IH 10: 0535-02-050; BR
0535-02-050 · let Aug 6, 2026 · Guadalupe, San Antonio · Bridge Replacement
$5,753,739Low bid: HUNTER INDUSTRIES, LTD.+0.9% vs estimate $5,699,899
$202,660Left on the table3.5% gap to the second bid
8BiddersSpread 38% low to high
110Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HUNTER INDUSTRIES, LTD. | $5,753,739 | 0.9% | $202,660 | 2+$243,256 | 2-$149,064 | |
| 2 | TEXAS STEEL INDUSTRIAL PLACING, LLC | $5,956,399 | +3.5% | 4.5% | $337,805 | 2+$295,867 | 0 |
| 3 | J3 COMPANY, LLC | $6,294,204 | +9.4% | 10.4% | $302,320 | 3+$270,547 | 0 |
| 4 | CAPITAL EXCAVATION COMPANY | $6,596,524 | +14.6% | 15.7% | $236,265 | 3+$290,866 | 1-$112,077 |
| 5 | DEAN WORD COMPANY, LTD. | $6,832,789 | +18.8% | 19.9% | $63,397 | 6+$791,391 | 1-$104,189 |
| 6 | E-Z BEL CONSTRUCTION, LLC | $6,896,186 | +19.9% | 21.0% | $266,839 | ||
| 7 | JOE BLAND CONSTRUCTION LLC | $7,163,025 | +24.5% | 25.7% | $792,779 | ||
| 8 | LUCANIA CONTRACTORS LLC | $7,955,804 | +38.3% | 39.6% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HUNTER INDUSTRIES, LTD. vs TEXAS STEEL INDUSTRIAL PLACING, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 422-7001 REINF CONC SLAB | 22,400 SF | $30.50 | $22.00 | $24.45 | -$190,400 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $25,000.00 | $12,000.00 | $11,585.04 | -$182,000 |
| 508-7001 CONSTRUCTING DETOURS | 1,628 SY | $71.92 | $165.00 | $83.58 | $151,534 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $189,807.74 | $300,000.00 | $136,676.66 | $110,192 |
| 100-7002 PREPARING ROW | 23 STA | $889.65 | $5,500.00 | $6,072.92 | $106,038 |
| 247-7089 FL BS (CMP IN PLC)(TY D GR1-2 OR 5)(8") | 9,148 SY | $14.42 | $25.00 | $14.42 | $96,786 |
| 420-7038 CL C CONC (COLUMN) | 148.9 CY | $1,900.00 | $1,400.00 | $1,548.37 | -$74,450 |
| 344-7030 SP MIXES SP-C SAC-A PG76-22 | 1,590 TON | $117.27 | $160.00 | $138.38 | $67,941 |
| 341-7001 D-GR HMA TY-B PG64-22 | 2,583 TON | $96.38 | $120.00 | $97.82 | $61,010 |
| 425-7004 PRESTR CONC GIRDER (TX46) | 2,883.89 LF | $200.00 | $220.00 | $236.72 | $57,678 |
| 420-7012 CL C CONC (ABUT) | 92.2 CY | $1,600.00 | $1,100.00 | $1,307.98 | -$46,100 |
| 420-7050 CL C CONC (CRASHWALL) | 62.5 CY | $1,900.00 | $1,200.00 | $1,012.86 | -$43,750 |
| 341-7015 D-GR HMA TY-C PG64-22 | 1,122 TON | $98.54 | $125.00 | $97.50 | $29,688 |
| 505-7001 TMA (STATIONARY) | 260 DAY | $102.77 | $200.00 | $217.57 | $25,280 |
| 500-7001 MOBILIZATION | 1 LS | $570,059.81 | $595,000.00 | $523,850.32 | $24,940 |
| 450-7024 RAIL (TY SSTR) | 708 LF | $67.00 | $100.00 | $69.92 | $23,364 |
| 400-7010 CEM STABIL BKFL | 340.3 CY | $125.00 | $185.00 | $138.14 | $20,418 |
| 512-7049 PORT CTB (REMOVE)(SGL SLP)(TY 1) | 2,310 LF | $13.00 | $20.00 | $12.08 | $16,170 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 1,307 CY | $35.97 | $25.00 | $16.96 | -$14,338 |
| 512-7001 PORT CTB (FUR & INST)(SGL SLOPE)(TY 1) | 2,310 LF | $36.00 | $30.00 | $52.29 | -$13,860 |
Positive: the low bidder was cheaper on that item. These 20 items account for $226,142 of the $202,660 gap.
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $25,000.00 | $11,585.04 | 2.16x | $187,809 |
| 420-7050 CL C CONC (CRASHWALL) | 62.5 CY | $1,900.00 | $1,012.86 | 1.88x | $55,446 |
| 100-7002 PREPARING ROW | 23 STA | $889.65 | $6,072.92 | 0.15x | -$119,215 |
| 505-7001 TMA (STATIONARY) | 260 DAY | $102.77 | $217.57 | 0.47x | -$29,848 |
TEXAS STEEL INDUSTRIAL PLACING, LLC: unbalanced items
Placed 2J3 COMPANY, LLC: unbalanced items
Placed 3CAPITAL EXCAVATION COMPANY: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7089 FL BS (CMP IN PLC)(TY D GR1-2 OR 5)(8") | 9,148 SY | $31.00 | $14.42 | 2.15x | $151,674 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $242,000.00 | $136,676.66 | 1.77x | $105,323 |
| 530-7010 DRIVEWAYS (ACP) | 349 SY | $152.00 | $54.96 | 2.77x | $33,869 |
| 100-7002 PREPARING ROW | 23 STA | $1,200.00 | $6,072.92 | 0.20x | -$112,077 |
DEAN WORD COMPANY, LTD.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 420-7038 CL C CONC (COLUMN) | 148.9 CY | $3,630.25 | $1,548.37 | 2.34x | $309,991 |
| 420-7022 CL C CONC (CAP) | 99.3 CY | $3,069.75 | $1,543.38 | 1.99x | $151,569 |
| 496-7010 REMOV STR (BRIDGE 100 - 499 FT LENGTH) | 1 EA | $279,227.00 | $136,676.66 | 2.04x | $142,550 |
| 505-7001 TMA (STATIONARY) | 260 DAY | $529.25 | $217.57 | 2.43x | $81,036 |
| 420-7050 CL C CONC (CRASHWALL) | 62.5 CY | $2,021.50 | $1,012.86 | 2.00x | $63,040 |
| 505-7003 TMA (MOBILE OPERATION) | 58 DAY | $974.50 | $229.60 | 4.24x | $43,204 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $4,143.00 | $11,585.04 | 0.36x | -$104,189 |