FM 1640: SS 529 to W of FM 2218
1683-01-040 · let Jun 3, 2026 · Fort Bend, Houston · Overlay
$3,065,936Low bid: DURWOOD GREENE CONSTRUCTION CO.+7.2% vs estimate $2,859,279
$331,833Left on the table10.8% gap to the second bid
5BiddersSpread 18% low to high
69Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DURWOOD GREENE CONSTRUCTION CO. | $3,065,936 | 7.2% | $331,833 | 0 | 2-$474,276 | |
| 2 | CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | $3,397,769 | +10.8% | 18.8% | $34,551 | 0 | 2-$359,276 |
| 3 | ENVIRONMENTAL ALLIES, INC. | $3,432,320 | +12.0% | 20.0% | $173,228 | 1+$25,537 | 1-$423,741 |
| 4 | HAYDEN PAVING, INC. | $3,605,548 | +17.6% | 26.1% | $15,081 | 2+$106,772 | 1-$464,050 |
| 5 | TEXAS MATERIALS GROUP, INC. | $3,620,628 | +18.1% | 26.6% | 1+$29,974 | 2-$467,372 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
DURWOOD GREENE CONSTRUCTION CO. vs CORNERSTONE PAVING AND CONSTRUCTION, L.L.C., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 351-7009 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") | 5,227 SY | $40.00 | $85.40 | $77.78 | $237,306 |
| 500-7001 MOBILIZATION | 1 LS | $85,000.00 | $200,000.00 | $523,850.32 | $115,000 |
| 341-7057 D-GR HMA TY-D SAC-A PG76-22 | 13,447 TON | $158.00 | $151.60 | $175.66 | -$86,061 |
| 351-7011 FLEXIBLE PAVEMENT STRUCTURE REPAIR(12") | 640 SY | $65.00 | $135.00 | $98.88 | $44,800 |
| 354-7051 PLANE ASPH CONC PAV(2") | 122,259 SY | $2.50 | $2.73 | $1.86 | $28,120 |
| 341-7082 TACK COAT | 11,427 GAL | $2.00 | $4.00 | $3.93 | $22,854 |
| 505-7001 TMA (STATIONARY) | 54 DAY | $350.00 | $125.00 | $217.57 | -$12,150 |
| 505-7003 TMA (MOBILE OPERATION) | 40 DAY | $250.00 | $50.00 | $229.60 | -$8,000 |
| 316-7007 ASPH (AC-20-5TR) | 6,612 GAL | $4.25 | $5.40 | $3.27 | $7,604 |
| 666-7036 REFL PAV MRK TY I (W)24"(SLD)(100MIL) | 3,020 LF | $7.00 | $6.00 | $7.19 | -$3,020 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,774 EA | $1.50 | $1.00 | $0.5715 | -$1,387 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 4,142 EA | $1.50 | $1.20 | $1.03 | -$1,243 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 44 EA | $250.00 | $225.00 | $201.69 | -$1,100 |
| 666-7315 ALL-WTHER PM TY I (Y)6"(SLD)(100MIL) | 25,121 LF | $0.8500 | $0.8100 | $0.6819 | -$1,005 |
| 666-7024 REFL PAV MRK TY I (W)8"(SLD)(100MIL) | 1,976 LF | $1.50 | $1.00 | $0.9489 | -$988 |
| 668-7093 PREFAB PM TY C (W)(DBL ARROW) | 24 EA | $300.00 | $265.00 | $314.80 | -$840 |
| 662-7017 WK ZN PAV MRK NON-REMOV (W)24"(SLD) | 3,020 LF | $4.00 | $3.75 | $3.95 | -$755 |
| 662-7019 WK ZN PAV MRK NON-REMOV (W)(DBL ARW) | 24 EA | $120.00 | $95.00 | $106.79 | -$600 |
| 662-7038 WK ZN PAV MRK NON-REMOV (Y)6"(SLD) | 25,122 LF | $0.3200 | $0.3000 | $0.2770 | -$502 |
| 666-7310 ALL-WTHER PM TY I (W)6"(BRK)(100MIL) | 11,460 LF | $0.8500 | $0.8100 | $0.8630 | -$458 |
Positive: the low bidder was cheaper on that item. These 20 items account for $337,574 of the $331,833 gap.