Bid Day Forecast: 6512-18-001

Jefferson · Dec 3, 2026 Sign up free
Set your company to personalize scores

Material Maintenance Project - Sealed

CCSJ 6512-18-001 · lets Dec 3, 2026 · Jefferson, Beaumont · US0069

$879,500Engineer's estimate Items at market: $754,066 (-14.3%)
$727,745Most likely low bid$661,276 to $844,246 (middle half)
4.3Expected bidders3 plan holders, 1 regular bidders
49/100Weak fitMarket only. Set your company for a personal score

Where the low bid should land

$516,383 (1 in 10 go lower)$1,007,576 (1 in 10 go higher)

From 109 comparable let jobs (district, estimates of $351,800 to $2,198,750, last 3 years). 80% of them went under the estimate; the typical low bid was -17.3% vs estimate.

Bid / no-bid score

  • Competition20 / 25Jobs like this draw about 4.3 bidders.
  • Margin2 / 20Low bids land at 83% of the estimate.

Set your company to add your experience, win rate and size fit.

Comparable jobs

Nov 2026 6508-25-001Jefferson · 7 bidders $360,270-16.2%
Nov 2026 6508-79-001Jasper · 8 bidders $319,025-23.6%
Sep 2026 6501-50-001Jefferson · 6 bidders $437,494-18.0%
Sep 2026 6491-31-001Liberty · 7 bidders $382,392-22.4%
Sep 2026 6487-54-001Jasper · 4 bidders $380,162-57.6%
Aug 2026 0920-39-028Chambers · 3 bidders $224,135-69.5%
Aug 2026 0920-39-033Chambers · 6 bidders $1,675,110+17.1%
Aug 2026 6488-31-001Jasper · 8 bidders $1,880,325-11.6%

The field: plan holders and how they bid

Last 3 years in Texas
Plan holderBidsWinsIn BeaumontAvg bid vs est.Avg win vs est.Their typical bid here
TOUCHSTONE RESOURCES, LLC SharpestBidders 4131706 of 8 11.0%0.5% $976,512
SHORETEX, LLCBidders 00
FLAGGSTONE DEVELOPMENT GROUP LLCBidders 00

"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.

Items that decide this job

9 of 9 items priced from low bids
ItemQtyMarket priceRange of low bidsAt marketShare
8011-7146 D-GR HMA TY D PG 70-22 (DEL) SITE 135 low bids 1,500 TON$117.96$92.00 – $200.00 $176,93423.5%
8011-7149 D-GR HMA TY D PG 70-22 (DEL) SITE 42 low bids 1,000 TON$167.50$165.00 – $170.00 $167,50022.2%
8011-7148 D-GR HMA TY D PG 70-22 (DEL) SITE 34 low bids 1,000 TON$165.00$165.00 – $165.00 $165,00021.9%
8011-7147 D-GR HMA TY D PG 70-22 (DEL) SITE 27 low bids 1,000 TON$142.41$113.00 – $170.00 $142,41218.9%
8011-7055 D-GR HMA TY D PG 64-22 (PICKUP)150 low bids 300 TON$89.12$59.00 – $147.00 $26,7373.5%
8011-7127 D-GR HMA TY C PG 70-22 (PICKUP)13 low bids 200 TON$120.24$87.00 – $137.00 $24,0493.2%
8011-7145 D-GR HMA TY D PG 70-22 (PICKUP)35 low bids 200 TON$111.44$78.50 – $142.00 $22,2883.0%
8011-7001 D-GR HMA TY B PG 64-22 (PICKUP)56 low bids 300 TON$69.58$54.00 – $132.00 $20,8742.8%
8011-7037 D-GR HMA TY C PG 64-22 (PICKUP)45 low bids 100 TON$82.72$58.00 – $150.00 $8,2721.1%