Bid Tab X-ray: 6504-75-001

Aug 20, 2026 · Johnson Sign up free
Set your company to personalize scores

FY27 Johnson Brine Solution

6504-75-001 · let Aug 20, 2026 · Johnson, Fort Worth · Material Maintenance Project

$38,104Low bid: CLEMENTS FLUIDS BUFFALO, LTD.-5.9% vs estimate $40,480
$2,376Left on the table6.2% gap to the second bid
3BiddersSpread 27% low to high
1Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1CLEMENTS FLUIDS BUFFALO, LTD. $38,104-5.9% $2,376 0 0
2NSG LOGISTICS, LLC $40,480+6.2%0.0% $7,920 0 0
3TOUCHSTONE RESOURCES, LLC $48,400+27.0%19.6% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

CLEMENTS FLUIDS BUFFALO, LTD. vs NSG LOGISTICS, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8032-7572 BRINE SOLUTION (DEL)(SITE 1)88,000 GAL $0.4330$0.4600$0.4203 $2,376

Positive: the low bidder was cheaper on that item. These 1 items account for $2,376 of the $2,376 gap.