CR 238 (Sign CR 128W) at Paradise Creek
0903-30-047 · let Oct 8, 2025 · Wilbarger, Wichita Falls · Bridge Replacement
$1,424,111Low bid: SKYLINE BRIDGE LLC-7.6% vs estimate $1,540,431
$101,390Left on the table7.1% gap to the second bid
5BiddersSpread 25% low to high
79Items comparedAgainst statewide low-bid averages
The bids
| # | Bidder | Total | vs low | vs estimate | Gap to next | Loaded items | Cut items |
|---|---|---|---|---|---|---|---|
| 1 | SKYLINE BRIDGE LLC | $1,424,111 | -7.6% | $101,390 | 9+$440,734 | 3-$510,822 | |
| 2 | ALTUS CONSTRUCTION LLC | $1,525,501 | +7.1% | -1.0% | $21,715 | 6+$469,286 | 2-$434,951 |
| 3 | HODGES AND SON CONSTRUCTION COMPANY, INC. | $1,547,216 | +8.6% | 0.4% | $146,302 | 8+$401,390 | 1-$393,850 |
| 4 | EARTH BUILDERS, L.P. | $1,693,517 | +18.9% | 9.9% | $83,883 | 8+$511,603 | 3-$419,872 |
| 5 | COPPELL CONSTRUCTION CO., INC. | $1,777,400 | +24.8% | 15.4% | 9+$485,255 | 1-$363,850 |
Loaded: priced 1.75x or more over the statewide average low bid. Cut: half of it or less. Only items worth at least $2,500 or 0.5% of the bid count. Checked for the top 5 bidders.
Where the job was won
SKYLINE BRIDGE LLC vs ALTUS CONSTRUCTION LLC, biggest item swings| Item | Qty | Low | 2nd | Market | 2nd minus low |
|---|---|---|---|---|---|
| 100-7002 PREPARING ROW | 4 STA | $2,500.00 | $37,756.32 | $6,072.92 | $141,025 |
| 466-7194 WINGWALL (PW - 2) (HW=10 FT) | 2 EA | $95,000.00 | $38,145.40 | $54,085.10 | -$113,709 |
| 403-7001 TEMPORARY SPL SHORING | 1,500 SF | $20.00 | $60.10 | $25.56 | $60,150 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $151,788.04 | $523,850.32 | $51,788 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 1,000 SY | $50.00 | $16.02 | $12.30 | -$33,976 |
| 110-7004 EXCAV (ROADWAY & CHANNEL) | 870 CY | $16.00 | $48.88 | $24.59 | $28,602 |
| 552-7010 WIRE FENCE (WATER GAP) | 166 LF | $150.00 | $46.55 | $49.94 | -$17,173 |
| 416-7004 DRILL SHAFT (24 IN) | 210 LF | $250.00 | $177.44 | $234.98 | -$15,237 |
| 462-7043 CONC BOX CULV (11 FT X 8 FT) | 160 LF | $2,200.00 | $2,121.27 | $1,123.92 | -$12,596 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $15,000.00 | $27,319.81 | $28,021.15 | $12,320 |
| 105-7112 RMV (2"-8") TRT/UNTRT BASE & ASPH PAV | 165 CY | $80.00 | $13.96 | $8.43 | -$10,896 |
| 530-7015 DRIVEWAYS (BASE) | 120 SY | $65.00 | $150.12 | $27.85 | $10,214 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,500.00 | $3,723.91 | $11,585.04 | $9,791 |
| 341-7001 D-GR HMA TY-B PG64-22 | 424 TON | $300.00 | $322.74 | $97.82 | $9,641 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 320 CY | $45.00 | $21.88 | $12.93 | -$7,399 |
| 425-7019 PRESTR CONC SLAB BEAM (5SB15) | 247.5 LF | $375.00 | $345.26 | $261.75 | -$7,360 |
| 400-7010 CEM STABIL BKFL | 106 CY | $300.00 | $232.74 | $138.14 | -$7,129 |
| 450-7021 RAIL (TY T631LS) | 124 LF | $75.00 | $115.48 | $73.55 | $5,020 |
| 432-7041 RIPRAP (STONE PROTECTION)(12 IN) | 302 CY | $160.00 | $175.03 | $179.97 | $4,538 |
| 552-7011 WIRE FENCE (REMOVE) | 636 LF | $5.00 | $10.15 | $2.42 | $3,273 |
Positive: the low bidder was cheaper on that item. These 20 items account for $110,887 of the $101,390 gap.
SKYLINE BRIDGE LLC: unbalanced items
Placed 1| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 462-7043 CONC BOX CULV (11 FT X 8 FT) | 160 LF | $2,200.00 | $1,123.92 | 1.96x | $172,172 |
| 341-7001 D-GR HMA TY-B PG64-22 | 424 TON | $300.00 | $97.82 | 3.07x | $85,722 |
| 466-7194 WINGWALL (PW - 2) (HW=10 FT) | 2 EA | $95,000.00 | $54,085.10 | 1.76x | $81,830 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 1,000 SY | $50.00 | $12.30 | 4.07x | $37,704 |
| 400-7010 CEM STABIL BKFL | 106 CY | $300.00 | $138.14 | 2.17x | $17,157 |
| 552-7010 WIRE FENCE (WATER GAP) | 166 LF | $150.00 | $49.94 | 3.00x | $16,611 |
| 105-7112 RMV (2"-8") TRT/UNTRT BASE & ASPH PAV | 165 CY | $80.00 | $8.43 | 9.49x | $11,809 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 320 CY | $45.00 | $12.93 | 3.48x | $10,264 |
| 552-7003 WIRE FENCE (TY C) | 470 LF | $28.00 | $12.12 | 2.31x | $7,464 |
| 500-7001 MOBILIZATION | 1 LS | $100,000.00 | $523,850.32 | 0.19x | -$423,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $2,500.00 | $11,585.04 | 0.22x | -$72,680 |
| 100-7002 PREPARING ROW | 4 STA | $2,500.00 | $6,072.92 | 0.41x | -$14,292 |
ALTUS CONSTRUCTION LLC: unbalanced items
Placed 2| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 462-7043 CONC BOX CULV (11 FT X 8 FT) | 160 LF | $2,121.27 | $1,123.92 | 1.89x | $159,576 |
| 100-7002 PREPARING ROW | 4 STA | $37,756.32 | $6,072.92 | 6.22x | $126,734 |
| 341-7001 D-GR HMA TY-B PG64-22 | 424 TON | $322.74 | $97.82 | 3.30x | $95,363 |
| 403-7001 TEMPORARY SPL SHORING | 1,500 SF | $60.10 | $25.56 | 2.35x | $51,809 |
| 110-7004 EXCAV (ROADWAY & CHANNEL) | 870 CY | $48.88 | $24.59 | 1.99x | $21,131 |
| 530-7015 DRIVEWAYS (BASE) | 120 SY | $150.12 | $27.85 | 5.39x | $14,673 |
| 500-7001 MOBILIZATION | 1 LS | $151,788.04 | $523,850.32 | 0.29x | -$372,062 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $3,723.91 | $11,585.04 | 0.32x | -$62,889 |
HODGES AND SON CONSTRUCTION COMPANY, INC.: unbalanced items
Placed 3| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 462-7043 CONC BOX CULV (11 FT X 8 FT) | 160 LF | $2,300.00 | $1,123.92 | 2.05x | $188,172 |
| 341-7001 D-GR HMA TY-B PG64-22 | 424 TON | $280.00 | $97.82 | 2.86x | $77,242 |
| 496-7008 REMOV STR (BOX CULVERT) | 130 LF | $435.00 | $85.27 | 5.10x | $45,465 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 1,000 SY | $40.00 | $12.30 | 3.25x | $27,704 |
| 496-7009 REMOV STR (BRIDGE 0 - 99 FT LENGTH) | 1 EA | $55,000.00 | $28,021.15 | 1.96x | $26,979 |
| 400-7010 CEM STABIL BKFL | 106 CY | $300.00 | $138.14 | 2.17x | $17,157 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 320 CY | $45.00 | $12.93 | 3.48x | $10,264 |
| 496-7005 REMOV STR (WINGWALL) | 4 EA | $4,000.00 | $1,898.40 | 2.11x | $8,406 |
| 500-7001 MOBILIZATION | 1 LS | $130,000.00 | $523,850.32 | 0.25x | -$393,850 |
EARTH BUILDERS, L.P.: unbalanced items
Placed 4| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 462-7043 CONC BOX CULV (11 FT X 8 FT) | 160 LF | $2,800.00 | $1,123.92 | 2.49x | $268,172 |
| 341-7001 D-GR HMA TY-B PG64-22 | 424 TON | $275.00 | $97.82 | 2.81x | $75,122 |
| 100-7002 PREPARING ROW | 4 STA | $20,000.00 | $6,072.92 | 3.29x | $55,708 |
| 416-7004 DRILL SHAFT (24 IN) | 210 LF | $450.00 | $234.98 | 1.92x | $45,155 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 1,000 SY | $40.00 | $12.30 | 3.25x | $27,704 |
| 400-7010 CEM STABIL BKFL | 106 CY | $300.00 | $138.14 | 2.17x | $17,157 |
| 552-7003 WIRE FENCE (TY C) | 470 LF | $40.00 | $12.12 | 3.30x | $13,104 |
| 450-7021 RAIL (TY T631LS) | 124 LF | $150.00 | $73.55 | 2.04x | $9,480 |
| 500-7001 MOBILIZATION | 1 LS | $180,000.00 | $523,850.32 | 0.34x | -$343,850 |
| 502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING | 8 MO | $5,000.00 | $11,585.04 | 0.43x | -$52,680 |
| 403-7001 TEMPORARY SPL SHORING | 1,500 SF | $10.00 | $25.56 | 0.39x | -$23,341 |
COPPELL CONSTRUCTION CO., INC.: unbalanced items
Placed 5| Item | Qty | Their price | Market | x market | $ vs market |
|---|---|---|---|---|---|
| 462-7043 CONC BOX CULV (11 FT X 8 FT) | 160 LF | $2,500.00 | $1,123.92 | 2.22x | $220,172 |
| 341-7001 D-GR HMA TY-B PG64-22 | 424 TON | $260.00 | $97.82 | 2.66x | $68,762 |
| 403-7001 TEMPORARY SPL SHORING | 1,500 SF | $65.00 | $25.56 | 2.54x | $59,159 |
| 496-7008 REMOV STR (BOX CULVERT) | 130 LF | $500.00 | $85.27 | 5.86x | $53,915 |
| 247-7044 FL BS (CMP IN PLC)(TY A GR 1-2) (6") | 1,000 SY | $35.00 | $12.30 | 2.85x | $22,704 |
| 400-7010 CEM STABIL BKFL | 106 CY | $325.00 | $138.14 | 2.35x | $19,807 |
| 496-7005 REMOV STR (WINGWALL) | 4 EA | $6,000.00 | $1,898.40 | 3.16x | $16,406 |
| 552-7003 WIRE FENCE (TY C) | 470 LF | $40.00 | $12.12 | 3.30x | $13,104 |
| 132-7004 EMBANK (FNL)(DC)(TY B) | 320 CY | $48.00 | $12.93 | 3.71x | $11,224 |
| 500-7001 MOBILIZATION | 1 LS | $160,000.00 | $523,850.32 | 0.31x | -$363,850 |