SH 171; US 377 TO SH 174
0365-03-050 · let Feb 6, 2025 · Johnson, Fort Worth · Rehabilitation of Existing Road
$26,976,280Low bid: JAY MILLS CONTRACTING, INCORPORATED-16.6% vs estimate $32,329,714
$1,281,444Left on the table4.8% gap to the second bid
4BiddersSpread 11% low to high
289Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | JAY MILLS CONTRACTING, INCORPORATED | $26,976,280 | -16.6% | $1,281,444 | 6+$2,896,789 | 2-$3,623,330 | |
| 2 | ED BELL CONSTRUCTION COMPANY | $28,257,724 | +4.8% | -12.6% | $0 | 8+$4,599,747 | 2-$5,431,659 |
| 2 | REYNOLDS ASPHALT & CONSTRUCTION COMPANY | $28,257,724 | +4.8% | -12.6% | $1,717,743 | 8+$4,599,747 | 2-$5,431,659 |
| 3 | TEXAS MATERIALS GROUP, INC. | $29,975,467 | +11.1% | -7.3% | 7+$6,655,672 | 2-$5,404,899 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
JAY MILLS CONTRACTING, INCORPORATED vs ED BELL CONSTRUCTION COMPANY, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 928 STA | $2,500.00 | $450.00 | $6,072.92 | -$1,902,400 |
| 500-7001 MOBILIZATION | 1 LS | $1,500,000.00 | $3,000,000.00 | $523,850.32 | $1,500,000 |
| 344-7024 SP MIXES SP-C SAC-A PG70-28 | 54,637 TON | $178.00 | $198.50 | $156.36 | $1,120,059 |
| 354-7002 PLANE & TEXT ASPH CONC PAV(0" TO 2") | 463,095 SY | $3.00 | $3.75 | $2.24 | $347,321 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 11,279 SY | $35.00 | $12.00 | $3.93 | -$259,417 |
| 505-7001 TMA (STATIONARY) | 1,364 DAY | $350.00 | $175.00 | $217.57 | -$238,700 |
| 496-7005 REMOV STR (WINGWALL) | 39 EA | $950.00 | $5,000.00 | $1,898.40 | $157,950 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 259 CY | $725.00 | $1,150.00 | $616.83 | $110,075 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 1,952 CY | $50.00 | $105.00 | $12.93 | $107,360 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 15,356 SY | $6.00 | $12.60 | $1.95 | $101,350 |
| 344-7077 TACK COAT | 95,021 GAL | $0.0100 | $1.00 | $3.25 | $94,071 |
| 466-7175 WINGWALL (PW - 1) (HW=5 FT) | 10 EA | $16,250.00 | $25,000.00 | $23,385.57 | $87,500 |
| 351-7009 FLEXIBLE PAVEMENT STRUCTURE REPAIR(10") | 16,262 SY | $105.00 | $100.00 | $77.78 | -$81,310 |
| 403-7001 TEMPORARY SPL SHORING | 1,905 SF | $60.00 | $100.00 | $25.56 | $76,200 |
| 760-7001 DITCH CLEANING AND RESHAPING (FOOT) | 3,800 LF | $5.00 | $25.00 | $1.96 | $76,000 |
| 545-7002 CRASH CUSH ATTEN (MOVE & RESET) | 80 EA | $2,400.00 | $1,500.00 | $1,471.00 | -$72,000 |
| 134-7002 BACKFILL (TY B) | 200 STA | $385.00 | $735.00 | $206.94 | $70,000 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 34 MO | $40,000.00 | $42,000.00 | $11,585.04 | $68,000 |
| 730-7018 STRIP MOWING | 8 CYC | $5,000.00 | $12,000.00 | $619.52 | $56,000 |
| 341-7002 D-GR HMA TY-B SAC-B PG64-22 | 2,764 TON | $140.00 | $160.00 | $109.80 | $55,280 |
Positive: the low bidder was cheaper on that item. These 20 items account for $1,473,338 of the $1,281,444 gap.
JAY MILLS CONTRACTING, INCORPORATED: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $1,500,000.00 | $523,850.32 | 2.86x | $976,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 34 MO | $40,000.00 | $11,585.04 | 3.45x | $966,109 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 11,279 SY | $35.00 | $3.93 | 8.92x | $350,489 |
| 400-7008 CUT & RESTORE ASPH PAVING | 446 SY | $650.00 | $140.13 | 4.64x | $227,402 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 12,802 SY | $30.00 | $12.30 | 2.44x | $226,652 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 4,620 LF | $40.00 | $7.54 | 5.31x | $149,988 |
| 100-7002 PREPARING ROW | 928 STA | $2,500.00 | $6,072.92 | 0.41x | -$3,315,671 |
| 344-7077 TACK COAT | 95,021 GAL | $0.0100 | $3.25 | 0.00x | -$307,659 |
ED BELL CONSTRUCTION COMPANY: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,000,000.00 | $523,850.32 | 5.73x | $2,476,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 34 MO | $42,000.00 | $11,585.04 | 3.63x | $1,034,109 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 12,802 SY | $30.00 | $12.30 | 2.44x | $226,652 |
| 400-7008 CUT & RESTORE ASPH PAVING | 446 SY | $630.00 | $140.13 | 4.50x | $218,482 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 1,952 CY | $105.00 | $12.93 | 8.12x | $179,729 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 15,356 SY | $12.60 | $1.95 | 6.47x | $163,591 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 4,620 LF | $42.00 | $7.54 | 5.57x | $159,228 |
| 403-7001 TEMPORARY SPL SHORING | 1,905 SF | $100.00 | $25.56 | 3.91x | $141,807 |
| 100-7002 PREPARING ROW | 928 STA | $450.00 | $6,072.92 | 0.07x | -$5,218,071 |
| 344-7077 TACK COAT | 95,021 GAL | $1.00 | $3.25 | 0.31x | -$213,588 |
REYNOLDS ASPHALT & CONSTRUCTION COMPANY: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $3,000,000.00 | $523,850.32 | 5.73x | $2,476,150 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 34 MO | $42,000.00 | $11,585.04 | 3.63x | $1,034,109 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 12,802 SY | $30.00 | $12.30 | 2.44x | $226,652 |
| 400-7008 CUT & RESTORE ASPH PAVING | 446 SY | $630.00 | $140.13 | 4.50x | $218,482 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 1,952 CY | $105.00 | $12.93 | 8.12x | $179,729 |
| 161-7002 COMPOST MANUF TOPSOIL (4") | 15,356 SY | $12.60 | $1.95 | 6.47x | $163,591 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 4,620 LF | $42.00 | $7.54 | 5.57x | $159,228 |
| 403-7001 TEMPORARY SPL SHORING | 1,905 SF | $100.00 | $25.56 | 3.91x | $141,807 |
| 100-7002 PREPARING ROW | 928 STA | $450.00 | $6,072.92 | 0.07x | -$5,218,071 |
| 344-7077 TACK COAT | 95,021 GAL | $1.00 | $3.25 | 0.31x | -$213,588 |
TEXAS MATERIALS GROUP, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 34 MO | $100,000.00 | $11,585.04 | 8.63x | $3,006,109 |
| 500-7001 MOBILIZATION | 1 LS | $3,000,410.00 | $523,850.32 | 5.73x | $2,476,560 |
| 341-7002 D-GR HMA TY-B SAC-B PG64-22 | 2,764 TON | $220.00 | $109.80 | 2.00x | $304,604 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 12,802 SY | $36.00 | $12.30 | 2.93x | $303,464 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 11,279 SY | $26.00 | $3.93 | 6.62x | $248,978 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 8 EA | $30,000.00 | $9,253.78 | 3.24x | $165,970 |
| 512-7025 PORT CTB (MOVE)(SGL SLP)(TY 1) | 4,620 LF | $40.00 | $7.54 | 5.31x | $149,988 |
| 100-7002 PREPARING ROW | 928 STA | $567.00 | $6,072.92 | 0.09x | -$5,109,495 |
| 505-7001 TMA (STATIONARY) | 1,364 DAY | $1.00 | $217.57 | 0.00x | -$295,404 |