REPLACE FM 1835 BRIDGE DOUBLE MTN FORK
1747-02-017 · let Sep 5, 2025 · Stonewall, Abilene · Bridge Replacement
$3,884,350Low bid: HODGES AND SON CONSTRUCTION COMPANY, INC.-53.0% vs estimate $8,261,190
$97,216Left on the table2.5% gap to the second bid
10BiddersSpread 96% low to high
61Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $3,884,350 | -53.0% | $97,216 | 3+$97,876 | 1-$387,206 | |
| 2 | L & N BRIDGE, LLC | $3,981,566 | +2.5% | -51.8% | $285,643 | 4+$136,233 | 2-$260,290 |
| 3 | RAGLE CONSTRUCTION, INC. | $4,267,209 | +9.9% | -48.3% | $358,791 | 4+$931,158 | 2-$565,506 |
| 4 | URBAN INFRACONSTRUCTION LLC | $4,626,000 | +19.1% | -44.0% | $776,561 | 2+$481,188 | 2-$148,759 |
| 5 | COPPELL CONSTRUCTION CO., INC. | $5,402,561 | +39.1% | -34.6% | $781,282 | 8+$1,148,031 | 1-$357,206 |
| 6 | EARTH BUILDERS, L.P. | $6,183,843 | +59.2% | -25.1% | $901,289 | ||
| 7 | JAMES CONSTRUCTION GROUP, LLC | $7,085,132 | +82.4% | -14.2% | $194,991 | ||
| 8 | ALTUS CONSTRUCTION LLC | $7,280,123 | +87.4% | -11.9% | $169,411 | ||
| 9 | C. E. BARKER, LTD. | $7,449,535 | +91.8% | -9.8% | $174,960 | ||
| 10 | GILVIN-TERRILL, LTD. | $7,624,495 | +96.3% | -7.7% |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
HODGES AND SON CONSTRUCTION COMPANY, INC. vs L & N BRIDGE, LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 4006-7001 TEMP CONSTRUCTION ACCESS | 1 LS | $60,000.00 | $240,000.00 | $447,206.31 | $180,000 |
| 416-7006 DRILL SHAFT (36 IN) | 825 LF | $285.00 | $475.00 | $280.58 | $156,750 |
| 425-7004 PRESTR CONC GIRDER (TX46) | 3,135 LF | $275.00 | $250.00 | $236.72 | -$78,375 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $12,000.00 | $1,290.34 | $11,585.04 | -$64,258 |
| 420-7039 CL C CONC (COLUMN)(HPC) | 92 CY | $1,400.00 | $1,100.00 | $1,492.16 | -$27,600 |
| 508-7001 CONSTRUCTING DETOURS | 1,493 SY | $62.00 | $45.00 | $83.58 | -$25,381 |
| 500-7001 MOBILIZATION | 1 LS | $350,000.00 | $375,000.00 | $523,850.32 | $25,000 |
| 427-7005 EPOXY WATERPROOF FINISH (TY X) | 2,690 SF | $15.00 | $6.00 | $9.61 | -$24,210 |
| 496-7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) | 1 EA | $200,000.00 | $180,000.00 | $378,521.97 | -$20,000 |
| 168-7001 VEGETATIVE WATERING | 240 TGL | $1.00 | $80.00 | $8.43 | $18,960 |
| 506-7003 ROCK FILTER DAMS (INSTALL) (TY 3) | 195 LF | $1.00 | $96.00 | $71.34 | $18,525 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 1,279 SY | $25.00 | $11.50 | $7.43 | -$17,267 |
| 420-7023 CL C CONC (CAP)(HPC) | 79.5 CY | $2,200.00 | $2,000.00 | $1,420.15 | -$15,900 |
| 341-7048 D-GR HMA TY-D PG70-22 | 144 TON | $250.00 | $350.00 | $126.94 | $14,400 |
| 341-7001 D-GR HMA TY-B PG64-22 | 287 TON | $250.00 | $300.00 | $97.82 | $14,350 |
| 132-7002 EMBANK (FNL)(DC)(TY A) | 707 CY | $30.00 | $50.00 | $15.82 | $14,140 |
| 420-7013 CL C CONC (ABUT)(HPC) | 57.2 CY | $1,400.00 | $1,200.00 | $1,329.26 | -$11,440 |
| 422-7002 REINF CONC SLAB (HPC) | 22,680 SF | $30.50 | $30.00 | $26.91 | -$11,340 |
| 275-7002 CEMENT TRT (EXIST MATL)(6") | 1,302 SY | $15.00 | $7.00 | $2.82 | -$10,416 |
| 432-7008 RIPRAP (CONC)(CL B)(5 IN) | 201 CY | $750.00 | $700.00 | $579.27 | -$10,050 |
Positive: the low bidder was cheaper on that item. These 20 items account for $125,889 of the $97,216 gap.
HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7001 D-GR HMA TY-B PG64-22 | 287 TON | $250.00 | $97.82 | 2.56x | $43,674 |
| 400-7010 CEM STABIL BKFL | 196 CY | $300.00 | $138.14 | 2.17x | $31,724 |
| 105-7052 RMV (0"-12") TRT/UNTRT BASE & ASPH PAV | 1,279 SY | $25.00 | $7.43 | 3.37x | $22,478 |
| 4006-7001 TEMP CONSTRUCTION ACCESS | 1 LS | $60,000.00 | $447,206.31 | 0.13x | -$387,206 |
L & N BRIDGE, LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 341-7001 D-GR HMA TY-B PG64-22 | 287 TON | $300.00 | $97.82 | 3.07x | $58,024 |
| 341-7048 D-GR HMA TY-D PG70-22 | 144 TON | $350.00 | $126.94 | 2.76x | $32,121 |
| 132-7002 EMBANK (FNL)(DC)(TY A) | 707 CY | $50.00 | $15.82 | 3.16x | $24,164 |
| 400-7010 CEM STABIL BKFL | 196 CY | $250.00 | $138.14 | 1.81x | $21,924 |
| 496-7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) | 1 EA | $180,000.00 | $378,521.97 | 0.48x | -$198,522 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $1,290.34 | $11,585.04 | 0.11x | -$61,768 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 496-7011 REMOV STR (BRIDGE 500 - 999 FT LENGTH) | 1 EA | $925,000.00 | $378,521.97 | 2.44x | $546,478 |
| 100-7002 PREPARING ROW | 3.7 STA | $76,750.00 | $6,072.92 | 12.64x | $261,505 |
| 110-7001 EXCAV (ROADWAY) | 726 CY | $137.00 | $11.68 | 11.73x | $90,981 |
| 341-7001 D-GR HMA TY-B PG64-22 | 287 TON | $210.00 | $97.82 | 2.15x | $32,194 |
| 4006-7001 TEMP CONSTRUCTION ACCESS | 1 LS | $5,000.00 | $447,206.31 | 0.01x | -$442,206 |
| 508-7001 CONSTRUCTING DETOURS | 1,493 SY | $1.00 | $83.58 | 0.01x | -$123,299 |
URBAN INFRACONSTRUCTION LLC: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 3.7 STA | $124,320.00 | $6,072.92 | 20.47x | $437,514 |
| 341-7001 D-GR HMA TY-B PG64-22 | 287 TON | $250.00 | $97.82 | 2.56x | $43,674 |
| 508-7001 CONSTRUCTING DETOURS | 1,493 SY | $8.00 | $83.58 | 0.10x | -$112,848 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $5,600.00 | $11,585.04 | 0.48x | -$35,910 |
COPPELL CONSTRUCTION CO., INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 508-7001 CONSTRUCTING DETOURS | 1,493 SY | $516.00 | $83.58 | 6.17x | $645,596 |
| 420-7023 CL C CONC (CAP)(HPC) | 79.5 CY | $3,900.00 | $1,420.15 | 2.75x | $197,148 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 6 MO | $35,000.00 | $11,585.04 | 3.02x | $140,490 |
| 400-7010 CEM STABIL BKFL | 196 CY | $340.00 | $138.14 | 2.46x | $39,564 |
| 341-7048 D-GR HMA TY-D PG70-22 | 144 TON | $400.00 | $126.94 | 3.15x | $39,321 |
| 100-7002 PREPARING ROW | 3.7 STA | $14,000.00 | $6,072.92 | 2.31x | $29,330 |
| 275-7002 CEMENT TRT (EXIST MATL)(6") | 1,302 SY | $25.00 | $2.82 | 8.88x | $28,884 |
| 132-7002 EMBANK (FNL)(DC)(TY A) | 707 CY | $55.00 | $15.82 | 3.48x | $27,699 |
| 4006-7001 TEMP CONSTRUCTION ACCESS | 1 LS | $90,000.00 | $447,206.31 | 0.20x | -$357,206 |