Routine Maintenance Project - Sealed
CCSJ 6509-26-001 · lets Dec 8, 2026 · Fort Bend, Houston · US0059
$410,070Engineer's estimate
Items at market: $313,895 (-23.5%)
$350,761Most likely low bid$307,246 to $391,633 (middle half)
3.7Expected bidders8 plan holders, 6 regular bidders
58/100Worth a lookMarket only. Set your company for a personal score
Where the low bid should land
$350,761
Estimate $410,070
$246,076 (1 in 10 go lower)$453,578 (1 in 10 go higher)
From 65 comparable let jobs (district + work type, estimates of $164,028 to $1,025,175, last 3 years). 82% of them went under the estimate; the typical low bid was -14.5% vs estimate.
Bid / no-bid score
- Competition22 / 25Jobs like this draw about 3.7 bidders.
- Margin4 / 20Low bids land at 86% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6506-72-001Harris · 3 bidders | $765,790+31.8% |
| Nov 2026 | 6507-15-001Brazoria · 4 bidders | $539,652-4.5% |
| Oct 2026 | 6508-18-001Harris · 2 bidders | $699,987+2.9% |
| Oct 2026 | 6508-74-001Waller · 3 bidders | $384,715-27.8% |
| Sep 2026 | 6499-61-001Montgomery · 1 bidders | $697,730-4.1% |
| Sep 2026 | 6494-58-001Fort Bend · 2 bidders | $667,500+25.3% |
| Sep 2026 | 6500-36-001Waller · 1 bidders | $239,693+9.7% |
| Aug 2026 | 6501-01-001Harris · 2 bidders | $888,100+15.2% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Houston | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| ROW Contractors LLC SharpestBidders | 12 | 1 | -7.5% | -8.0% | $379,373 | |
| SKYLINE CONSTRUCTION PAVING & STRIPINGBidders | 49 | 6 | 0 of 3 | 4.5% | -20.5% | $428,608 |
| WESTERN CERTIFIED ARBORISTSBidders | 61 | 2 | 16.4% | 3.4% | $477,397 | |
| S FOWLER SERVICES LLCBidders | 73 | 9 | 1 of 2 | 20.5% | -19.6% | $494,259 |
| YELLOWSTONE LANDSCAPE - CENTRAL, INC.Bidders | 51 | 12 | 12 of 28 | 27.8% | -6.6% | $524,197 |
| LOOKS GREAT SERVICES OF MS, INC.Bidders | 67 | 4 | 0 of 1 | 29.2% | 22.9% | $529,647 |
| SHORETEX, LLCBidders | 0 | 0 | ||||
| FLAGGSTONE DEVELOPMENT GROUP LLCBidders | 0 | 0 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
9 of 9 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 752-7001 TREE TRIMMING / BRUSH REMOVAL137 low bids · prices swing 64,000x | 100 MI | $1,716.86 | $1.00 – $64,000.00 | $171,686 | 54.7% |
| 752-7005 TREE REMOVAL (4" - 12" DIA)186 low bids · prices swing 2,000x | 1,500 EA | $60.77 | $1.00 – $2,000.00 | $91,161 | 29.0% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 80 DAY | $217.57 | $0.0010 – $16,487.00 | $17,406 | 5.5% |
| 752-7008 TREE REMOVAL (24" - 30" DIA)137 low bids · prices swing 5,500x | 50 EA | $208.61 | $1.00 – $5,500.00 | $10,431 | 3.3% |
| 752-7003 TREE TRIMMING / BRUSH REMOVAL(CHANNELS)110 low bids · prices swing 750,000,000x | 5 AC | $1,602.83 | $0.0010 – $750,000.00 | $8,014 | 2.6% |
| 500-7002 MOBILIZATION (CALLOUT)748 low bids · prices swing 535,000,000x | 12 EA | $600.85 | $0.0010 – $535,000.00 | $7,210 | 2.3% |
| 752-7006 TREE REMOVAL (12" - 18" DIA)151 low bids · prices swing 2,500x | 50 EA | $100.44 | $1.00 – $2,500.00 | $5,022 | 1.6% |
| 752-7007 TREE REMOVAL (18" - 24" DIA)147 low bids · prices swing 3,000x | 15 EA | $141.37 | $1.00 – $3,000.00 | $2,120 | 0.7% |
| 500-7033 MOBILIZATION (EMERGENCY)256 low bids · prices swing 20,000,000x | 1 EA | $844.81 | $0.0010 – $20,000.00 | $845 | 0.3% |