On CR 143 at Dry Berry Creek
0914-05-203 · let Aug 8, 2025 · Williamson, Austin · Bridge Replacement
$1,585,425Low bid: DAN WILLIAMS COMPANY-21.6% vs estimate $2,022,834
$104,541Left on the table6.6% gap to the second bid
11BiddersSpread 59% low to high
126Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | DAN WILLIAMS COMPANY | $1,585,425 | -21.6% | $104,541 | 0 | 1-$373,850 | |
| 2 | CHASCO CONSTRUCTORS | $1,689,966 | +6.6% | -16.5% | $122,736 | 2+$24,659 | 3-$473,125 |
| 3 | PATIN CONSTRUCTION LLC | $1,812,702 | +14.3% | -10.4% | $25,854 | 7+$158,084 | 3-$551,779 |
| 4 | STX CIVIL | $1,838,556 | +16.0% | -9.1% | $59,444 | 3+$75,314 | 3-$502,516 |
| 5 | CHAMPION SITE PREP, INC. | $1,898,000 | +19.7% | -6.2% | $76,942 | 8+$172,634 | 3-$531,714 |
| 6 | KNIFE RIVER CORPORATION - SOUTH | $1,974,942 | +24.6% | -2.4% | $117,150 | ||
| 7 | JORDAN FOSTER CONSTRUCTION, LLC | $2,092,092 | +32.0% | 3.4% | $33,215 | ||
| 8 | E-Z BEL CONSTRUCTION, LLC | $2,125,307 | +34.1% | 5.1% | $48,577 | ||
| 9 | C. E. BARKER, LTD. | $2,173,884 | +37.1% | 7.5% | $5,237 | ||
| 10 | DEAN WORD COMPANY, LTD. | $2,179,122 | +37.4% | 7.7% | $340,035 | ||
| 11 | TALBERT COMPANIES LLC | $2,519,156 | +58.9% | 24.5% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
DAN WILLIAMS COMPANY vs CHASCO CONSTRUCTORS, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $10,000.00 | $2,500.00 | $11,585.04 | -$45,000 |
| 432-7001 RIPRAP (CONC)(4 IN) | 79 CY | $525.00 | $800.00 | $573.24 | $21,725 |
| 432-7043 RIPRAP (STONE PROTECTION)(18 IN) | 306 CY | $110.00 | $180.00 | $184.74 | $21,420 |
| 110-7001 EXCAV (ROADWAY) | 4,129 CY | $13.00 | $18.00 | $11.68 | $20,645 |
| 450-7008 RAIL (TY T223) | 240 LF | $130.00 | $215.00 | $141.07 | $20,400 |
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $130,000.00 | $523,850.32 | -$20,000 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 8,729 SY | $1.10 | $3.00 | $1.43 | $16,585 |
| 420-7012 CL C CONC (ABUT) | 51.2 CY | $1,200.00 | $1,500.00 | $1,307.98 | $15,360 |
| 100-7002 PREPARING ROW | 16.2 STA | $5,900.00 | $5,000.00 | $6,072.92 | -$14,580 |
| 422-7013 APPROACH SLAB | 77 CY | $600.00 | $765.00 | $738.51 | $12,705 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 6,089 SY | $3.75 | $5.50 | $3.93 | $10,656 |
| 422-7001 REINF CONC SLAB | 4,000 SF | $27.50 | $30.00 | $24.45 | $10,000 |
| 105-7011 RMV (11"-15") TRT/UNTRT BASE & ASPH PAV | 4,719 SY | $6.00 | $4.00 | $9.25 | -$9,438 |
| 425-7003 PRESTR CONC GIRDER (TX40) | 596.94 LF | $235.00 | $250.00 | $213.86 | $8,954 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 3,856 CY | $14.00 | $12.00 | $16.96 | -$7,712 |
| 432-7013 RIPRAP (MOW STRIP)(4 IN) | 29.7 CY | $700.00 | $950.00 | $616.83 | $7,425 |
| 530-7016 DRIVEWAYS (SURF TREAT) | 109 SY | $73.00 | $135.00 | $34.56 | $6,758 |
| 164-7007 BROADCAST SEED (TEMP_WARM_COOL) | 8,729 SY | $0.2500 | $1.00 | $0.2110 | $6,547 |
| 400-7010 CEM STABIL BKFL | 191 CY | $225.00 | $195.00 | $138.14 | -$5,730 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 114 DAY | $110.00 | $60.00 | $87.82 | -$5,700 |
Positive: the low bidder was cheaper on that item. These 20 items account for $71,020 of the $104,541 gap.
DAN WILLIAMS COMPANY: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7001 MOBILIZATION | 1 LS | $150,000.00 | $523,850.32 | 0.29x | -$373,850 |
CHASCO CONSTRUCTORS: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 160-7002 FURN & PLACE TOPSOIL (4") | 8,729 SY | $3.00 | $1.43 | 2.10x | $13,711 |
| 530-7016 DRIVEWAYS (SURF TREAT) | 109 SY | $135.00 | $34.56 | 3.91x | $10,948 |
| 500-7001 MOBILIZATION | 1 LS | $130,000.00 | $523,850.32 | 0.25x | -$393,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,500.00 | $11,585.04 | 0.22x | -$54,510 |
| 105-7011 RMV (11"-15") TRT/UNTRT BASE & ASPH PAV | 4,719 SY | $4.00 | $9.25 | 0.43x | -$24,765 |
PATIN CONSTRUCTION LLC: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 450-7008 RAIL (TY T223) | 240 LF | $300.00 | $141.07 | 2.13x | $38,144 |
| 400-7010 CEM STABIL BKFL | 191 CY | $300.00 | $138.14 | 2.17x | $30,915 |
| 260-7020 LIME TRT (SUBGRADE) (8") | 6,089 SY | $8.00 | $3.93 | 2.04x | $24,810 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 8,729 SY | $4.00 | $1.43 | 2.80x | $22,440 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 114 DAY | $250.00 | $87.82 | 2.85x | $18,489 |
| 168-7001 VEGETATIVE WATERING | 146.66 TGL | $100.00 | $8.43 | 11.86x | $13,429 |
| 530-7016 DRIVEWAYS (SURF TREAT) | 109 SY | $125.00 | $34.56 | 3.62x | $9,858 |
| 500-7001 MOBILIZATION | 1 LS | $50,000.00 | $523,850.32 | 0.10x | -$473,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,000.00 | $11,585.04 | 0.43x | -$39,510 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 3,856 CY | $7.00 | $16.96 | 0.41x | -$38,418 |
STX CIVIL: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7058 D-GR HMA TY-D SAC-B PG76-22 | 539 TON | $215.00 | $120.18 | 1.79x | $51,107 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 8,729 SY | $3.00 | $1.43 | 2.10x | $13,711 |
| 168-7001 VEGETATIVE WATERING | 146.66 TGL | $80.00 | $8.43 | 9.49x | $10,496 |
| 500-7001 MOBILIZATION | 1 LS | $145,000.00 | $523,850.32 | 0.28x | -$378,850 |
| 100-7002 PREPARING ROW | 16.2 STA | $1,730.00 | $6,072.92 | 0.28x | -$70,355 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $2,700.00 | $11,585.04 | 0.23x | -$53,310 |
CHAMPION SITE PREP, INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 416-7006 DRILL SHAFT (36 IN) | 136 LF | $529.10 | $280.58 | 1.89x | $33,799 |
| 160-7002 FURN & PLACE TOPSOIL (4") | 8,729 SY | $4.98 | $1.43 | 3.48x | $30,994 |
| 400-7010 CEM STABIL BKFL | 191 CY | $289.18 | $138.14 | 2.09x | $28,848 |
| 530-7016 DRIVEWAYS (SURF TREAT) | 109 SY | $222.65 | $34.56 | 6.44x | $20,502 |
| 168-7001 VEGETATIVE WATERING | 146.66 TGL | $134.84 | $8.43 | 15.99x | $18,539 |
| 530-7010 DRIVEWAYS (ACP) | 150 SY | $173.01 | $54.96 | 3.15x | $17,708 |
| 464-7003 RC PIPE (CL III)(18 IN) | 106 LF | $188.17 | $83.08 | 2.26x | $11,139 |
| 467-7467 SET (TY II)(18 IN)(RCP)(3:1)(P) | 4 EA | $4,237.50 | $1,461.41 | 2.90x | $11,104 |
| 500-7001 MOBILIZATION | 1 LS | $74,548.45 | $523,850.32 | 0.14x | -$449,302 |
| 132-7003 EMBANK (FNL)(OC)(TY B) | 3,856 CY | $5.71 | $16.96 | 0.34x | -$43,393 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,081.81 | $11,585.04 | 0.44x | -$39,019 |