CR 452/Dennis Rd: At Patrick Creek
0902-38-134 · let Aug 5, 2026 · Parker, Fort Worth · Bridge Replacement
$1,531,854Low bid: HODGES AND SON CONSTRUCTION COMPANY, INC.-15.2% vs estimate $1,806,941
$224,044Left on the table14.6% gap to the second bid
10BiddersSpread 46% low to high
50Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $1,531,854 | -15.2% | $224,044 | 3+$53,744 | 5-$591,447 | |
| 2 | SCOTT TUCKER CONSTRUCTION COMPANY, LLC | $1,755,898 | +14.6% | -2.8% | $17,718 | 5+$108,030 | 4-$543,284 |
| 3 | GARRET SHIELDS INFRASTRUCTURE | $1,773,616 | +15.8% | -1.8% | $9,858 | 5+$169,874 | 3-$513,207 |
| 4 | COPPELL CONSTRUCTION CO., INC. | $1,783,475 | +16.4% | -1.3% | $10,570 | 4+$89,320 | 2-$440,527 |
| 5 | PMCO CONSTRUCTION LLC | $1,794,044 | +17.1% | -0.7% | $73,842 | 3+$71,579 | 3-$515,207 |
| 6 | ED BELL CONSTRUCTION COMPANY | $1,867,886 | +21.9% | 3.4% | $20,955 | ||
| 7 | DELGADO'S CONTRACTORS, LLC | $1,888,841 | +23.3% | 4.5% | $176,986 | ||
| 8 | EARTH BUILDERS, L.P. | $2,065,827 | +34.9% | 14.3% | $7,635 | ||
| 9 | TUCAN CONTRACTING, LLC | $2,073,462 | +35.4% | 14.7% | $157,153 | ||
| 10 | CASTILLO ARANDA LLC | $2,230,615 | +45.6% | 23.4% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HODGES AND SON CONSTRUCTION COMPANY, INC. vs SCOTT TUCKER CONSTRUCTION COMPANY, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 425-7001 PRESTR CONC GIRDER (TX28) | 742.42 LF | $250.00 | $355.00 | $217.69 | $77,954 |
| 500-7001 MOBILIZATION | 1 LS | $125,000.00 | $175,500.00 | $523,850.32 | $50,500 |
| 420-7023 CL C CONC (CAP)(HPC) | 37.4 CY | $1,200.00 | $2,372.00 | $1,420.15 | $43,833 |
| 110-7001 EXCAV (ROADWAY) | 2,076 CY | $5.00 | $24.00 | $11.68 | $39,444 |
| 416-7006 DRILL SHAFT (36 IN) | 469 LF | $250.00 | $325.00 | $280.58 | $35,175 |
| 168-7001 VEGETATIVE WATERING | 75 TGL | $1.00 | $422.00 | $8.43 | $31,575 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 4 EA | $15,000.00 | $7,381.00 | $9,253.78 | -$30,476 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 607 CY | $30.00 | $71.00 | $18.71 | $24,887 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $5,000.00 | $2,037.00 | $11,585.04 | -$23,704 |
| 420-7039 CL C CONC (COLUMN)(HPC) | 30.1 CY | $1,200.00 | $1,934.00 | $1,492.16 | $22,093 |
| 400-7010 CEM STABIL BKFL | 178 CY | $280.00 | $156.00 | $138.14 | -$22,072 |
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 1,256 SY | $38.00 | $22.00 | $21.46 | -$20,096 |
| 422-7014 APPROACH SLAB (HPC) | 82 CY | $800.00 | $566.00 | $731.91 | -$19,188 |
| 422-7002 REINF CONC SLAB (HPC) | 6,300 SF | $32.00 | $29.00 | $26.91 | -$18,900 |
| 450-7009 RAIL (TY T223)(HPC) | 348 LF | $180.00 | $222.00 | $152.11 | $14,616 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 1,160 SY | $3.50 | $15.00 | $6.84 | $13,340 |
| 432-7045 RIPRAP (STONE PROTECTION)(24 IN) | 902 CY | $160.00 | $150.00 | $190.61 | -$9,020 |
| 552-7003 WIRE FENCE (TY C) | 321 LF | $20.00 | $44.00 | $12.12 | $7,704 |
| 100-7002 PREPARING ROW | 7.3 STA | $2,050.00 | $3,025.00 | $6,072.92 | $7,118 |
| 454-7006 SEALED EXPANSION JOINT (4 IN) (SEJ - B) | 85 LF | $175.00 | $112.00 | $158.57 | -$5,355 |
Positive: the low bidder was cheaper on that item. These 20 items account for $219,428 of the $224,044 gap.
HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 400-7010 CEM STABIL BKFL | 178 CY | $280.00 | $138.14 | 2.03x | $25,250 |
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 1,256 SY | $38.00 | $21.46 | 1.77x | $20,774 |
| 162-7002 BLOCK SODDING | 2,137 SY | $8.00 | $4.39 | 1.82x | $7,719 |
| 500-7001 MOBILIZATION | 1 LS | $125,000.00 | $523,850.32 | 0.24x | -$398,850 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $40,000.00 | $136,676.66 | 0.29x | -$96,677 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $5,000.00 | $11,585.04 | 0.43x | -$52,680 |
| 100-7002 PREPARING ROW | 7.3 STA | $2,050.00 | $6,072.92 | 0.34x | -$29,367 |
| 110-7001 EXCAV (ROADWAY) | 2,076 CY | $5.00 | $11.68 | 0.43x | -$13,872 |
SCOTT TUCKER CONSTRUCTION COMPANY, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7005 EMBANK (FNL)(OC)(TY C) | 607 CY | $71.00 | $18.71 | 3.79x | $31,738 |
| 168-7001 VEGETATIVE WATERING | 75 TGL | $422.00 | $8.43 | 50.04x | $31,017 |
| 110-7001 EXCAV (ROADWAY) | 2,076 CY | $24.00 | $11.68 | 2.05x | $25,572 |
| 552-7003 WIRE FENCE (TY C) | 321 LF | $44.00 | $12.12 | 3.63x | $10,234 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 1,160 SY | $15.00 | $6.84 | 2.19x | $9,469 |
| 500-7001 MOBILIZATION | 1 LS | $175,500.00 | $523,850.32 | 0.34x | -$348,350 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $40,377.00 | $136,676.66 | 0.30x | -$96,300 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,037.00 | $11,585.04 | 0.18x | -$76,384 |
| 100-7002 PREPARING ROW | 7.3 STA | $3,025.00 | $6,072.92 | 0.50x | -$22,250 |
GARRET SHIELDS INFRASTRUCTURE: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 2,076 CY | $40.00 | $11.68 | 3.42x | $58,788 |
| 420-7023 CL C CONC (CAP)(HPC) | 37.4 CY | $2,500.00 | $1,420.15 | 1.76x | $40,386 |
| 344-7024 SP MIXES SP-C SAC-A PG70-28 | 250 TON | $280.00 | $156.36 | 1.79x | $30,910 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 1,160 SY | $30.00 | $6.84 | 4.39x | $26,869 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 607 CY | $40.00 | $18.71 | 2.14x | $12,921 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $523,850.32 | 0.29x | -$373,850 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $50,000.00 | $136,676.66 | 0.37x | -$86,677 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $5,000.00 | $11,585.04 | 0.43x | -$52,680 |
COPPELL CONSTRUCTION CO., INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 2,076 CY | $25.00 | $11.68 | 2.14x | $27,648 |
| 400-7010 CEM STABIL BKFL | 178 CY | $270.00 | $138.14 | 1.95x | $23,470 |
| 496-7001 REMOV STR (BOX CULVERT) | 2 EA | $15,000.00 | $4,831.36 | 3.10x | $20,337 |
| 496-7006 REMOV STR (HEADWALL) | 4 EA | $6,000.00 | $1,533.90 | 3.91x | $17,864 |
| 500-7001 MOBILIZATION | 1 LS | $160,000.00 | $523,850.32 | 0.31x | -$363,850 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $60,000.00 | $136,676.66 | 0.44x | -$76,677 |
PMCO CONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7067 FL BS (CMP IN PLC)(TY A GR 1-2) (8") | 1,256 SY | $42.00 | $21.46 | 1.96x | $25,798 |
| 400-7010 CEM STABIL BKFL | 178 CY | $275.00 | $138.14 | 1.99x | $24,360 |
| 110-7001 EXCAV (ROADWAY) | 2,076 CY | $22.00 | $11.68 | 1.88x | $21,420 |
| 500-7001 MOBILIZATION | 1 LS | $175,000.00 | $523,850.32 | 0.33x | -$348,850 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $35,000.00 | $136,676.66 | 0.26x | -$101,677 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $3,500.00 | $11,585.04 | 0.30x | -$64,680 |