Bid Tab X-ray: 0229-01-042

Jul 1, 2026 · Ector Sign up free
Set your company to personalize scores

US385_AT S SL338

0229-01-042 · let Jul 1, 2026 · Ector, Odessa · Interchange (New or Reconstructed)

$53,657,268Low bid: JONES BROS. DIRT & PAVING CONTRACTORS, INC.+16.1% vs estimate $46,211,493
$3,961,167Left on the table7.4% gap to the second bid
6BiddersSpread 24% low to high
255Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1JONES BROS. DIRT & PAVING CONTRACTORS, INC. $53,657,26816.1% $3,961,167 3+$3,154,763 0
2RAGLE CONSTRUCTION, INC. $57,618,435+7.4%24.7% $1,302,599 5+$16,601,516 1-$4,048,247
3FNF CONSTRUCTION, INC. $58,921,034+9.8%27.5% $2,506,096 4+$12,144,456 0
4JAMES CONSTRUCTION GROUP, LLC $61,427,130+14.5%32.9% $1,888,370 3+$16,337,194 0
5WEBBER, LLC $63,315,500+18.0%37.0% $3,190,048 4+$12,315,712 0
6ALTUS CONSTRUCTION LLC $66,505,548+23.9%43.9%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

JONES BROS. DIRT & PAVING CONTRACTORS, INC. vs RAGLE CONSTRUCTION, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
100-7002 PREPARING ROW14 STA $3,700.00$371,425.00$6,072.92 $5,148,150
423-7002 RETAINING WALL (MSE) (ASHLAR STONE FIN)91,546 SF $93.23$40.00$84.22 -$4,872,994
500-7001 MOBILIZATION1 LS $2,570,000.00$5,500,000.00$523,850.32 $2,930,000
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING24 MO $20,000.00$134,500.00$11,585.04 $2,748,000
132-7006 EMBANK (FNL)(DC)(TY C)265,703 CY $18.89$23.50$13.19 $1,224,891
508-7001 CONSTRUCTING DETOURS28,467 SY $56.00$90.00$83.58 $967,878
247-7343 FL BS (CMP IN PLC)(TY A GR 4)(7")197,014 SY $13.50$9.00$12.89 -$886,563
360-7005 CONC PVMT (CRCP) (11")19,378 SY $148.08$114.00$94.72 -$660,402
681-7001 TEMP TRAF SIGNALS1 EA $456,875.00$50,000.00$62,461.14 -$406,875
400-7010 CEM STABIL BKFL1,482 CY $299.02$111.00$138.14 -$278,646
450-7025 RAIL (TY SSTR)(HPC)4,973 LF $111.80$60.00$96.82 -$257,601
530-7006 DRIVEWAYS (CONC)5,667 SY $130.64$88.00$109.20 -$241,641
432-7013 RIPRAP (MOW STRIP)(4 IN)1,107 CY $687.33$522.00$616.83 -$183,020
425-7005 PRESTR CONC GIRDER (TX54)3,220.02 LF $295.62$240.00$215.33 -$179,098
462-7003 CONC BOX CULV (4 FT X 2 FT)1,145 LF $671.88$520.00$419.86 -$173,903
344-7005 SP MIXES SP-B SAC-B PG70-2285,803 TON $106.00$108.00$94.47 $171,606
528-7001 LANDSCAPE PAVERS2,986 SY $164.48$108.00$113.93 -$168,649
416-7007 DRILL SHAFT (42 IN)878 LF $575.70$396.00$318.92 -$157,777
512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)4,204 LF $16.13$47.00$52.29 $129,777
529-7002 CONC CURB (TY II)6,795 LF $12.36$30.00$26.45 $119,864

Positive: the low bidder was cheaper on that item. These 20 items account for $4,972,998 of the $3,961,167 gap.

JONES BROS. DIRT & PAVING CONTRACTORS, INC.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $2,570,000.00$523,850.324.91x$2,046,150
110-7001 EXCAV (ROADWAY)66,699 CY $22.39$11.681.92x$714,200
681-7001 TEMP TRAF SIGNALS1 EA $456,875.00$62,461.147.31x$394,414

RAGLE CONSTRUCTION, INC.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
100-7002 PREPARING ROW14 STA $371,425.00$6,072.9261.16x$5,114,929
500-7001 MOBILIZATION1 LS $5,500,000.00$523,850.3210.50x$4,976,150
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING24 MO $134,500.00$11,585.0411.61x$2,949,959
132-7006 EMBANK (FNL)(DC)(TY C)265,703 CY $23.50$13.191.78x$2,738,893
110-7001 EXCAV (ROADWAY)66,699 CY $24.00$11.682.05x$821,585
423-7002 RETAINING WALL (MSE) (ASHLAR STONE FIN)91,546 SF $40.00$84.220.47x-$4,048,247

FNF CONSTRUCTION, INC.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $5,914,000.00$523,850.3211.29x$5,390,150
132-7006 EMBANK (FNL)(DC)(TY C)265,703 CY $32.00$13.192.43x$4,997,369
100-7002 PREPARING ROW14 STA $100,000.00$6,072.9216.47x$1,314,979
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING24 MO $30,000.00$11,585.042.59x$441,959

JAMES CONSTRUCTION GROUP, LLC: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
100-7002 PREPARING ROW14 STA $425,000.00$6,072.9269.98x$5,864,979
132-7006 EMBANK (FNL)(DC)(TY C)265,703 CY $34.45$13.192.61x$5,648,341
500-7001 MOBILIZATION1 LS $5,347,723.89$523,850.3210.21x$4,823,874

WEBBER, LLC: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
500-7001 MOBILIZATION1 LS $6,212,000.00$523,850.3211.86x$5,688,150
100-7002 PREPARING ROW14 STA $400,000.00$6,072.9265.87x$5,514,979
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING24 MO $35,415.00$11,585.043.06x$571,919
528-7001 LANDSCAPE PAVERS2,986 SY $295.00$113.932.59x$540,664