FY 26 SOUTH MILL & INLAY
6488-58-001 · let Sep 5, 2025 · Henderson, Tyler · Routine Maintenance Project - Sealed
$4,487,610Low bid: BIG CREEK CONSTRUCTION, LTD.-19.9% vs estimate $5,605,030
$359,957Left on the table8.0% gap to the second bid
3BiddersSpread 55% low to high
16Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | BIG CREEK CONSTRUCTION, LTD. | $4,487,610 | -19.9% | $359,957 | 2+$620,794 | 1-$26,340 | |
| 2 | DREWERY CONSTRUCTION COMPANY, INCORPORATED | $4,847,567 | +8.0% | -13.5% | $2,128,481 | 1+$27,991 | 1-$268,850 |
| 3 | GREY SKY CONSTRUCTION LLC | $6,976,048 | +55.5% | 24.5% | 2+$3,096,476 | 0 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.
Where the job was won
BIG CREEK CONSTRUCTION, LTD. vs DREWERY CONSTRUCTION COMPANY, INCORPORATED, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 344-7020 SP MIXES SP-C SAC-A PG70-22 | 18,713 TON | $155.00 | $200.00 | $137.95 | $842,085 |
| 354-7051 PLANE ASPH CONC PAV(2") | 162,724 SY | $5.50 | $3.20 | $1.86 | -$374,265 |
| 500-7001 MOBILIZATION | 1 LS | $403,000.00 | $255,000.00 | $523,850.32 | -$148,000 |
| 3005-7001 MEMBRANE UNDERSEAL | 40,681 GAL | $3.00 | $4.00 | $4.76 | $40,681 |
| 7010-7001 MAINTENANCE SPEED LIMIT SIGNING | 6 EA | $2,500.00 | $750.00 | $36.55 | -$10,500 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 MO | $5,000.00 | $7,500.00 | $11,585.04 | $10,000 |
| 503-7001 PORTABLE CHANGEABLE MESSAGE SIGN | 84 DAY | $200.00 | $150.00 | $87.82 | -$4,200 |
| 505-7001 TMA (STATIONARY) | 34 DAY | $500.00 | $400.00 | $217.57 | -$3,400 |
| 662-7088 WK ZN PAV MRK REMOV (W)(RR XING) | 5 EA | $250.00 | $900.00 | $414.03 | $3,250 |
| 662-7077 WK ZN PAV MRK REMOV (W)24"(SLD) | 526 LF | $10.00 | $15.00 | $7.79 | $2,630 |
| 662-7076 WK ZN PAV MRK REMOV (W)18"(SLD) | 124 LF | $5.00 | $14.00 | $9.72 | $1,116 |
| 662-7082 WK ZN PAV MRK REMOV (W)(ARROW) | 14 EA | $250.00 | $290.00 | $166.91 | $560 |
| 662-7061 WK ZN PAV MRK REMOV (W)4"(BRK) | 11,654 LF | $2.00 | $2.00 | $1.22 | $0 |
| 662-7064 WK ZN PAV MRK REMOV (W)4"(SLD) | 1,885 LF | $2.00 | $2.00 | $0.8527 | $0 |
| 662-7095 WK ZN PAV MRK REMOV (Y)4"(BRK) | 6,708 LF | $2.00 | $2.00 | $1.35 | $0 |
| 662-7097 WK ZN PAV MRK REMOV (Y)4"(SLD) | 23,573 LF | $2.00 | $2.00 | $0.8126 | $0 |
Positive: the low bidder was cheaper on that item. These 16 items account for $359,957 of the $359,957 gap.