Bid Tab X-ray: 6501-48-001

Aug 12, 2026 · Collin Sign up free
Set your company to personalize scores

FLEXIBLE BASE COLLIN FY27

6501-48-001 · let Aug 12, 2026 · Collin, Dallas · Material Maintenance Project

$42,400Low bid: RK HALL, LLC-7.8% vs estimate $46,000
$2,490Left on the table5.9% gap to the second bid
4BiddersSpread 38% low to high
1Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1RK HALL, LLC $42,400-7.8% $2,490 0 0
2SOUTHERN SOURCING SOLUTIONS, LLC $44,890+5.9%-2.4% $5,110 0 0
3TOUCHSTONE RESOURCES, LLC $50,000+17.9%8.7% $8,640 0 0
4DIGG COMMERCIAL, LLC $58,640+38.3%27.5% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.

Where the job was won

RK HALL, LLC vs SOUTHERN SOURCING SOLUTIONS, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8010-7097 FL BS(TY A GR 4)(DEL)(ST1)1,000 TON $42.40$44.89$40.00 $2,490

Positive: the low bidder was cheaper on that item. These 1 items account for $2,490 of the $2,490 gap.