FY27 BPM
6488-31-001 · let Aug 5, 2026 · Jasper, Beaumont · Bridge Preventative Maintenance - Sealed
$1,880,325Low bid: PATHFIELD INVESTMENTS LLC-11.6% vs estimate $2,126,165
$8,090Left on the table0.4% gap to the second bid
8BiddersSpread 91% low to high
31Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | PATHFIELD INVESTMENTS LLC | $1,880,325 | -11.6% | $8,090 | 3+$70,983 | 4-$534,880 | |
| 2 | ISI CONTRACTING, INC. | $1,888,415 | +0.4% | -11.2% | $485,056 | 5+$224,675 | 1-$383,850 |
| 3 | GARRET SHIELDS INFRASTRUCTURE | $2,373,471 | +26.2% | 11.6% | $97,806 | 2+$58,475 | 3-$360,113 |
| 4 | SCR CIVIL CONSTRUCTION, LLC | $2,471,277 | +31.4% | 16.2% | $133,505 | 8+$765,070 | 2-$388,117 |
| 5 | RAGLE CONSTRUCTION, INC. | $2,604,783 | +38.5% | 22.5% | $188,730 | 4+$616,897 | 1-$263,850 |
| 6 | STRUCTURAL INTEGRITY GROUP LLC | $2,793,513 | +48.6% | 31.4% | $528,132 | ||
| 7 | BLACKSMITH VENTURES LLC | $3,321,645 | +76.7% | 56.2% | $275,100 | ||
| 8 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $3,596,745 | +91.3% | 69.2% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
PATHFIELD INVESTMENTS LLC vs ISI CONTRACTING, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 37 DAY | $150.00 | $2,530.00 | $217.57 | $88,060 |
| 429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD) | 1,507 SF | $170.00 | $127.00 | $150.68 | -$64,801 |
| 495-7001 RAISING EXIST STRUCT | 3 LS | $14,000.00 | $31,833.00 | $52,755.69 | $53,499 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 3,200 SF | $40.00 | $55.00 | $28.47 | $48,000 |
| 438-7007 CLEANING AND SEALING EXIST JOINTS (CL7) | 22,429 LF | $28.00 | $26.00 | $38.57 | -$44,858 |
| 429-7009 CONC STR REPAIR (STANDARD) | 1,027 SF | $150.00 | $111.00 | $146.35 | -$40,053 |
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 1,419 LF | $45.00 | $20.00 | $19.19 | -$35,475 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 960 CY | $210.00 | $180.00 | $190.61 | -$28,800 |
| 420-7061 CL C CONC (COLLAR) | 16 EA | $1,500.00 | $3,250.00 | $1,390.28 | $28,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $1,500.00 | $8,885.00 | $11,585.04 | $22,155 |
| 432-7002 RIPRAP (CONC)(5 IN) | 22 CY | $1,600.00 | $1,018.00 | $585.15 | -$12,804 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $140,000.00 | $523,850.32 | -$10,000 |
| 5011-7002 REMOVE LEAD-CONTAINING COATING (OTHER) | 1 LS | $20,000.00 | $10,000.00 | $15,780.56 | -$10,000 |
| 483-7016 SHOT BLASTING | 583 SY | $10.00 | $25.00 | $5.25 | $8,745 |
| 434-7001 ELASTOMERIC BEARING (PLAIN) | 2 EA | $5,000.00 | $1,441.00 | $1,155.61 | -$7,118 |
| 420-7166 CL K CONCRETE (PEDESTAL) | 2 EA | $2,500.00 | $5,993.00 | $2,500.00 | $6,986 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $2,000.00 | $5,024.00 | $9,253.78 | $6,048 |
| 104-7007 REMOV CONC (RIPRAP) | 21 CY | $350.00 | $79.00 | $26.91 | -$5,691 |
| 104-7033 REMOV CONC (PILE ENCASEMENT) | 5 CY | $3,000.00 | $2,203.00 | $592.82 | -$3,985 |
| 454-7011 HEADER TYPE EXPANSION JOINT | 92 LF | $270.00 | $306.00 | $165.20 | $3,312 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,220 of the $8,090 gap.
PATHFIELD INVESTMENTS LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 1,419 LF | $45.00 | $19.19 | 2.34x | $36,620 |
| 432-7002 RIPRAP (CONC)(5 IN) | 22 CY | $1,600.00 | $585.15 | 2.73x | $22,327 |
| 104-7033 REMOV CONC (PILE ENCASEMENT) | 5 CY | $3,000.00 | $592.82 | 5.06x | $12,036 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $523,850.32 | 0.29x | -$373,850 |
| 495-7001 RAISING EXIST STRUCT | 3 LS | $14,000.00 | $52,755.69 | 0.27x | -$116,267 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $1,500.00 | $11,585.04 | 0.13x | -$30,255 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $2,000.00 | $9,253.78 | 0.22x | -$14,508 |
ISI CONTRACTING, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 37 DAY | $2,530.00 | $217.57 | 11.63x | $85,560 |
| 403-7002 TEMPORARY SPL SHORING (COFFERDAM) | 3,200 SF | $55.00 | $28.47 | 1.93x | $84,894 |
| 420-7061 CL C CONC (COLLAR) | 16 EA | $3,250.00 | $1,390.28 | 2.34x | $29,756 |
| 454-7011 HEADER TYPE EXPANSION JOINT | 92 LF | $306.00 | $165.20 | 1.85x | $12,953 |
| 483-7016 SHOT BLASTING | 583 SY | $25.00 | $5.25 | 4.76x | $11,512 |
| 500-7001 MOBILIZATION | 1 LS | $140,000.00 | $523,850.32 | 0.27x | -$383,850 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 438-7004 CLEANING AND SEALING EXIST JOINTS (CL3) | 1,419 LF | $40.00 | $19.19 | 2.08x | $29,525 |
| 505-7001 TMA (STATIONARY) | 37 DAY | $1,000.00 | $217.57 | 4.60x | $28,950 |
| 500-7001 MOBILIZATION | 1 LS | $200,000.00 | $523,850.32 | 0.38x | -$323,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,000.00 | $11,585.04 | 0.43x | -$19,755 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $1,000.00 | $9,253.78 | 0.11x | -$16,508 |
SCR CIVIL CONSTRUCTION, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 960 CY | $680.00 | $190.61 | 3.57x | $469,812 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $48,000.00 | $11,585.04 | 4.14x | $109,245 |
| 420-7061 CL C CONC (COLLAR) | 16 EA | $3,955.00 | $1,390.28 | 2.84x | $41,036 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 65 CY | $800.00 | $179.97 | 4.45x | $40,302 |
| 104-7033 REMOV CONC (PILE ENCASEMENT) | 5 CY | $7,310.00 | $592.82 | 12.33x | $33,586 |
| 442-7010 STR STEEL (PEDESTAL) | 1,395 LB | $43.00 | $20.55 | 2.09x | $31,323 |
| 104-7007 REMOV CONC (RIPRAP) | 21 CY | $1,135.00 | $26.91 | 42.18x | $23,270 |
| 432-7002 RIPRAP (CONC)(5 IN) | 22 CY | $1,335.00 | $585.15 | 2.28x | $16,497 |
| 500-7001 MOBILIZATION | 1 LS | $246,000.00 | $523,850.32 | 0.47x | -$277,850 |
| 495-7001 RAISING EXIST STRUCT | 3 LS | $16,000.00 | $52,755.69 | 0.30x | -$110,267 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 495-7001 RAISING EXIST STRUCT | 3 LS | $152,000.00 | $52,755.69 | 2.88x | $297,733 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $100,000.00 | $11,585.04 | 8.63x | $265,245 |
| 5011-7002 REMOVE LEAD-CONTAINING COATING (OTHER) | 1 LS | $50,000.00 | $15,780.56 | 3.17x | $34,219 |
| 505-7001 TMA (STATIONARY) | 37 DAY | $750.00 | $217.57 | 3.45x | $19,700 |
| 500-7001 MOBILIZATION | 1 LS | $260,000.00 | $523,850.32 | 0.50x | -$263,850 |