5,016 LF $3.20$0.50146.38x$13,536
2005-7001 TIED-CONCRETE BLOCK EROSION CONTROL MAT225 SF $53.00$14.653.62x$8,629
788-7001 CONCRETE BEAM REPAIR5 EA $2,200.00$4,623.250.48x-$12,116