FY 25 Athens RDC Pre-Packaged Concrete
6475-64-001 · let Dec 4, 2024 · Henderson, Maintenance Division · Material Maintenance Project
$151,980Low bid: AKA-MATERIALS-25.5% vs estimate $204,000
$1,020Left on the table0.7% gap to the second bid
6BiddersSpread 258% low to high
1Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | AKA-MATERIALS | $151,980 | -25.5% | $1,020 | 0 | 0 | |
| 2 | TOUCHSTONE RESOURCES, LLC | $153,000 | +0.7% | -25.0% | $5,882 | 0 | 0 |
| 3 | SOUTHERN SOURCING SOLUTIONS, LLC | $158,882 | +4.5% | -22.1% | $44,098 | 0 | 0 |
| 4 | SKYLINE BRIDGE LLC | $202,980 | +33.6% | -0.5% | $64,260 | 0 | 0 |
| 5 | USA AMTECH, INC. | $267,240 | +75.8% | 31.0% | $276,760 | 1+$115,260 | 0 |
| 6 | TUFFTEX MATERIALS | $544,000 | +257.9% | 166.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
AKA-MATERIALS vs TOUCHSTONE RESOURCES, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 7032-7002 PREPACKAGED CONCRETE (DEL)(ST2) | 34,000 BAG | $4.47 | $4.50 | $4.47 | $1,020 |
Positive: the low bidder was cheaper on that item. These 1 items account for $1,020 of the $1,020 gap.
USA AMTECH, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 7032-7002 PREPACKAGED CONCRETE (DEL)(ST2) | 34,000 BAG | $7.86 | $4.47 | 1.76x | $115,260 |