Bid Tab X-ray: 1194-02-020

Jul 1, 2026 · Hardin Sign up free
Set your company to personalize scores

FM 943-(S/POLK C/L-FM1003)BASE REPAIR,OV

1194-02-020 · let Jul 1, 2026 · Hardin, Beaumont · Overlay

$6,974,719Low bid: DURWOOD GREENE CONSTRUCTION CO.+17.9% vs estimate $5,913,740
$260,359Left on the table3.7% gap to the second bid
3BiddersSpread 17% low to high
69Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1DURWOOD GREENE CONSTRUCTION CO. $6,974,71917.9% $260,359 1+$50,993 1-$838,723
2TEXAS MATERIALS GROUP, INC. $7,235,078+3.7%22.3% $942,733 5+$320,564 3-$1,313,760
3HAYDEN PAVING, INC. $8,177,812+17.2%38.3% 4+$1,934,449 3-$1,213,870

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

DURWOOD GREENE CONSTRUCTION CO. vs TEXAS MATERIALS GROUP, INC., biggest item swings
ItemQtyLow2ndMarket2nd minus low
500-7001 MOBILIZATION1 LS $460,000.00$170,000.00$523,850.32 -$290,000
341-7048 D-GR HMA TY-D PG70-2210,884 TON $140.00$155.75$126.94 $171,423
530-7002 INTERSECTIONS (ACP)572 SY $55.00$175.00$50.74 $68,640
530-7018 TURNOUTS (ACP)805 SY $100.00$175.00$82.59 $60,375
400-7010 CEM STABIL BKFL1,071 CY $80.00$136.25$138.14 $60,244
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING9 MO $7,500.00$890.00$11,585.04 -$59,490
402-7001 TRENCH EXCAVATION PROTECTION562 LF $10.00$115.25$5.96 $59,151
346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-2214,513 TON $220.00$224.00$152.44 $58,052
351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")659 SY $97.00$166.25$60.19 $45,636
496-7007 REMOV STR (PIPE)910 LF $80.00$31.50$23.96 -$44,135
530-7015 DRIVEWAYS (BASE)1,003 SY $35.00$71.50$27.85 $36,610
100-7002 PREPARING ROW159.82 STA $825.00$669.00$6,072.92 -$24,932
400-7006 CUT & RESTORING PAV218 SY $200.00$314.00$171.81 $24,852
467-7470 SET (TY II) (48 IN) (TP) (4:1) (C)12 EA $6,000.00$7,953.50$6,000.00 $23,442
467-7390 SET (TY II) (48 IN) (RCP) (4: 1) (C)4 EA $4,200.00$7,745.00$9,736.49 $14,180
466-7013 HEADWALL (CH - FW - 0) (DIA= 60 IN)2 EA $19,000.00$25,000.00$17,356.67 $12,000
467-7471 SET (TY II) (60 IN) (TP) (4:1) (C)6 EA $8,500.00$10,465.00$8,500.00 $11,790
468-7006 THERMOPLASTIC PIPE (PP) (48")366 LF $190.00$220.00$165.95 $10,980
468-7003 THERMOPLASTIC PIPE (PP) (30")156 LF $130.00$199.00$108.89 $10,764
432-7033 RIPRAP (STONE COMMON)(DRY)(18 IN)91 CY $265.00$146.75$187.68 -$10,761

Positive: the low bidder was cheaper on that item. These 20 items account for $238,820 of the $260,359 gap.

DURWOOD GREENE CONSTRUCTION CO.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
496-7007 REMOV STR (PIPE)910 LF $80.00$23.963.34x$50,993
100-7002 PREPARING ROW159.82 STA $825.00$6,072.920.14x-$838,723

TEXAS MATERIALS GROUP, INC.: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
530-7018 TURNOUTS (ACP)805 SY $175.00$82.592.12x$74,387
530-7002 INTERSECTIONS (ACP)572 SY $175.00$50.743.45x$71,079
351-7007 FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")659 SY $166.25$60.192.76x$69,893
402-7001 TRENCH EXCAVATION PROTECTION562 LF $115.25$5.9619.34x$61,421
530-7015 DRIVEWAYS (BASE)1,003 SY $71.50$27.852.57x$43,784
100-7002 PREPARING ROW159.82 STA $669.00$6,072.920.11x-$863,655
500-7001 MOBILIZATION1 LS $170,000.00$523,850.320.32x-$353,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING9 MO $890.00$11,585.040.08x-$96,255

HAYDEN PAVING, INC.: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
346-7009 STONE-MTRX-ASPH SMA-D SAC-A PG76-2214,513 TON $270.00$152.441.77x$1,706,164
134-7004 BACKFILL (TY A OR B)438.72 STA $450.00$211.212.13x$104,762
168-7001 VEGETATIVE WATERING513 TGL $140.00$8.4316.60x$67,494
506-7002 ROCK FILTER DAMS (INSTALL) (TY 2)320 LF $220.00$44.914.90x$56,029
100-7002 PREPARING ROW159.82 STA $1,000.00$6,072.920.16x-$810,754
500-7001 MOBILIZATION1 LS $180,000.00$523,850.320.34x-$343,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING9 MO $5,000.00$11,585.040.43x-$59,265