Bid Tab X-ray: 6505-29-001

Aug 18, 2026 · Nueces Sign up free
Set your company to personalize scores

6505-29-001 West Nueces Mowing

6505-29-001 · let Aug 18, 2026 · Nueces, Corpus Christi · Routine Maintenance Project - Sealed

$438,350Low bid: R&M INCORPORATED-8.9% vs estimate $480,916
$141,664Left on the table32.3% gap to the second bid
2BiddersSpread 32% low to high
4Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1R&M INCORPORATED $438,350-8.9% $141,664 0 1-$2,927
2CROSS PLUS CONSTRUCTION, LLC $580,014+32.3%20.6% 3+$241,685 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 2 bidders.

Where the job was won

R&M INCORPORATED vs CROSS PLUS CONSTRUCTION, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
730-7022 FULL - WIDTH MOWING6,522 AC $48.76$70.00$38.53 $138,527
734-7001 LITTER REMOVAL3,138 AC $25.00$18.00$15.14 -$21,966
730-7020 STRIP MOWING857 AC $48.76$70.00$32.12 $18,203
730-7021 SPOT MOWING100 AC $1.00$70.00$30.27 $6,900

Positive: the low bidder was cheaper on that item. These 4 items account for $141,664 of the $141,664 gap.

R&M INCORPORATED: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
730-7021 SPOT MOWING100 AC $1.00$30.270.03x-$2,927

CROSS PLUS CONSTRUCTION, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
730-7022 FULL - WIDTH MOWING6,522 AC $70.00$38.531.82x$205,251
730-7020 STRIP MOWING857 AC $70.00$32.122.18x$32,461
730-7021 SPOT MOWING100 AC $70.00$30.272.31x$3,973