Routine Maintenance Project - Sealed
CCSJ 6511-55-001 · lets Dec 3, 2026 · Terry, Lubbock · US0062
$421,350Engineer's estimate
Items at market: $284,383 (-32.5%)
$351,449Most likely low bid$274,623 to $385,834 (middle half)
3.6Expected bidders3 plan holders, 3 regular bidders
56/100Worth a lookMarket only. Set your company for a personal score
Where the low bid should land
$351,449
Estimate $421,350
$234,800 (1 in 10 go lower)$590,612 (1 in 10 go higher)
From 40 comparable let jobs (district + work type, estimates of $168,540 to $1,053,375, last 3 years). 85% of them went under the estimate; the typical low bid was -16.6% vs estimate.
Bid / no-bid score
- Competition23 / 25Jobs like this draw about 3.6 bidders.
- Margin2 / 20Low bids land at 83% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6510-77-001Hale · 4 bidders | $158,004-55.3% |
| Nov 2026 | 6510-78-001Hale · 4 bidders | $297,939-21.9% |
| Nov 2026 | 6510-79-001Lamb · 3 bidders | $331,625-36.1% |
| Nov 2026 | 6510-80-001Hale · 3 bidders | $182,004-63.4% |
| Sep 2026 | 6510-24-001Crosby · 5 bidders | $595,302-13.7% |
| Sep 2026 | 6504-26-001Terry · 4 bidders | $377,840-19.9% |
| Sep 2026 | 6504-27-001Lamb · 4 bidders | $715,655-10.6% |
| Sep 2026 | 6504-28-001Hale · 4 bidders | $465,946-7.8% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Lubbock | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| ROSS SA ENTERPRISE LLC SharpestBidders | 98 | 40 | 3 of 4 | -19.4% | -24.5% | $339,622 |
| TI-ZACK CONCRETE, LLCBidders | 133 | 19 | 2 of 15 | 3.1% | -7.5% | $434,568 |
| T&L CLEANING SERVICES LLCBidders | 105 | 29 | 0 of 1 | 4.7% | -18.0% | $441,329 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
10 of 10 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 770-7037 REPLACE GUARDRAIL END TREATMENT SYSTEM29 low bids · prices swing 8x | 35 EA | $3,116.90 | $1,300.00 – $10,000.00 | $109,091 | 38.4% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 360 DAY | $217.57 | $0.0010 – $16,487.00 | $78,326 | 27.5% |
| 770-7035 REPLACE W-BEAM RAIL29 low bids · prices swing 6x | 2,500 LF | $24.10 | $10.00 – $55.00 | $60,254 | 21.2% |
| 500-7002 MOBILIZATION (CALLOUT)748 low bids · prices swing 535,000,000x | 24 EA | $600.85 | $0.0010 – $535,000.00 | $14,420 | 5.1% |
| 770-7040 REMOVE RAIL16 low bids · prices swing 8,200x | 1,000 LF | $9.45 | $0.0100 – $82.00 | $9,449 | 3.3% |
| 770-7026 REPLACE DOWNSTREAM ANCHOR TERMINAL62 low bids · prices swing 2,500x | 10 EA | $534.87 | $1.00 – $2,500.00 | $5,349 | 1.9% |
| 770-7039 REPLACE LOW FILL CULVERT RAIL11 low bids · prices swing 50x | 250 LF | $13.50 | $1.00 – $50.00 | $3,375 | 1.2% |
| 770-7038 REPLACE CURVED RAIL21 low bids · prices swing 100x | 100 LF | $26.19 | $1.00 – $100.00 | $2,619 | 0.9% |
| 770-7036 REPLACE THRIE-BEAM RAIL26 low bids · prices swing 500x | 25 LF | $48.04 | $1.00 – $500.00 | $1,201 | 0.4% |
| 770-7041 REPLACE GDRL END TREATMENT MRKR9 low bids · prices swing 1,000x | 10 EA | $29.93 | $1.00 – $1,000.00 | $299 | 0.1% |