Non-IH Pavement Markings (2026)
0906-00-264 · let Jul 1, 2026 · Ector, Odessa · Traffic Control Devices
$5,487,908Low bid: VIZCAINO, L.P.-17.2% vs estimate $6,626,989
$360,417Left on the table6.6% gap to the second bid
8BiddersSpread 40% low to high
29Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | VIZCAINO, L.P. | $5,487,908 | -17.2% | $360,417 | 0 | 5-$923,866 | |
| 2 | CENTERLINE TECHNOLOGIES, LLC | $5,848,324 | +6.6% | -11.7% | $215,968 | 0 | 3-$666,510 |
| 3 | FC TRAFFIC CONTROL, LLC | $6,064,293 | +10.5% | -8.5% | $169,839 | 0 | 1-$423,850 |
| 4 | L&L COMPANY | $6,234,132 | +13.6% | -5.9% | $463,755 | 0 | 3-$666,510 |
| 5 | STRIPE-A-ZONE, LLC | $6,697,887 | +22.0% | 1.1% | $426,324 | 0 | 3-$640,620 |
| 6 | TRP INFRASTRUCTURE SERVICES, LLC | $7,124,210 | +29.8% | 7.5% | $474,841 | ||
| 7 | PMI PAVEMENT MARKING, LLC | $7,599,052 | +38.5% | 14.7% | $62,879 | ||
| 8 | STRIPE LINES, INC. | $7,661,931 | +39.6% | 15.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
VIZCAINO, L.P. vs CENTERLINE TECHNOLOGIES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $750,000.00 | $1.00 | $523,850.32 | -$749,999 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 156,843 LF | $0.0350 | $3.90 | $2.80 | $606,198 |
| 666-7265 RE PROFILE PM TY I(W)6"(SLD)(090MIL) | 2,393,396 LF | $0.3500 | $0.5800 | $0.5887 | $550,481 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 2,132,246 LF | $0.7000 | $0.5800 | $0.6515 | -$255,870 |
| 666-7269 RE PROFILE PM TY I(Y)6"(SLD)(090MIL) | 1,035,086 LF | $0.3500 | $0.5800 | $0.6020 | $238,070 |
| 672-7004 REFL PAV MRKR TY II-A-A | 58,298 EA | $0.0400 | $4.00 | $3.97 | $230,860 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 752,675 LF | $0.6600 | $0.4200 | $0.4757 | -$180,642 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 603,292 LF | $0.6600 | $0.4200 | $0.4986 | -$144,790 |
| 666-7273 RE PROFILE PM TY I(Y)6"(BRK)(090MIL) | 256,350 LF | $0.0540 | $0.5800 | $0.5289 | $134,840 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 586,314 LF | $0.7000 | $0.5800 | $0.6629 | -$70,358 |
| 666-7408 REFL PAV MRK TY I (W)6"(BRK)(100MIL) | 124,174 LF | $0.6600 | $0.4200 | $0.5627 | -$29,802 |
| 666-7407 REFL PAV MRK TY I (W)6"(BRK)(090MIL) | 116,170 LF | $0.6600 | $0.4200 | $0.5397 | -$27,881 |
| 666-7274 RE PROFILE PM TY I(Y)6"(BRK)(100MIL) | 231,960 LF | $0.7000 | $0.5800 | $0.6738 | -$27,835 |
| 666-7410 REFL PAV MRK TY I (W)6"(SLD)(090MIL) | 336,886 LF | $0.3500 | $0.4200 | $0.4886 | $23,582 |
| 666-7422 REFL PAV MRK TY I (Y)6"(SLD)(090MIL) | 336,886 LF | $0.3500 | $0.4200 | $0.5014 | $23,582 |
| 672-7006 REFL PAV MRKR TY II-C-R | 5,560 EA | $0.0400 | $4.00 | $4.19 | $22,018 |
| 668-7091 PREFAB PM TY C (W)(ARROW) | 281 EA | $150.00 | $190.00 | $201.69 | $11,240 |
| 666-7420 REFL PAV MRK TY I (Y)6"(BRK)(100MIL) | 44,175 LF | $0.6600 | $0.4200 | $0.4829 | -$10,602 |
| 672-7002 REFL PAV MRKR TY I-C | 2,249 EA | $0.0400 | $4.00 | $4.04 | $8,906 |
| 668-7110 PREFAB PM TY C (W)(18")(YLD TRI) | 314 EA | $5.00 | $25.00 | $25.92 | $6,280 |
Positive: the low bidder was cheaper on that item. These 20 items account for $358,279 of the $360,417 gap.
VIZCAINO, L.P.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 156,843 LF | $0.0350 | $2.80 | 0.01x | -$433,342 |
| 672-7004 REFL PAV MRKR TY II-A-A | 58,298 EA | $0.0400 | $3.97 | 0.01x | -$229,315 |
| 666-7273 RE PROFILE PM TY I(Y)6"(BRK)(090MIL) | 256,350 LF | $0.0540 | $0.5289 | 0.10x | -$121,741 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 MO | $1.00 | $11,585.04 | 0.00x | -$104,256 |
| 505-7003 TMA (MOBILE OPERATION) | 168 DAY | $20.00 | $229.60 | 0.09x | -$35,212 |
CENTERLINE TECHNOLOGIES, LLC: unbalanced items
Placed 2FC TRAFFIC CONTROL, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |