CR403 BRIDGE REPLACEMENT 2609
0913-28-101 · let Aug 5, 2026 · Fayette, Yoakum · Bridge Replacement
$1,617,207Low bid: TREVWAY, INC.-5.4% vs estimate $1,710,089
$112,880Left on the table7.0% gap to the second bid
9BiddersSpread 45% low to high
110Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | TREVWAY, INC. | $1,617,207 | -5.4% | $112,880 | 4+$121,027 | 7-$625,126 | |
| 2 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $1,730,087 | +7.0% | 1.2% | $928 | 2+$36,419 | 3-$550,723 |
| 3 | PRESIDIO CONTRACTING, LLC | $1,731,015 | +7.0% | 1.2% | $205,013 | 7+$144,871 | 2-$503,676 |
| 4 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $1,936,028 | +19.7% | 13.2% | $52,178 | 5+$61,404 | 2-$507,626 |
| 5 | Rucoba & Maya Construction, LLC | $1,988,206 | +22.9% | 16.3% | $1,668 | 8+$257,326 | 3-$622,189 |
| 6 | E-Z BEL CONSTRUCTION, LLC | $1,989,874 | +23.0% | 16.4% | $105,050 | ||
| 7 | DEAN WORD COMPANY, LTD. | $2,094,924 | +29.5% | 22.5% | $215,603 | ||
| 8 | STX CIVIL | $2,310,527 | +42.9% | 35.1% | $37,720 | ||
| 9 | CASTILLO ARANDA LLC | $2,348,247 | +45.2% | 37.3% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
TREVWAY, INC. vs TEXAS STEEL INDUSTRIAL PLACING, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 425-7019 PRESTR CONC SLAB BEAM (5SB15) | 1,162.5 LF | $250.00 | $200.00 | $261.75 | -$58,125 |
| 422-7007 REINF CONC SLAB (SLAB BEAM) | 6,110 SF | $15.00 | $22.00 | $23.90 | $42,770 |
| 450-7008 RAIL (TY T223) | 542 LF | $84.00 | $150.00 | $141.07 | $35,772 |
| 420-7012 CL C CONC (ABUT) | 61.6 CY | $630.00 | $1,200.00 | $1,307.98 | $35,112 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 3 EA | $20,000.00 | $30,000.00 | $28,021.15 | $30,000 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 22 CY | $2,200.00 | $1,000.00 | $111.76 | -$26,400 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 20 CY | $2,300.00 | $1,000.00 | $156.13 | -$26,000 |
| 420-7022 CL C CONC (CAP) | 19.8 CY | $830.00 | $2,000.00 | $1,543.38 | $23,166 |
| 416-7004 DRILL SHAFT (24 IN) | 1,164 LF | $345.00 | $330.00 | $234.98 | -$17,460 |
| 420-7038 CL C CONC (COLUMN) | 13.1 CY | $800.00 | $2,000.00 | $1,548.37 | $15,720 |
| 247-7196 FL BS (CMP IN PLC)(TY E GR 5)(FNAL POS) | 672 CY | $110.00 | $90.00 | $88.48 | -$13,440 |
| 500-7001 MOBILIZATION | 1 LS | $160,000.00 | $172,993.13 | $523,850.32 | $12,993 |
| 552-7001 WIRE FENCE (TY A) | 559 LF | $8.00 | $30.00 | $22.53 | $12,298 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $1,800.00 | $1,000.00 | $11,585.04 | -$12,000 |
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 970 GAL | $24.00 | $12.00 | $4.17 | -$11,640 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 1,121 CY | $140.00 | $150.00 | $184.74 | $11,210 |
| 316-7016 ASPH (RC-250) | 571 GAL | $28.00 | $12.00 | $5.28 | -$9,136 |
| 552-7010 WIRE FENCE (WATER GAP) | 206 LF | $11.00 | $50.00 | $49.94 | $8,034 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 549 CY | $8.00 | $22.00 | $18.71 | $7,686 |
| 454-7003 ARMOR JOINT (SEALED) | 134 LF | $70.00 | $125.00 | $154.25 | $7,370 |
Positive: the low bidder was cheaper on that item. These 20 items account for $67,930 of the $112,880 gap.
TREVWAY, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 22 CY | $2,200.00 | $111.76 | 19.69x | $45,941 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 20 CY | $2,300.00 | $156.13 | 14.73x | $42,877 |
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 970 GAL | $24.00 | $4.17 | 5.75x | $19,233 |
| 316-7016 ASPH (RC-250) | 571 GAL | $28.00 | $5.28 | 5.31x | $12,975 |
| 500-7001 MOBILIZATION | 1 LS | $160,000.00 | $523,850.32 | 0.31x | -$363,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $1,800.00 | $11,585.04 | 0.16x | -$146,776 |
| 100-7002 PREPARING ROW | 8.1 STA | $500.00 | $6,072.92 | 0.08x | -$45,141 |
| 420-7012 CL C CONC (ABUT) | 61.6 CY | $630.00 | $1,307.98 | 0.48x | -$41,764 |
| 454-7003 ARMOR JOINT (SEALED) | 134 LF | $70.00 | $154.25 | 0.45x | -$11,290 |
| 150-7002 BLADING | 48 HR | $1.00 | $171.50 | 0.01x | -$8,184 |
| 552-7001 WIRE FENCE (TY A) | 559 LF | $8.00 | $22.53 | 0.36x | -$8,121 |
TEXAS STEEL INDUSTRIAL PLACING, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 22 CY | $1,000.00 | $111.76 | 8.95x | $19,541 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 20 CY | $1,000.00 | $156.13 | 6.40x | $16,877 |
| 500-7001 MOBILIZATION | 1 LS | $172,993.13 | $523,850.32 | 0.33x | -$350,857 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $1,000.00 | $11,585.04 | 0.09x | -$158,776 |
| 100-7002 PREPARING ROW | 8.1 STA | $1,000.00 | $6,072.92 | 0.16x | -$41,091 |
PRESIDIO CONTRACTING, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 22 CY | $1,905.00 | $111.76 | 17.05x | $39,451 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 20 CY | $1,880.00 | $156.13 | 12.04x | $34,477 |
| 110-7002 EXCAV (CHANNEL) | 655 CY | $50.00 | $16.69 | 3.00x | $21,815 |
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 970 GAL | $21.00 | $4.17 | 5.03x | $16,323 |
| 110-7001 EXCAV (ROADWAY) | 314 CY | $50.00 | $11.68 | 4.28x | $12,032 |
| 316-7016 ASPH (RC-250) | 571 GAL | $25.00 | $5.28 | 4.74x | $11,262 |
| 400-7010 CEM STABIL BKFL | 89 CY | $245.00 | $138.14 | 1.77x | $9,510 |
| 500-7001 MOBILIZATION | 1 LS | $171,450.00 | $523,850.32 | 0.33x | -$352,400 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $1,500.00 | $11,585.04 | 0.13x | -$151,276 |
HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 970 GAL | $20.00 | $4.17 | 4.79x | $15,353 |
| 400-7010 CEM STABIL BKFL | 89 CY | $285.00 | $138.14 | 2.06x | $13,070 |
| 316-7232 AGGR (TY-PE, GR-4)(SAC-B) | 22 CY | $650.00 | $111.76 | 5.82x | $11,841 |
| 316-7016 ASPH (RC-250) | 571 GAL | $25.00 | $5.28 | 4.74x | $11,262 |
| 316-7194 AGGR (TY-E, GR-5)(SAC-B) | 20 CY | $650.00 | $156.13 | 4.16x | $9,877 |
| 500-7001 MOBILIZATION | 1 LS | $160,000.00 | $523,850.32 | 0.31x | -$363,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $2,000.00 | $11,585.04 | 0.17x | -$143,776 |
Rucoba & Maya Construction, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7012 CL C CONC (ABUT) | 61.6 CY | $2,730.00 | $1,307.98 | 2.09x | $87,596 |
| 420-7022 CL C CONC (CAP) | 19.8 CY | $4,500.00 | $1,543.38 | 2.92x | $58,541 |
| 132-7005 EMBANK (FNL)(OC)(TY C) | 549 CY | $77.00 | $18.71 | 4.11x | $32,000 |
| 420-7038 CL C CONC (COLUMN) | 13.1 CY | $3,304.00 | $1,548.37 | 2.13x | $22,999 |
| 506-7001 ROCK FILTER DAMS (INSTALL) (TY 1) | 200 LF | $130.00 | $37.24 | 3.49x | $18,552 |
| 110-7001 EXCAV (ROADWAY) | 314 CY | $62.00 | $11.68 | 5.31x | $15,800 |
| 110-7002 EXCAV (CHANNEL) | 655 CY | $34.00 | $16.69 | 2.04x | $11,335 |
| 316-7264 ASPH (AC 20-5TR OR AC-20XP OR CRS-2P) | 970 GAL | $15.00 | $4.17 | 3.59x | $10,503 |
| 500-7001 MOBILIZATION | 1 LS | $110,000.00 | $523,850.32 | 0.21x | -$413,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 15 MO | $600.00 | $11,585.04 | 0.05x | -$164,776 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 3 EA | $13,500.00 | $28,021.15 | 0.48x | -$43,563 |