Bid Tab X-ray: 0586-01-069

Jun 5, 2025 · Brazoria Sign up free
Set your company to personalize scores

SH 332, FM 523 to End of Maintenance

0586-01-069 · let Jun 5, 2025 · Brazoria, Houston · Overlay

$2,104,777Low bid: DURWOOD GREENE CONSTRUCTION CO.-11.7% vs estimate $2,384,508
$96,339Left on the table4.6% gap to the second bid
5BiddersSpread 28% low to high
58Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1DURWOOD GREENE CONSTRUCTION CO. $2,104,777-11.7% $96,339 7+$259,265 2-$443,605
2ELITE KINGS CONSTRUCTION, LLC $2,201,117+4.6%-7.7% $46,228 4+$224,334 8-$515,240
3VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC $2,247,344+6.8%-5.8% $51,518 5+$179,309 1-$325,850
4CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. $2,298,863+9.2%-3.6% $392,463 8+$323,495 2-$418,605
5TEXAS MATERIALS GROUP, INC. $2,691,325+27.9%12.9% 9+$348,903 2-$418,142

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.

Where the job was won

DURWOOD GREENE CONSTRUCTION CO. vs ELITE KINGS CONSTRUCTION, LLC, biggest item swings
ItemQtyLow2ndMarket2nd minus low
341-7057 D-GR HMA TY-D SAC-A PG76-227,506 TON $130.00$154.00$175.66 $180,144
354-7018 PLANE & TEXT ASPH CONC PAV(1.5")69,437 SY $1.00$3.50$1.85 $173,593
500-7001 MOBILIZATION1 LS $100,000.00$200,000.00$523,850.32 $100,000
438-7001 CLEANING AND SEALING EXISTING JOINTS1,200 LF $57.00$5.00$15.92 -$62,400
3006-7001 UNDERSEAL COURSE22,970 GAL $7.50$5.00$3.65 -$57,425
533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR)28,150 LF $0.2000$2.00$0.2040 $50,670
780-7004 CNC CRACK REPAIR (DISCRETE)(SURF SEAL)1,200 LF $36.00$1.00$49.91 -$42,000
432-7013 RIPRAP (MOW STRIP)(4 IN)36 CY $1,100.00$3.00$616.83 -$39,492
644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P)54 EA $830.00$230.00$696.14 -$32,400
533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE)18,000 LF $0.2000$2.00$0.2394 $32,400
540-7039 TL-3 31" SHORT RADIUS (COMPLETE)1 EA $30,000.00$15.00$13,068.91 -$29,985
6065-7004 MLTPLY PV MK W/WTY (Y) (6") (SLD)14,312 LF $3.00$1.00$0.6356 -$28,624
351-7013 FLEXIBLE PAVEMENT STRUCTURE REPAIR(14")200 SY $125.00$5.00$150.09 -$24,000
721-7001 FIBER REINFORCED POLYMER PATCHING MATLS1,801 LB $20.00$7.00$4.41 -$23,413
644-7073 REMOVE SM RD SN SUP&AM95 EA $160.00$400.00$108.47 $22,800
662-7068 WK ZN PAV MRK REMOV (W)6"(SLD)61,302 LF $0.6500$1.00$0.8015 $21,456
6065-7001 MLTPLY PV MK W/WTY (W) (6") (SLD)10,651 LF $3.00$1.00$0.6352 -$21,302
662-7100 WK ZN PAV MRK REMOV (Y)6"(SLD)57,656 LF $0.6500$1.00$0.8371 $20,180
505-7001 TMA (STATIONARY)96 DAY $350.00$150.00$217.57 -$19,200
467-7328 SET (TY II) (24 IN) (RCP) (6: 1) (P)14 EA $2,500.00$1,300.00$1,883.43 -$16,800

Positive: the low bidder was cheaper on that item. These 20 items account for $204,201 of the $96,339 gap.

DURWOOD GREENE CONSTRUCTION CO.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
3006-7001 UNDERSEAL COURSE22,970 GAL $7.50$3.652.06x$88,531
438-7001 CLEANING AND SEALING EXISTING JOINTS1,200 LF $57.00$15.923.58x$49,299
6065-7004 MLTPLY PV MK W/WTY (Y) (6") (SLD)14,312 LF $3.00$0.63564.72x$33,839
721-7001 FIBER REINFORCED POLYMER PATCHING MATLS1,801 LB $20.00$4.414.54x$28,083
6065-7001 MLTPLY PV MK W/WTY (W) (6") (SLD)10,651 LF $3.00$0.63524.72x$25,187
432-7013 RIPRAP (MOW STRIP)(4 IN)36 CY $1,100.00$616.831.78x$17,394
540-7039 TL-3 31" SHORT RADIUS (COMPLETE)1 EA $30,000.00$13,068.912.30x$16,931
500-7001 MOBILIZATION1 LS $100,000.00$523,850.320.19x-$423,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO $5,000.00$11,585.040.43x-$19,755

ELITE KINGS CONSTRUCTION, LLC: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
354-7018 PLANE & TEXT ASPH CONC PAV(1.5")69,437 SY $3.50$1.851.89x$114,391
533-7001 MILL RUMBLE STRIPS (ASPHALT) (SHLDR)28,150 LF $2.00$0.20409.80x$50,557
533-7002 MILL RUMBLE STRIPS (ASPH) (CENTERLINE)18,000 LF $2.00$0.23948.35x$31,691
644-7073 REMOVE SM RD SN SUP&AM95 EA $400.00$108.473.69x$27,695
500-7001 MOBILIZATION1 LS $200,000.00$523,850.320.38x-$323,850
780-7004 CNC CRACK REPAIR (DISCRETE)(SURF SEAL)1,200 LF $1.00$49.910.02x-$58,692
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO $1,500.00$11,585.040.13x-$30,255
351-7013 FLEXIBLE PAVEMENT STRUCTURE REPAIR(14")200 SY $5.00$150.090.03x-$29,018
644-7001 IN SM RD SN SUP&AM TY10BWG(1)SA(P)54 EA $230.00$696.140.33x-$25,172
432-7013 RIPRAP (MOW STRIP)(4 IN)36 CY $3.00$616.830.00x-$22,098
438-7001 CLEANING AND SEALING EXISTING JOINTS1,200 LF $5.00$15.920.31x-$13,101
540-7039 TL-3 31" SHORT RADIUS (COMPLETE)1 EA $15.00$13,068.910.00x-$13,054

VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
3006-7001 UNDERSEAL COURSE22,970 GAL $7.30$3.652.00x$83,937
438-7001 CLEANING AND SEALING EXISTING JOINTS1,200 LF $52.00$15.923.27x$43,299
721-7001 FIBER REINFORCED POLYMER PATCHING MATLS1,801 LB $18.00$4.414.08x$24,481
540-7039 TL-3 31" SHORT RADIUS (COMPLETE)1 EA $28,000.00$13,068.912.14x$14,931
529-7014 CONC CURB (DOWEL)482 LF $60.00$33.731.78x$12,660
500-7001 MOBILIZATION1 LS $198,000.00$523,850.320.38x-$325,850

CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.: unbalanced items

Placed 4
ItemQtyTheir priceMarketx market$ vs market
3006-7001 UNDERSEAL COURSE22,970 GAL $9.80$3.652.69x$141,362
438-7001 CLEANING AND SEALING EXISTING JOINTS1,200 LF $52.00$15.923.27x$43,299
6065-7004 MLTPLY PV MK W/WTY (Y) (6") (SLD)14,312 LF $3.00$0.63564.72x$33,839
134-7004 BACKFILL (TY A OR B)141 STA $415.00$211.211.96x$28,734
6065-7001 MLTPLY PV MK W/WTY (W) (6") (SLD)10,651 LF $3.00$0.63524.72x$25,187
721-7001 FIBER REINFORCED POLYMER PATCHING MATLS1,801 LB $18.00$4.414.08x$24,481
540-7039 TL-3 31" SHORT RADIUS (COMPLETE)1 EA $27,000.00$13,068.912.07x$13,931
529-7014 CONC CURB (DOWEL)482 LF $60.00$33.731.78x$12,660
500-7001 MOBILIZATION1 LS $125,000.00$523,850.320.24x-$398,850
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3 MO $5,000.00$11,585.040.43x-$19,755

TEXAS MATERIALS GROUP, INC.: unbalanced items

Placed 5
ItemQtyTheir priceMarketx market$ vs market
354-7018 PLANE & TEXT ASPH CONC PAV(1.5")69,437 SY $3.85$1.852.08x$138,693
721-7001 FIBER REINFORCED POLYMER PATCHING MATLS1,801 LB $29.00$4.416.58x$44,292
6065-7004 MLTPLY PV MK W/WTY (Y) (6") (SLD)14,312 LF $3.50$0.63565.51x$40,995
6065-7001 MLTPLY PV MK W/WTY (W) (6") (SLD)10,651 LF $3.50$0.63525.51x$30,513
351-7013 FLEXIBLE PAVEMENT STRUCTURE REPAIR(14")200 SY $264.00$150.091.76x$22,782
134-7004 BACKFILL (TY A OR B)141 STA $370.00$211.211.75x$22,389
540-7039 TL-3 31" SHORT RADIUS (COMPLETE)1 EA $31,500.00$13,068.912.41x$18,431
351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3")150 SY $145.00$36.284.00x$16,307
438-7001 CLEANING AND SEALING EXISTING JOINTS1,200 LF $28.00$15.921.76x$14,499
500-7001 MOBILIZATION1 LS $138,000.00$523,850.320.26x-$385,850
780-7004 CNC CRACK REPAIR (DISCRETE)(SURF SEAL)1,200 LF $23.00$49.910.46x-$32,292