6504-31-001 Cleaning & Sealing Cracks
6504-31-001 · let Jul 14, 2026 · Pecos, Odessa · Routine Maintenance Project - Sealed
$236,501Low bid: SCOUT 5 CONSTRUCTION LLC-15.6% vs estimate $280,079
$124,601Left on the table52.7% gap to the second bid
5BiddersSpread 227% low to high
5Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SCOUT 5 CONSTRUCTION LLC | $236,501 | -15.6% | $124,601 | 0 | 2-$525,434 | |
| 2 | D & M CONTRACTORS, LLC | $361,102 | +52.7% | 28.9% | $19,385 | 0 | 3-$518,497 |
| 3 | FYL ENTERPRISES, LLC | $380,487 | +60.9% | 35.8% | $139,163 | 0 | 3-$489,914 |
| 4 | CRACKSEAL OF TEXAS, LLC | $519,650 | +119.7% | 85.5% | $254,182 | 0 | 2-$450,435 |
| 5 | GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY | $773,832 | +227.2% | 176.3% | 1+$481,521 | 2-$520,335 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SCOUT 5 CONSTRUCTION LLC vs D & M CONTRACTORS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 316 LMI | $700.00 | $1,077.00 | $868.20 | $119,132 |
| 500-7001 MOBILIZATION | 1 LS | $10,000.00 | $20,000.00 | $523,850.32 | $10,000 |
| 505-7001 TMA (STATIONARY) | 16 DAY | $200.00 | $20.00 | $217.57 | -$2,880 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 7 DAY | $300.00 | $50.00 | $87.82 | -$1,750 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 MO | $1.00 | $100.00 | $11,585.04 | $99 |
Positive: the low bidder was cheaper on that item. These 5 items account for $124,601 of the $124,601 gap.