FY 26 Crack Seal BTAO
6487-42-001 · let Aug 12, 2026 · Burnet, Austin · Routine Maintenance Project - Sealed
$246,706Low bid: FYL ENTERPRISES, LLC-18.2% vs estimate $301,553
$75,912Left on the table30.8% gap to the second bid
3BiddersSpread 74% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | FYL ENTERPRISES, LLC | $246,706 | -18.2% | $75,912 | 0 | 1-$7,179 | |
| 2 | D & M CONTRACTORS, LLC | $322,618 | +30.8% | 7.0% | $106,979 | 0 | 1-$6,190 |
| 3 | CRACKSEAL OF TEXAS, LLC | $429,597 | +74.1% | 42.5% | 0 | 1-$6,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
FYL ENTERPRISES, LLC vs D & M CONTRACTORS, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 712-7001 JT / CRCK SEAL (RUBBER - ASPHALT) | 328.94 LMI | $750.00 | $977.77 | $868.20 | $74,923 |
| 505-7001 TMA (STATIONARY) | 33 DAY | $0.0300 | $30.00 | $217.57 | $989 |
Positive: the low bidder was cheaper on that item. These 2 items account for $75,912 of the $75,912 gap.
FYL ENTERPRISES, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 33 DAY | $0.0300 | $217.57 | 0.00x | -$7,179 |
D & M CONTRACTORS, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 33 DAY | $30.00 | $217.57 | 0.14x | -$6,190 |
CRACKSEAL OF TEXAS, LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 505-7001 TMA (STATIONARY) | 33 DAY | $10.00 | $217.57 | 0.05x | -$6,850 |