FM3334_SH17_Old Dairy
2370-01-009 · let Jul 1, 2026 · Reeves, Odessa · Rehabilitation of Existing Road
$7,369,594Low bid: A. L. HELMCAMP, INC.+9.3% vs estimate $6,744,963
$2,731Left on the table0.0% gap to the second bid
4BiddersSpread 15% low to high
84Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | A. L. HELMCAMP, INC. | $7,369,594 | 9.3% | $2,731 | 3+$451,053 | 0 | |
| 2 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | $7,372,325 | +0.0% | 9.3% | $1,066,928 | 2+$224,926 | 0 |
| 3 | DAN WILLIAMS COMPANY | $8,439,252 | +14.5% | 25.1% | $20,953 | 2+$285,539 | 1-$57,430 |
| 4 | FNF CONSTRUCTION, INC. | $8,460,206 | +14.8% | 25.4% | 5+$824,061 | 1-$43,269 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
A. L. HELMCAMP, INC. vs JONES BROS. DIRT & PAVING CONTRACTORS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 347-7001 TOM-C PG76-22 SAC-A | 11,572 TON | $188.00 | $149.00 | $169.86 | -$451,308 |
| 247-7046 FL BS (CMP IN PLC)(TY A GR 4) (6") | 91,141 SY | $12.00 | $15.00 | $15.69 | $273,423 |
| 134-7002 BACKFILL (TY B) | 404.6 STA | $700.00 | $175.00 | $206.94 | -$212,415 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $28,000.00 | $15,000.00 | $11,585.04 | -$169,000 |
| 530-7010 DRIVEWAYS (ACP) | 3,158 SY | $55.00 | $87.00 | $54.96 | $101,056 |
| 112-7001 SUBGR WIDEN (OC) | 404.6 STA | $700.00 | $885.00 | $458.34 | $74,851 |
| 316-7007 ASPH (AC-20-5TR) | 69,266 GAL | $3.90 | $4.92 | $3.27 | $70,651 |
| 3007-7001 BONDING COURSE | 39,885 GAL | $3.00 | $4.63 | $3.32 | $65,013 |
| 500-7001 MOBILIZATION | 1 LS | $700,000.00 | $761,000.00 | $523,850.32 | $61,000 |
| 505-7003 TMA (MOBILE OPERATION) | 52 DAY | $10.00 | $935.00 | $229.60 | $48,100 |
| 618-7030 CONDT (PVC) (SCH 40) (2") | 3,390 LF | $16.00 | $28.60 | $13.17 | $42,714 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 9,000 CY | $25.00 | $29.00 | $16.96 | $36,000 |
| 505-7001 TMA (STATIONARY) | 205 DAY | $250.00 | $82.50 | $217.57 | -$34,338 |
| 104-7041 REMOV CONC (FLUME) | 962 SY | $52.00 | $25.00 | $18.83 | -$25,974 |
| 462-7010 CONC BOX CULV (6 FT X 2 FT) | 64 LF | $1,155.00 | $819.50 | $558.64 | -$21,472 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 15 EA | $2,600.00 | $3,935.25 | $1,883.43 | $20,029 |
| 416-7040 DRILL SHAFT (RDWY ILL POLE) (30 IN) | 136 LF | $320.00 | $445.50 | $270.84 | $17,068 |
| 467-7327 SET (TY II) (24 IN) (RCP) (6: 1) (C) | 12 EA | $2,600.00 | $3,935.25 | $2,267.09 | $16,023 |
| 468-7003 THERMOPLASTIC PIPE (PP) (30") | 236 LF | $220.00 | $155.77 | $108.89 | -$15,158 |
| 467-7122 SET (TY I)(S= 6 FT)(HW= 2 FT)(6:1)(C) | 2 EA | $15,000.00 | $7,535.00 | $15,000.00 | -$14,930 |
Positive: the low bidder was cheaper on that item. These 20 items account for -$118,667 of the $2,731 gap.
A. L. HELMCAMP, INC.: unbalanced items
Placed 1JONES BROS. DIRT & PAVING CONTRACTORS, INC.: unbalanced items
Placed 2DAN WILLIAMS COMPANY: unbalanced items
Placed 3FNF CONSTRUCTION, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 112-7001 SUBGR WIDEN (OC) | 404.6 STA | $1,300.00 | $458.34 | 2.84x | $340,535 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $25,000.00 | $11,585.04 | 2.16x | $174,394 |
| 530-7010 DRIVEWAYS (ACP) | 3,158 SY | $105.00 | $54.96 | 1.91x | $158,041 |
| 3007-7001 BONDING COURSE | 39,885 GAL | $6.00 | $3.32 | 1.81x | $106,844 |
| 462-7010 CONC BOX CULV (6 FT X 2 FT) | 64 LF | $1,250.00 | $558.64 | 2.24x | $44,247 |
| 134-7002 BACKFILL (TY B) | 404.6 STA | $100.00 | $206.94 | 0.48x | -$43,269 |