Tree/Brush Removal/Trimming 04 07/26
6492-44-001 · let Jul 8, 2026 · Denton, Dallas · Routine Maintenance Project - Sealed
$101,186Low bid: TEXWAY WASTEWATER SERVICES, LLC-23.3% vs estimate $131,970
$15,150Left on the table15.0% gap to the second bid
9BiddersSpread 134% low to high
10Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TEXWAY WASTEWATER SERVICES, LLC | $101,186 | -23.3% | $15,150 | 0 | 3-$554,164 | |
| 2 | CROSS PLUS CONSTRUCTION, LLC | $116,336 | +15.0% | -11.8% | $9,544 | 0 | 3-$554,164 |
| 3 | RHINO EQUITY, LLC | $125,880 | +24.4% | -4.6% | $3,320 | 0 | 3-$541,900 |
| 4 | GV LANDSCAPE AND CONSTRUCTION LLC | $129,200 | +27.7% | -2.1% | $696 | 0 | 2-$541,620 |
| 5 | GOOD NEWS RANCH AND FARM LLC | $129,896 | +28.4% | -1.6% | $39,557 | 0 | 2-$511,670 |
| 6 | AUSTIN BARRICADE COMPANY, L.L.C. | $169,453 | +67.5% | 28.4% | $2,120 | ||
| 7 | BOEN LANDSCAPING & IRRIGATION, LLC | $171,573 | +69.6% | 30.0% | $923 | ||
| 8 | WESTERN CERTIFIED ARBORISTS | $172,495 | +70.5% | 30.7% | $64,207 | ||
| 9 | ANTHONY SERVICES | $236,702 | +133.9% | 79.4% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TEXWAY WASTEWATER SERVICES, LLC vs CROSS PLUS CONSTRUCTION, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 752-7001 TREE TRIMMING / BRUSH REMOVAL | 10 MI | $1,350.00 | $2,500.00 | $1,716.86 | $11,500 |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 33 AC | $1,590.00 | $1,500.00 | $1,602.83 | -$2,970 |
| 752-7007 TREE REMOVAL (18" - 24" DIA) | 7 EA | $100.00 | $400.00 | $141.37 | $2,100 |
| 752-7009 TREE REMOVAL (30" - 36" DIA) | 2 EA | $100.00 | $899.00 | $293.05 | $1,598 |
| 752-7006 TREE REMOVAL (12" - 18" DIA) | 36 EA | $100.00 | $144.00 | $100.44 | $1,584 |
| 752-7008 TREE REMOVAL (24" - 30" DIA) | 2 EA | $100.00 | $769.00 | $208.61 | $1,338 |
| 500-7001 MOBILIZATION | 1 LS | $1.00 | $1.00 | $523,850.32 | $0 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 MO | $1.00 | $1.00 | $11,585.04 | $0 |
| 505-7001 TMA (STATIONARY) | 33 DAY | $1.00 | $1.00 | $217.57 | $0 |
| 752-7005 TREE REMOVAL (4" - 12" DIA) | 381 EA | $80.00 | $80.00 | $60.77 | $0 |
Positive: the low bidder was cheaper on that item. These 10 items account for $15,150 of the $15,150 gap.