Routine Maintenance Project - Sealed
CCSJ 6508-63-001 · lets Dec 10, 2026 · La Salle, Laredo · IH0035
$489,500Engineer's estimate
Items at market: $584,058 (+19.3%)
$517,210Most likely low bid$450,118 to $576,601 (middle half)
2.1Expected bidders2 plan holders, 2 regular bidders
93/100Strong fit: bid itMarket only. Set your company for a personal score
Where the low bid should land
$517,210
Estimate $489,500
$418,806 (1 in 10 go lower)$658,574 (1 in 10 go higher)
From 14 comparable let jobs (district + work type, estimates of $195,800 to $1,223,750, last 3 years). 36% of them went under the estimate; the typical low bid was 5.7% vs estimate.
Bid / no-bid score
- Competition25 / 25Jobs like this draw about 2.1 bidders.
- Margin17 / 20Low bids land at 106% of the estimate.
Set your company to add your experience, win rate and size fit.
Comparable jobs
| Nov 2026 | 6509-66-001Dimmit · 4 bidders | $428,848-8.9% |
| Jun 2026 | 6499-01-001Webb · 3 bidders | $623,184+4.3% |
| Jun 2026 | 6500-57-001Maverick · 3 bidders | $460,615+4.8% |
| Jun 2026 | 6499-00-001Webb · 1 bidders | $885,125+12.1% |
| May 2026 | 6498-99-001La Salle · 1 bidders | $632,346+19.0% |
| Nov 2025 | 6492-47-001Kinney · 2 bidders | $241,954-18.1% |
| Nov 2025 | 6492-75-001Duval · 2 bidders | $569,033+19.0% |
| Nov 2025 | 6492-99-001Val Verde · 3 bidders | $528,285-5.4% |
The field: plan holders and how they bid
Last 3 years in Texas| Plan holder | Bids | Wins | In Laredo | Avg bid vs est. | Avg win vs est. | Their typical bid here |
|---|---|---|---|---|---|---|
| HJC FARMS, INC. SharpestBidders | 108 | 20 | 2 of 3 | 4.7% | -7.0% | $512,629 |
| WG ENGINEERING & CONSTRUCTION, LLCBidders | 90 | 13 | 9.2% | 10.1% | $534,666 |
"Typical bid here" is the estimate times that contractor's average bid ratio. Plan holders with no bids are usually suppliers or subs.
Items that decide this job
23 of 23 items priced from low bids| Item | Qty | Market price | Range of low bids | At market | Share |
|---|---|---|---|---|---|
| 500-7004 MOBILIZATION (CALLOUT 2)19 low bids · prices swing 1,100,000,000x | 10 EA | $18,951.60 | $0.0010 – $1,100,000.00 | $189,516 | 32.4% |
| 636-7005 REPLACE EXISTING ALUMINUM SIGNS(TY G)37 low bids · prices swing 6x | 2,600 SF | $34.37 | $23.00 – $142.00 | $89,372 | 15.3% |
| 644-7027 IN SM RD SN SUP&AM TYS80(1)SA(P-EXAL)4 low bids · prices swing 4x | 60 EA | $955.95 | $250.00 – $1,100.00 | $57,357 | 9.8% |
| 647-7008 REMOVE AND RESET LRSA3 low bids · prices swing 6x | 10 EA | $3,675.00 | $1,000.00 – $5,500.00 | $36,750 | 6.3% |
| 647-7001 INSTALL LRSS (STRUCT STEEL)111 low bids · prices swing 8x | 4,500 LB | $7.97 | $3.00 – $25.00 | $35,884 | 6.1% |
| 416-7032 DRILL SHAFT (SIGN MTS) (48 IN)30 low bids · prices swing 5x | 32 LF | $661.43 | $250.00 – $1,200.00 | $21,166 | 3.6% |
| 647-7003 REMOVE LRSA97 low bids · prices swing 100x | 25 EA | $842.12 | $100.00 – $10,000.00 | $21,053 | 3.6% |
| 416-7031 DRILL SHAFT (SIGN MTS) (42 IN)20 low bids · prices swing 12x | 30 LF | $679.76 | $360.00 – $4,360.00 | $20,393 | 3.5% |
| 636-7002 ALUMINUM SIGNS (TY G)112 low bids · prices swing 10x | 550 SF | $34.70 | $16.00 – $156.00 | $19,082 | 3.3% |
| 644-7048 IN SM RD SN SUP&AM TYS80(2)SA(P)24 low bids · prices swing 4x | 10 EA | $1,822.52 | $760.00 – $3,050.00 | $18,225 | 3.1% |
| 647-7002 RELOCATE LRSA26 low bids · prices swing 10x | 5 EA | $2,343.24 | $1,000.00 – $10,000.00 | $11,716 | 2.0% |
| 636-7003 ALUMINUM SIGNS (TY O)81 low bids · prices swing 9x | 300 SF | $35.17 | $15.00 – $135.00 | $10,550 | 1.8% |
| 505-7001 TMA (STATIONARY)2363 low bids · prices swing 16,487,000x | 40 DAY | $217.57 | $0.0010 – $16,487.00 | $8,703 | 1.5% |
| 432-7001 RIPRAP (CONC)(4 IN)321 low bids · prices swing 153x | 15 CY | $573.24 | $50.00 – $7,650.86 | $8,599 | 1.5% |
| 416-7024 DRILL SHAFT (NON - REINFORCED) (12 IN)24 low bids · prices swing 9x | 50 LF | $151.56 | $25.00 – $230.69 | $7,578 | 1.3% |