Bid Tab X-ray: 6488-58-001

Sep 5, 2025 · Henderson Sign up free
Set your company to personalize scores

FY 26 SOUTH MILL & INLAY

6488-58-001 · let Sep 5, 2025 · Henderson, Tyler · Routine Maintenance Project - Sealed

$4,487,610Low bid: BIG CREEK CONSTRUCTION, LTD.-19.9% vs estimate $5,605,030
$359,957Left on the table8.0% gap to the second bid
3BiddersSpread 55% low to high
16Items comparedAgainst statewide low-bid averages

The bids

#BidderTotalvs lowvs estimateGap to nextLoaded itemsCut items
1BIG CREEK CONSTRUCTION, LTD. $4,487,610-19.9% $359,957 2+$620,794 1-$26,340
2DREWERY CONSTRUCTION COMPANY, INCORPORATED $4,847,567+8.0%-13.5% $2,128,481 1+$27,991 1-$268,850
3GREY SKY CONSTRUCTION LLC $6,976,048+55.5%24.5% 2+$3,096,476 0

Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 3 bidders.

Where the job was won

BIG CREEK CONSTRUCTION, LTD. vs DREWERY CONSTRUCTION COMPANY, INCORPORATED, biggest item swings
ItemQtyLow2ndMarket2nd minus low
344-7020 SP MIXES SP-C SAC-A PG70-2218,713 TON $155.00$200.00$137.95 $842,085
354-7051 PLANE ASPH CONC PAV(2")162,724 SY $5.50$3.20$1.86 -$374,265
500-7001 MOBILIZATION1 LS $403,000.00$255,000.00$523,850.32 -$148,000
3005-7001 MEMBRANE UNDERSEAL40,681 GAL $3.00$4.00$4.76 $40,681
7010-7001 MAINTENANCE SPEED LIMIT SIGNING6 EA $2,500.00$750.00$36.55 -$10,500
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING4 MO $5,000.00$7,500.00$11,585.04 $10,000
503-7001 PORTABLE CHANGEABLE MESSAGE SIGN84 DAY $200.00$150.00$87.82 -$4,200
505-7001 TMA (STATIONARY)34 DAY $500.00$400.00$217.57 -$3,400
662-7088 WK ZN PAV MRK REMOV (W)(RR XING)5 EA $250.00$900.00$414.03 $3,250
662-7077 WK ZN PAV MRK REMOV (W)24"(SLD)526 LF $10.00$15.00$7.79 $2,630
662-7076 WK ZN PAV MRK REMOV (W)18"(SLD)124 LF $5.00$14.00$9.72 $1,116
662-7082 WK ZN PAV MRK REMOV (W)(ARROW)14 EA $250.00$290.00$166.91 $560
662-7061 WK ZN PAV MRK REMOV (W)4"(BRK)11,654 LF $2.00$2.00$1.22 $0
662-7064 WK ZN PAV MRK REMOV (W)4"(SLD)1,885 LF $2.00$2.00$0.8527 $0
662-7095 WK ZN PAV MRK REMOV (Y)4"(BRK)6,708 LF $2.00$2.00$1.35 $0
662-7097 WK ZN PAV MRK REMOV (Y)4"(SLD)23,573 LF $2.00$2.00$0.8126 $0

Positive: the low bidder was cheaper on that item. These 16 items account for $359,957 of the $359,957 gap.

BIG CREEK CONSTRUCTION, LTD.: unbalanced items

Placed 1
ItemQtyTheir priceMarketx market$ vs market
354-7051 PLANE ASPH CONC PAV(2")162,724 SY $5.50$1.862.96x$592,804
662-7097 WK ZN PAV MRK REMOV (Y)4"(SLD)23,573 LF $2.00$0.81262.46x$27,991
502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING4 MO $5,000.00$11,585.040.43x-$26,340

DREWERY CONSTRUCTION COMPANY, INCORPORATED: unbalanced items

Placed 2
ItemQtyTheir priceMarketx market$ vs market
662-7097 WK ZN PAV MRK REMOV (Y)4"(SLD)23,573 LF $2.00$0.81262.46x$27,991
500-7001 MOBILIZATION1 LS $255,000.00$523,850.320.49x-$268,850

GREY SKY CONSTRUCTION LLC: unbalanced items

Placed 3
ItemQtyTheir priceMarketx market$ vs market
344-7020 SP MIXES SP-C SAC-A PG70-2218,713 TON $250.00$137.951.81x$2,096,863
354-7051 PLANE ASPH CONC PAV(2")162,724 SY $8.00$1.864.31x$999,614