6487-53-001 Mill and Inlay
6487-53-001 · let Sep 4, 2025 · Midland, Odessa · Routine Maintenance Project - Sealed
$1,532,796Low bid: RK HALL, LLC-13.6% vs estimate $1,774,838
$101,685Left on the table6.6% gap to the second bid
4BiddersSpread 11% low to high
31Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | RK HALL, LLC | $1,532,796 | -13.6% | $101,685 | 7+$316,571 | 2-$422,512 | |
| 2 | JONES BROS. DIRT & PAVING CONTRACTORS, INC. | $1,634,481 | +6.6% | -7.9% | $12,322 | 7+$357,729 | 2-$429,876 |
| 3 | RAGLE CONSTRUCTION, INC. | $1,646,803 | +7.4% | -7.2% | $47,206 | 6+$323,804 | 2-$395,373 |
| 4 | REECE ALBERT, INC. | $1,694,009 | +10.5% | -4.6% | 5+$305,225 | 1-$383,040 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 4 bidders.
Where the job was won
RK HALL, LLC vs JONES BROS. DIRT & PAVING CONTRACTORS, INC., biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 341-7024 D-GR HMA TY-C SAC-B PG70-22 | 4,634 TON | $158.57 | $174.58 | $112.90 | $74,190 |
| 351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") | 2,000 SY | $100.00 | $69.43 | $36.28 | -$61,140 |
| 354-7053 PLANE ASPH CONC PAV(4") | 18,052 SY | $7.24 | $10.59 | $3.14 | $60,474 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 6 EA | $4,473.33 | $13,500.00 | $9,253.78 | $54,160 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $15,275.00 | $26,917.50 | $600.85 | $46,570 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $19,000.00 | $5,154.06 | $11,585.04 | -$41,538 |
| 500-7001 MOBILIZATION | 1 LS | $130,021.46 | $113,267.51 | $523,850.32 | -$16,754 |
| 505-7001 TMA (STATIONARY) | 60 DAY | $340.00 | $202.50 | $217.57 | -$8,250 |
| 315-7004 FOG SEAL (CSS-1H) | 3,309 GAL | $5.74 | $4.15 | $4.02 | -$5,261 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,952 EA | $5.00 | $3.65 | $0.5715 | -$3,985 |
| 310-7001 PRIME COAT (AE-P) | 3,611 GAL | $3.89 | $4.50 | $5.11 | $2,203 |
| 505-7002 TMA (MOBILE OPERATION) | 60 HR | $81.64 | $114.75 | $64.00 | $1,987 |
| 662-7112 WK ZN PAV MRK SHT TERM (TAB)TY W | 1,276 EA | $5.00 | $3.65 | $1.03 | -$1,723 |
| 354-7052 PLANE ASPH CONC PAV(3") | 4,000 SY | $5.95 | $6.23 | $2.92 | $1,120 |
| 150-7002 BLADING | 30 HR | $350.00 | $384.13 | $171.50 | $1,024 |
| 216-7001 PROOF ROLLING | 30 HR | $118.00 | $151.00 | $127.71 | $990 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 13,680 LF | $1.65 | $1.58 | $0.4986 | -$958 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 13,195 LF | $1.65 | $1.58 | $0.4757 | -$924 |
| 341-7082 TACK COAT | 2,206 GAL | $3.61 | $3.85 | $3.93 | $529 |
| 668-7089 PREFAB PM TY C (W)(24")(SLD) | 326 LF | $19.25 | $18.38 | $13.72 | -$284 |
Positive: the low bidder was cheaper on that item. These 20 items account for $102,431 of the $101,685 gap.
RK HALL, LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") | 2,000 SY | $100.00 | $36.28 | 2.76x | $127,433 |
| 354-7053 PLANE ASPH CONC PAV(4") | 18,052 SY | $7.24 | $3.14 | 2.31x | $74,004 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $15,275.00 | $600.85 | 25.42x | $58,697 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 13,680 LF | $1.65 | $0.4986 | 3.31x | $15,751 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 13,195 LF | $1.65 | $0.4757 | 3.47x | $15,495 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,952 EA | $5.00 | $0.5715 | 8.75x | $13,073 |
| 354-7052 PLANE ASPH CONC PAV(3") | 4,000 SY | $5.95 | $2.92 | 2.04x | $12,118 |
| 500-7001 MOBILIZATION | 1 LS | $130,021.46 | $523,850.32 | 0.25x | -$393,829 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 6 EA | $4,473.33 | $9,253.78 | 0.48x | -$28,683 |
JONES BROS. DIRT & PAVING CONTRACTORS, INC.: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 354-7053 PLANE ASPH CONC PAV(4") | 18,052 SY | $10.59 | $3.14 | 3.37x | $134,478 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $26,917.50 | $600.85 | 44.80x | $105,267 |
| 351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") | 2,000 SY | $69.43 | $36.28 | 1.91x | $66,293 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 13,680 LF | $1.58 | $0.4986 | 3.17x | $14,794 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 13,195 LF | $1.58 | $0.4757 | 3.32x | $14,571 |
| 354-7052 PLANE ASPH CONC PAV(3") | 4,000 SY | $6.23 | $2.92 | 2.13x | $13,238 |
| 662-7114 WK ZN PAV MRK SHT TERM (TAB)TY Y-2 | 2,952 EA | $3.65 | $0.5715 | 6.39x | $9,088 |
| 500-7001 MOBILIZATION | 1 LS | $113,267.51 | $523,850.32 | 0.22x | -$410,583 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $5,154.06 | $11,585.04 | 0.44x | -$19,293 |
RAGLE CONSTRUCTION, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") | 2,000 SY | $95.00 | $36.28 | 2.62x | $117,433 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 MO | $35,500.00 | $11,585.04 | 3.06x | $71,745 |
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $15,000.00 | $600.85 | 24.96x | $57,597 |
| 354-7053 PLANE ASPH CONC PAV(4") | 18,052 SY | $5.90 | $3.14 | 1.88x | $49,814 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 13,680 LF | $1.50 | $0.4986 | 3.01x | $13,699 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 13,195 LF | $1.50 | $0.4757 | 3.15x | $13,516 |
| 500-7001 MOBILIZATION | 1 LS | $160,000.00 | $523,850.32 | 0.31x | -$363,850 |
| 503-7002 PORTABLE CHANGEABLE MESSAGE SIGN | 6 EA | $4,000.00 | $9,253.78 | 0.43x | -$31,523 |
REECE ALBERT, INC.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 500-7002 MOBILIZATION (CALLOUT) | 4 EA | $26,668.54 | $600.85 | 44.38x | $104,271 |
| 354-7053 PLANE ASPH CONC PAV(4") | 18,052 SY | $8.82 | $3.14 | 2.81x | $102,526 |
| 351-7002 FLEXIBLE PAVEMENT STRUCTURE REPAIR(3") | 2,000 SY | $69.74 | $36.28 | 1.92x | $66,913 |
| 666-7423 REFL PAV MRK TY I (Y)6"(SLD)(100MIL) | 13,680 LF | $1.66 | $0.4986 | 3.33x | $15,888 |
| 666-7411 REFL PAV MRK TY I (W)6"(SLD)(100MIL) | 13,195 LF | $1.66 | $0.4757 | 3.49x | $15,627 |
| 500-7001 MOBILIZATION | 1 LS | $140,810.78 | $523,850.32 | 0.27x | -$383,040 |