Bid Tab X-ray: 6475-64-001

Dec 4, 2024 · Henderson Sign up free
Set your company to personalize scores

FY 25 Athens RDC Pre-Packaged Concrete

6475-64-001 · let Dec 4, 2024 · Henderson, Maintenance Division · Material Maintenance Project

$151,980Low bid: AKA-MATERIALS-25.5% vs estimate $204,000
$1,020Left on the table0.7% gap to the second bid
6BiddersSpread 258% low to high
1Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1AKA-MATERIALS $151,980-25.5% $1,020 0 0
2TOUCHSTONE RESOURCES, LLC $153,000+0.7%-25.0% $5,882 0 0
3SOUTHERN SOURCING SOLUTIONS, LLC $158,882+4.5%-22.1% $44,098 0 0
4SKYLINE BRIDGE LLC $202,980+33.6%-0.5% $64,260 0 0
5USA AMTECH, INC. $267,240+75.8%31.0% $276,760 1+$115,260 0
6TUFFTEX MATERIALS $544,000+257.9%166.7%

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

AKA-MATERIALS vs TOUCHSTONE RESOURCES, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
7032-7002 PREPACKAGED CONCRETE (DEL)(ST2)34,000 BAG $4.47$4.50$4.47 $1,020

Positive: the low bidder was cheaper on that item. These 1 items account for $1,020 of the $1,020 gap.

USA AMTECH, INC.: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
7032-7002 PREPACKAGED CONCRETE (DEL)(ST2)34,000 BAG $7.86$4.471.76x$115,260