US67_REAGAN_C/L_E_OF_CR225
0076-07-040 · let Jan 8, 2025 · Upton, Odessa · Super-2 Highway
$13,723,466Low bid: JONES BROS. DIRT & PAVING CONTRACTORS, INC.-32.7% vs estimate $20,376,775
$169,535Left on the table1.2% gap to the second bid
4BiddersSpread 35% low to high
95Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | $13,723,466 | -32.7% | $169,535 | 3+$1,061,690 | 1-$139,536 | |
| 2 | REECE ALBERT, INC. | $13,893,001 | +1.2% | -31.8% | $3,098,348 | 0 | 6-$1,097,175 |
| 3 | CK NEWBERRY, LLC | $16,991,349 | +23.8% | -16.6% | $1,508,651 | 2+$1,341,864 | 0 |
| 4 | RK HALL, LLC | $18,500,000 | +34.8% | -9.2% | 6+$2,002,805 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
JONES BROS. DIRT & PAVING CONTRACTORS, INC. vs REECE ALBERT, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7005 SP MIXES SP-B SAC-B PG70-22 | 43,320 TON | $105.00 | $144.23 | $94.47 | $1,699,444 |
| 346-7023 STONE-MTRX-ASPH SMAR-F SAC-A | 12,752 TON | $143.00 | $201.17 | $122.43 | $741,784 |
| 110-7001 EXCAV (ROADWAY) | 65,867 CY | $12.44 | $3.75 | $11.68 | -$572,384 |
| 500-7001 MOBILIZATION | 1 LS | $1,250,000.00 | $899,483.65 | $523,850.32 | -$350,516 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $30,000.00 | $5,382.37 | $11,585.04 | -$344,647 |
| 247-7069 FL BS (CMP IN PLC)(TY A GR 4) (8") | 45,389 SY | $12.75 | $15.83 | $17.87 | $139,798 |
| 403-7001 TEMPORARY SPL SHORING | 2,842 SF | $38.50 | $0.4700 | $25.56 | -$108,081 |
| 508-7001 CONSTRUCTING DETOURS | 2,872 SY | $35.00 | $0.4600 | $83.58 | -$99,199 |
| 666-7270 RE PROFILE PM TY I(Y)6"(SLD)(100MIL) | 119,152 LF | $0.9400 | $0.1100 | $0.6629 | -$98,896 |
| 666-7266 RE PROFILE PM TY I(W)6"(SLD)(100MIL) | 116,048 LF | $0.9400 | $0.1000 | $0.6515 | -$97,480 |
| 677-7002 ELIM EXT PM & MRKS (6") | 457,172 LF | $0.2500 | $0.0400 | $0.2755 | -$96,006 |
| 512-7086 PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL) | 8,430 LF | $13.75 | $3.70 | $9.41 | -$84,722 |
| 545-7002 CRASH CUSH ATTEN (MOVE & RESET) | 36 EA | $2,750.00 | $420.73 | $1,471.00 | -$83,854 |
| 3007-7001 BONDING COURSE | 30,765 GAL | $5.11 | $2.51 | $3.32 | -$79,989 |
| 251-7083 REWORK BS MTL (TY D)(SURF)(ORD COMP) | 114,395 SY | $0.6400 | $0.1000 | $0.5657 | -$61,773 |
| 545-7014 CRASH CUSH ATTEN (INSTL)(S)(N)(TL3) | 12 EA | $9,625.00 | $5,020.31 | $8,780.51 | -$55,256 |
| 164-7009 DRILL SEED (PERM_RURAL_SAND) | 258,106 SY | $0.2200 | $0.0200 | $0.1844 | -$51,621 |
| 467-7006 SET (TY I) (24 IN) (4: 1) (C) | 4 EA | $3,357.20 | $16,129.09 | $3,340.28 | $51,088 |
| 480-7001 CLEAN EXIST CULVERTS | 25 EA | $1,980.00 | $131.87 | $1,712.97 | -$46,203 |
| 316-7136 AGGR (TY-PB, GR-4)(SAC-A) | 1,400 CY | $180.00 | $210.35 | $137.54 | $42,490 |
Positive: the low bidder was cheaper on that item. These 20 items account for $443,975 of the $169,535 gap.
JONES BROS. DIRT & PAVING CONTRACTORS, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,250,000.00 | $523,850.32 | 2.39x | $726,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $30,000.00 | $11,585.04 | 2.59x | $257,809 |
| 341-7024 D-GR HMA TY-C SAC-B PG70-22 | 547 TON | $255.00 | $112.90 | 2.26x | $77,731 |
| 508-7001 CONSTRUCTING DETOURS | 2,872 SY | $35.00 | $83.58 | 0.42x | -$139,536 |
REECE ALBERT, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 110-7001 EXCAV (ROADWAY) | 65,867 CY | $3.75 | $11.68 | 0.32x | -$522,470 |
| 508-7001 CONSTRUCTING DETOURS | 2,872 SY | $0.4600 | $83.58 | 0.01x | -$238,735 |
| 677-7002 ELIM EXT PM & MRKS (6") | 457,172 LF | $0.0400 | $0.2755 | 0.15x | -$107,664 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $5,382.37 | $11,585.04 | 0.46x | -$86,837 |
| 403-7001 TEMPORARY SPL SHORING | 2,842 SF | $0.4700 | $25.56 | 0.02x | -$71,307 |
| 505-7001 TMA (STATIONARY) | 400 DAY | $42.17 | $217.57 | 0.19x | -$70,161 |
CK NEWBERRY, LLC: unbalanced items
Placed 3RK HALL, LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,600,980.51 | $523,850.32 | 3.06x | $1,077,130 |
| 677-7002 ELIM EXT PM & MRKS (6") | 457,172 LF | $0.9400 | $0.2755 | 3.41x | $303,791 |
| 251-7083 REWORK BS MTL (TY D)(SURF)(ORD COMP) | 114,395 SY | $2.22 | $0.5657 | 3.92x | $189,244 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 14 MO | $24,699.07 | $11,585.04 | 2.13x | $183,596 |
| 100-7002 PREPARING ROW | 2 STA | $73,317.62 | $6,072.92 | 12.07x | $134,489 |
| 512-7086 PTB (MOVE)(SSCB OR CSB)(TY1)OR(STL) | 8,430 LF | $23.00 | $9.41 | 2.44x | $114,554 |