FY27 - Madison HMA - 11
6511-08-001 · let Nov 18, 2026 · Madison, Bryan · Material Maintenance Project
$270,750Low bid: KNIFE RIVER CORPORATION - SOUTH-12.7% vs estimate $310,000
$550Left on the table0.2% gap to the second bid
3BiddersSpread 11% low to high
2Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | KNIFE RIVER CORPORATION - SOUTH | $270,750 | -12.7% | $550 | 0 | 0 | |
| 2 | BIG CREEK CONSTRUCTION, LTD. | $271,300 | +0.2% | -12.5% | $28,400 | 0 | 0 |
| 3 | AMERICAN MATERIALS, INC. | $299,700 | +10.7% | -3.3% | 0 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
KNIFE RIVER CORPORATION - SOUTH vs BIG CREEK CONSTRUCTION, LTD., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 8011-7092 D-GR HMA TY F PG 64-22 (DEL) SITE 1 | 2,000 TON | $96.25 | $98.10 | $101.37 | $3,700 |
| 8011-7091 D-GR HMA TY F PG 64-22 (PICKUP) | 1,000 TON | $78.25 | $75.10 | $87.59 | -$3,150 |
Positive: the low bidder was cheaper on that item. These 2 items account for $550 of the $550 gap.