Bid Tab X-ray: 6511-06-001

Nov 17, 2026 · Freestone Sign up free
Set your company to personalize scores

FY27 - Freestone HMA - 11

6511-06-001 · let Nov 17, 2026 · Freestone, Bryan · Material Maintenance Project

$444,000Low bid: BIG CREEK CONSTRUCTION, LTD.-12.9% vs estimate $510,000
$37,500Left on the table8.4% gap to the second bid
3BiddersSpread 17% low to high
2Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1BIG CREEK CONSTRUCTION, LTD. $444,000-12.9% $37,500 0 0
2KNIFE RIVER CORPORATION - SOUTH $481,500+8.4%-5.6% $39,500 0 0
3AMERICAN MATERIALS, INC. $521,000+17.3%2.2% 0 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

BIG CREEK CONSTRUCTION, LTD. vs KNIFE RIVER CORPORATION - SOUTH, biggest item swings
ItemQtyLow2ndMarket2nd minus low
8011-7056 D-GR HMA TY D PG 64-22 (DEL) SITE 13,000 TON $98.00$105.50$99.54 $22,500
8011-7055 D-GR HMA TY D PG 64-22 (PICKUP)2,000 TON $75.00$82.50$89.12 $15,000

Positive: the low bidder was cheaper on that item. These 2 items account for $37,500 of the $37,500 gap.