RM 3237 from RM 150 to RM 12-FY 25(11SF)
0805-04-039 · let Nov 7, 2024 · Hays, Austin · Intersection & Operational Imprv
$4,963,084Low bid: DEAN WORD COMPANY, LTD.-18.7% vs estimate $6,105,603
$579,879Left on the table11.7% gap to the second bid
7BiddersSpread 48% low to high
101Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DEAN WORD COMPANY, LTD. | $4,963,084 | -18.7% | $579,879 | 7+$528,885 | 3-$216,810 | |
| 2 | TEXAS MATERIALS GROUP, INC. | $5,542,963 | +11.7% | -9.2% | $379,846 | 7+$687,476 | 1-$95,323 |
| 3 | HUNTER INDUSTRIES, LTD. | $5,922,810 | +19.3% | -3.0% | $96,651 | 6+$665,070 | 1-$74,384 |
| 4 | AARON CONCRETE CONTRACTORS, LLC | $6,019,461 | +21.3% | -1.4% | $117,666 | 11+$708,525 | 2-$370,028 |
| 5 | LONE STAR SITEWORK, LLC | $6,137,127 | +23.7% | 0.5% | $355,517 | 12+$1,169,618 | 3-$805,323 |
| 6 | ALTUS CONSTRUCTION LLC | $6,492,643 | +30.8% | 6.3% | $856,279 | ||
| 7 | DAN WILLIAMS COMPANY | $7,348,922 | +48.1% | 20.4% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
DEAN WORD COMPANY, LTD. vs TEXAS MATERIALS GROUP, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 132-7003 EMBANK (FNL)(OC)(TY B) | 9,872 CY | $41.10 | $16.15 | $16.96 | -$246,306 |
| 110-7001 EXCAV (ROADWAY) | 12,593 CY | $8.20 | $27.00 | $11.68 | $236,748 |
| 342-7001 PFC-C PG76-22 SAC-A | 1,917 TON | $129.50 | $215.00 | $170.34 | $163,904 |
| 500-7001 MOBILIZATION | 1 LS | $450,000.00 | $539,000.00 | $523,850.32 | $89,000 |
| 464-7007 RC PIPE (CL III)(30 IN) | 354 LF | $128.40 | $366.00 | $140.03 | $84,110 |
| 341-7003 D-GR HMA TY-B PG64-22 (EXEMPT) | 3,738 TON | $78.00 | $100.00 | $127.48 | $82,236 |
| 341-7059 D-GR HMA TY-D PG76-22 (LEVEL-UP) | 1,000 TON | $88.00 | $153.00 | $115.04 | $65,000 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 17,390 LF | $4.20 | $7.77 | $2.80 | $62,082 |
| 462-7021 CONC BOX CULV (8 FT X 4 FT) | 136 LF | $1,400.30 | $1,836.00 | $765.77 | $59,255 |
| 423-7012 RETAINING WALL (TEMP WALL) | 1,600 SF | $37.40 | $71.00 | $22.94 | $53,760 |
| 351-7005 FLEXIBLE PAVEMENT STRUCTURE REPAIR(6") | 3,022 SY | $38.60 | $54.00 | $49.06 | $46,539 |
| 512-7093 PORT CTB (FURN & INST)(TL-3 LPCB) | 240 LF | $13.70 | $200.00 | $67.00 | $44,712 |
| 100-7002 PREPARING ROW | 53.1 STA | $4,350.00 | $3,600.00 | $6,072.92 | -$39,825 |
| 247-7179 FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS) | 4,845 CY | $83.10 | $74.90 | $63.96 | -$39,729 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 1,680 LF | $13.70 | $37.00 | $38.28 | $39,144 |
| 341-7065 D-GR HMA TY-D PG 76-22 (EXEMPT) | 1,472 TON | $111.00 | $135.00 | $111.42 | $35,328 |
| 530-7010 DRIVEWAYS (ACP) | 2,217 SY | $72.50 | $88.00 | $54.96 | $34,364 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 50 DAY | $911.00 | $250.00 | $87.82 | -$33,050 |
| 169-7001 SOIL RET BLKT(SL_MOD_CLAY_SHORT) | 31,784 SY | $2.50 | $1.50 | $1.27 | -$31,784 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 14 EA | $7,398.80 | $9,280.00 | $8,780.51 | $26,337 |
Positive: the low bidder was cheaper on that item. These 20 items account for $731,825 of the $579,879 gap.
DEAN WORD COMPANY, LTD.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 132-7003 EMBANK (FNL)(OC)(TY B) | 9,872 CY | $41.10 | $16.96 | 2.42x | $238,278 |
| 462-7021 CONC BOX CULV (8 FT X 4 FT) | 136 LF | $1,400.30 | $765.77 | 1.83x | $86,296 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 31,784 SY | $3.20 | $1.43 | 2.24x | $56,280 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 50 DAY | $911.00 | $87.82 | 10.37x | $41,159 |
| 169-7001 SOIL RET BLKT(SL_MOD_CLAY_SHORT) | 31,784 SY | $2.50 | $1.27 | 1.96x | $39,021 |
| 168-7001 VEGETATIVE WATERING | 1,271 TGL | $39.10 | $8.43 | 4.64x | $38,977 |
| 666-7265 RE PROFILE PM TY I(W)6"(SLD)(090MIL) | 9,918 LF | $3.50 | $0.5887 | 5.95x | $28,874 |
| 505-7001 TMA (STATIONARY) | 495 DAY | $34.70 | $217.57 | 0.16x | -$90,521 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $5,047.20 | $11,585.04 | 0.44x | -$84,992 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 1,680 LF | $13.70 | $38.28 | 0.36x | -$41,296 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 12,593 CY | $27.00 | $11.68 | 2.31x | $192,897 |
| 462-7021 CONC BOX CULV (8 FT X 4 FT) | 136 LF | $1,836.00 | $765.77 | 2.40x | $145,551 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 17,390 LF | $7.77 | $2.80 | 2.78x | $86,465 |
| 464-7007 RC PIPE (CL III)(30 IN) | 354 LF | $366.00 | $140.03 | 2.61x | $79,993 |
| 423-7012 RETAINING WALL (TEMP WALL) | 1,600 SF | $71.00 | $22.94 | 3.09x | $76,888 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 31,784 SY | $3.75 | $1.43 | 2.62x | $73,761 |
| 512-7093 PORT CTB (FURN & INST)(TL-3 LPCB) | 240 LF | $200.00 | $67.00 | 2.99x | $31,920 |
| 505-7001 TMA (STATIONARY) | 495 DAY | $25.00 | $217.57 | 0.11x | -$95,323 |
HUNTER INDUSTRIES, LTD.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 12,593 CY | $28.00 | $11.68 | 2.40x | $205,490 |
| 462-7021 CONC BOX CULV (8 FT X 4 FT) | 136 LF | $2,082.54 | $765.77 | 2.72x | $179,081 |
| 464-7007 RC PIPE (CL III)(30 IN) | 354 LF | $415.30 | $140.03 | 2.97x | $97,446 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 17,390 LF | $7.99 | $2.80 | 2.86x | $90,291 |
| 512-7085 PTB (FUR&INST)(SSCB OR CSB)(TY1)OR(STL) | 1,680 LF | $75.00 | $38.28 | 1.96x | $61,688 |
| 169-7001 SOIL RET BLKT(SL_MOD_CLAY_SHORT) | 31,784 SY | $2.25 | $1.27 | 1.77x | $31,075 |
| 505-7001 TMA (STATIONARY) | 495 DAY | $67.30 | $217.57 | 0.31x | -$74,384 |
AARON CONCRETE CONTRACTORS, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 530-7010 DRIVEWAYS (ACP) | 2,217 SY | $117.00 | $54.96 | 2.13x | $137,553 |
| 668-7002 PRFB RUMBLE STRIP (BLK)(1')(CENTERLINE) | 17,390 LF | $10.00 | $2.80 | 3.57x | $125,245 |
| 462-7021 CONC BOX CULV (8 FT X 4 FT) | 136 LF | $1,400.00 | $765.77 | 1.83x | $86,255 |
| 423-7012 RETAINING WALL (TEMP WALL) | 1,600 SF | $63.00 | $22.94 | 2.75x | $64,088 |
| 505-7003 TMA (MOBILE OPERATION) | 130 DAY | $680.00 | $229.60 | 2.96x | $58,552 |
| 169-7001 SOIL RET BLKT(SL_MOD_CLAY_SHORT) | 31,784 SY | $2.80 | $1.27 | 2.20x | $48,556 |
| 512-7093 PORT CTB (FURN & INST)(TL-3 LPCB) | 240 LF | $240.00 | $67.00 | 3.58x | $41,520 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 31,784 SY | $2.70 | $1.43 | 1.89x | $40,388 |
| 400-7008 CUT & RESTORE ASPH PAVING | 55 SY | $840.00 | $140.13 | 5.99x | $38,493 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 61 CY | $1,176.00 | $616.83 | 1.91x | $34,109 |
| 100-7002 PREPARING ROW | 53.1 STA | $1,500.00 | $6,072.92 | 0.25x | -$242,822 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $1,800.00 | $11,585.04 | 0.16x | -$127,206 |
LONE STAR SITEWORK, LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 423-7012 RETAINING WALL (TEMP WALL) | 1,600 SF | $140.00 | $22.94 | 6.10x | $187,288 |
| 403-7001 TEMPORARY SPL SHORING | 1,296 SF | $150.00 | $25.56 | 5.87x | $161,273 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 31,784 SY | $6.50 | $1.43 | 4.55x | $161,167 |
| 462-7021 CONC BOX CULV (8 FT X 4 FT) | 136 LF | $1,760.00 | $765.77 | 2.30x | $135,215 |
| 505-7001 TMA (STATIONARY) | 495 DAY | $450.00 | $217.57 | 2.07x | $115,052 |
| 530-7010 DRIVEWAYS (ACP) | 2,217 SY | $100.00 | $54.96 | 1.82x | $99,864 |
| 505-7003 TMA (MOBILE OPERATION) | 130 DAY | $900.00 | $229.60 | 3.92x | $87,152 |
| 168-7001 VEGETATIVE WATERING | 1,271 TGL | $66.00 | $8.43 | 7.83x | $73,167 |
| 464-7007 RC PIPE (CL III)(30 IN) | 354 LF | $272.00 | $140.03 | 1.94x | $46,717 |
| 467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P) | 6 EA | $8,400.00 | $1,883.43 | 4.46x | $39,099 |
| 500-7001 MOBILIZATION | 1 LS | $137,700.00 | $523,850.32 | 0.26x | -$386,150 |
| 100-7002 PREPARING ROW | 53.1 STA | $550.00 | $6,072.92 | 0.09x | -$293,267 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 13 MO | $1,900.00 | $11,585.04 | 0.16x | -$125,906 |