BI 45-F at Post Oak Creek
0092-13-031 · let May 1, 2025 · Navarro, Dallas · Bridge Replacement
$3,850,000Low bid: PMCO CONSTRUCTION LLC-9.0% vs estimate $4,230,373
$131,746Left on the table3.4% gap to the second bid
10BiddersSpread 32% low to high
89Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | PMCO CONSTRUCTION LLC | $3,850,000 | -9.0% | $131,746 | 7+$379,187 | 0 | |
| 2 | TALBERT COMPANIES LLC | $3,981,746 | +3.4% | -5.9% | $246,965 | 9+$381,835 | 1-$22,049 |
| 3 | ED BELL CONSTRUCTION COMPANY | $4,228,711 | +9.8% | 0.0% | $18,832 | 13+$609,154 | 0 |
| 4 | ALTUS CONSTRUCTION LLC | $4,247,543 | +10.3% | 0.4% | $251,378 | 7+$720,026 | 0 |
| 5 | URBAN INFRACONSTRUCTION LLC | $4,498,921 | +16.9% | 6.3% | $23,503 | 13+$828,281 | 0 |
| 6 | A. L. HELMCAMP, INC. | $4,522,424 | +17.5% | 6.9% | $237,638 | ||
| 7 | GREY SKY CONSTRUCTION LLC | $4,760,062 | +23.6% | 12.5% | $31,535 | ||
| 8 | RAGLE CONSTRUCTION, INC. | $4,791,597 | +24.5% | 13.3% | $70,109 | ||
| 9 | COPPELL CONSTRUCTION CO., INC. | $4,861,707 | +26.3% | 14.9% | $233,668 | ||
| 10 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $5,095,375 | +32.3% | 20.4% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
PMCO CONSTRUCTION LLC vs TALBERT COMPANIES LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $360,000.00 | $447,944.95 | $523,850.32 | $87,945 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 698 CY | $165.00 | $275.00 | $179.97 | $76,780 |
| 344-7001 SP MIXES SP-B PG64-22 | 408 TON | $325.00 | $148.50 | $124.45 | -$72,012 |
| 422-7008 REINF CONC SLAB (SLAB BEAM)(HPC) | 8,960 SF | $26.00 | $33.00 | $28.14 | $62,720 |
| 423-7015 RETAINING WALL (SPREAD FOOTING) | 286 SF | $360.00 | $154.00 | $107.44 | -$58,916 |
| 168-7001 VEGETATIVE WATERING | 340 TGL | $25.00 | $181.50 | $8.43 | $53,210 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 3,695 SY | $8.00 | $22.00 | $6.84 | $51,730 |
| 344-7021 SP MIXES SP-C SAC-B PG70-22 | 3,550 TON | $131.00 | $143.00 | $120.21 | $42,600 |
| 104-7001 REMOV CONC (PAV) | 2,348 SY | $18.00 | $33.00 | $11.85 | $35,220 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 10 MO | $7,000.00 | $10,450.00 | $11,585.04 | $34,500 |
| 450-7033 RAIL (TY C221)(HPC) | 432 LF | $170.00 | $246.71 | $144.01 | $33,140 |
| 247-7102 FL BS (CMP IN PLC)(TY D GR 1-2) (10") | 2,109 SY | $65.00 | $49.50 | $25.28 | -$32,690 |
| 425-7018 PRESTR CONC SLAB BEAM (4SB15) | 415.5 LF | $263.00 | $187.74 | $233.81 | -$31,272 |
| 260-7006 LIME TRT (EXIST MATL)(6") | 2,135 SY | $25.00 | $11.15 | $3.80 | -$29,561 |
| 677-7002 ELIM EXT PM & MRKS (6") | 53,870 LF | $0.5200 | $0.9350 | $0.2755 | $22,356 |
| 416-7004 DRILL SHAFT (24 IN) | 480 LF | $195.00 | $148.50 | $234.98 | -$22,320 |
| 416-7005 DRILL SHAFT (30 IN) | 318 LF | $300.00 | $231.00 | $239.74 | -$21,942 |
| 425-7019 PRESTR CONC SLAB BEAM (5SB15) | 1,385 LF | $203.00 | $187.74 | $261.75 | -$21,139 |
| 100-7002 PREPARING ROW | 5.27 STA | $5,886.00 | $1,888.99 | $6,072.92 | -$21,064 |
| 454-7004 SEALED EXPANSION JOINT (4 IN) (SEJ - M) | 126 LF | $125.00 | $291.50 | $221.89 | $20,979 |
Positive: the low bidder was cheaper on that item. These 20 items account for $210,264 of the $131,746 gap.
PMCO CONSTRUCTION LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 247-7102 FL BS (CMP IN PLC)(TY D GR 1-2) (10") | 2,109 SY | $65.00 | $25.28 | 2.57x | $83,769 |
| 344-7001 SP MIXES SP-B PG64-22 | 408 TON | $325.00 | $124.45 | 2.61x | $81,825 |
| 423-7015 RETAINING WALL (SPREAD FOOTING) | 286 SF | $360.00 | $107.44 | 3.35x | $72,231 |
| 260-7006 LIME TRT (EXIST MATL)(6") | 2,135 SY | $25.00 | $3.80 | 6.59x | $45,270 |
| 354-7019 PLANE & TEXT ASPH CONC PAV(2") | 30,397 SY | $3.00 | $1.62 | 1.85x | $42,030 |
| 400-7010 CEM STABIL BKFL | 188 CY | $300.00 | $138.14 | 2.17x | $30,429 |
| 508-7001 CONSTRUCTING DETOURS | 203 SY | $200.00 | $83.58 | 2.39x | $23,632 |
TALBERT COMPANIES LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 168-7001 VEGETATIVE WATERING | 340 TGL | $181.50 | $8.43 | 21.52x | $58,843 |
| 105-7002 RMV (2"-6") TRT/UNTRT BASE & ASPH PAV | 3,695 SY | $22.00 | $6.84 | 3.22x | $56,027 |
| 354-7019 PLANE & TEXT ASPH CONC PAV(2") | 30,397 SY | $3.30 | $1.62 | 2.04x | $51,149 |
| 247-7102 FL BS (CMP IN PLC)(TY D GR 1-2) (10") | 2,109 SY | $49.50 | $25.28 | 1.96x | $51,079 |
| 104-7001 REMOV CONC (PAV) | 2,348 SY | $33.00 | $11.85 | 2.79x | $49,664 |
| 677-7002 ELIM EXT PM & MRKS (6") | 53,870 LF | $0.9350 | $0.2755 | 3.39x | $35,527 |
| 400-7010 CEM STABIL BKFL | 188 CY | $319.00 | $138.14 | 2.31x | $34,001 |
| 529-7009 CONC CURB & GUTTER (TY II) | 550 LF | $75.90 | $32.57 | 2.33x | $23,832 |
| 512-7029 PORT CTB (MOVE)(F-SHAPE)(TY 1) | 1,110 LF | $28.60 | $9.04 | 3.16x | $21,712 |
| 100-7002 PREPARING ROW | 5.27 STA | $1,888.99 | $6,072.92 | 0.31x | -$22,049 |
ED BELL CONSTRUCTION COMPANY: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 698 CY | $315.00 | $179.97 | 1.75x | $94,251 |
| 100-7002 PREPARING ROW | 5.27 STA | $21,000.00 | $6,072.92 | 3.46x | $78,666 |
| 423-7015 RETAINING WALL (SPREAD FOOTING) | 286 SF | $343.00 | $107.44 | 3.19x | $67,369 |
| 420-7013 CL C CONC (ABUT)(HPC) | 38.6 CY | $3,000.00 | $1,329.26 | 2.26x | $64,491 |
| 247-7102 FL BS (CMP IN PLC)(TY D GR 1-2) (10") | 2,109 SY | $50.00 | $25.28 | 1.98x | $52,134 |
| 420-7023 CL C CONC (CAP)(HPC) | 30.8 CY | $3,000.00 | $1,420.15 | 2.11x | $48,659 |
| 420-7039 CL C CONC (COLUMN)(HPC) | 18.8 CY | $4,000.00 | $1,492.16 | 2.68x | $47,147 |
| 400-7010 CEM STABIL BKFL | 188 CY | $350.00 | $138.14 | 2.53x | $39,829 |
| 508-7001 CONSTRUCTING DETOURS | 203 SY | $210.00 | $83.58 | 2.51x | $25,662 |
| 132-7008 EMBANK (FNL)(DC)(TY C1) | 431 CY | $73.50 | $17.39 | 4.23x | $24,184 |
ALTUS CONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 5.27 STA | $79,791.30 | $6,072.92 | 13.14x | $388,496 |
| 344-7001 SP MIXES SP-B PG64-22 | 408 TON | $380.64 | $124.45 | 3.06x | $104,526 |
| 450-7033 RAIL (TY C221)(HPC) | 432 LF | $294.21 | $144.01 | 2.04x | $64,885 |
| 420-7013 CL C CONC (ABUT)(HPC) | 38.6 CY | $2,677.33 | $1,329.26 | 2.01x | $52,036 |
| 420-7023 CL C CONC (CAP)(HPC) | 30.8 CY | $2,839.89 | $1,420.15 | 2.00x | $43,728 |
| 422-7022 BRIDGE SIDEWALK(HPC) | 1,680 SF | $36.71 | $14.80 | 2.48x | $36,813 |
| 104-7001 REMOV CONC (PAV) | 2,348 SY | $24.43 | $11.85 | 2.06x | $29,542 |
URBAN INFRACONSTRUCTION LLC: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 5.27 STA | $35,000.00 | $6,072.92 | 5.76x | $152,446 |
| 344-7001 SP MIXES SP-B PG64-22 | 408 TON | $365.00 | $124.45 | 2.93x | $98,145 |
| 423-7015 RETAINING WALL (SPREAD FOOTING) | 286 SF | $430.00 | $107.44 | 4.00x | $92,251 |
| 420-7013 CL C CONC (ABUT)(HPC) | 38.6 CY | $3,600.00 | $1,329.26 | 2.71x | $87,651 |
| 450-7033 RAIL (TY C221)(HPC) | 432 LF | $300.00 | $144.01 | 2.08x | $67,387 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 2 EA | $40,000.00 | $9,253.78 | 4.32x | $61,492 |
| 420-7023 CL C CONC (CAP)(HPC) | 30.8 CY | $3,300.00 | $1,420.15 | 2.32x | $57,899 |
| 260-7006 LIME TRT (EXIST MATL)(6") | 2,135 SY | $30.00 | $3.80 | 7.90x | $55,945 |
| 354-7019 PLANE & TEXT ASPH CONC PAV(2") | 30,397 SY | $3.00 | $1.62 | 1.85x | $42,030 |
| 400-7010 CEM STABIL BKFL | 188 CY | $320.00 | $138.14 | 2.32x | $34,189 |