| 10 | 201(A)1200 |
CLEARING AND GRUBBING | 1 | LSUM |
$3,000.00 |
$8,100.00 |
$30,500.00 |
$15,000.00 |
$20,000.00 |
$50,000.00 |
$80,000.00 |
| 20 | 202(A)2200 |
UNCLASSIFIED EXCAVATION | 3,119 | CY |
$12.50 |
$14.07 |
$10.00 |
$26.00 |
$13.25 |
$15.00 |
$25.00 |
| 30 | 202(D)2500 |
UNCLASSIFIED BORROW | 250 | CY |
$14.00 |
$36.00 |
$12.00 |
$32.50 |
$3.25 |
$20.00 |
$25.00 |
| 40 | 205(A)6200 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$14,500.00 |
$5,500.00 |
$8,500.00 |
$13,500.00 |
$8,750.00 |
$50,000.00 |
$15,000.00 |
| 50 | 221(B)2300 |
TEMPORARY SILT FENCE | 551 | LF |
$4.00 |
$7.00 |
$7.50 |
$3.00 |
$4.00 |
$5.00 |
$8.00 |
| 60 | 221(E)2600 |
TEMPORARY SILT DIKE | 54 | LF |
$15.00 |
$16.00 |
$20.00 |
$10.00 |
$22.00 |
$25.00 |
$15.00 |
| 70 | 221(H)2900 |
(PL)TEMPORARY INLET SEDIMENT FILTER | 3 | EA |
$450.00 |
$480.00 |
$925.00 |
$350.00 |
$450.00 |
$1,000.00 |
$230.00 |
| 80 | 230(A)7200 |
SOLID SLAB SODDING | 8,008 | SY |
$4.25 |
$4.24 |
$7.89 |
$4.75 |
$5.50 |
$7.00 |
$8.00 |
| 90 | 233(A)0200 |
VEGETATIVE MULCHING | 1.65 | AC |
$1,750.00 |
$2,002.00 |
$3,800.00 |
$1,250.00 |
$500.00 |
$4,000.00 |
$2,800.00 |
| 100 | 241 3100 |
MOWING | 3.3 | AC |
$275.00 |
$275.00 |
$1,100.00 |
$350.00 |
$350.00 |
$1,500.00 |
$500.00 |
| 110 | 307(K)4200 |
STABILIZED SUBGRADE | 3,361 | SY |
$12.50 |
$12.48 |
$14.50 |
$12.50 |
$18.00 |
$15.00 |
$38.00 |
| 120 | 402(E)2600 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 28 | TON |
$55.00 |
$97.07 |
$55.00 |
$60.00 |
$76.50 |
$70.00 |
$90.00 |
| 130 | 407(B)7300 |
TACK COAT | 505 | GAL |
$5.00 |
$3.12 |
$3.50 |
$3.00 |
$3.00 |
$6.00 |
$6.00 |
| 140 | 408 8100 |
PRIME COAT | 1,177 | GAL |
$7.00 |
$1.10 |
$5.50 |
$1.00 |
$1.00 |
$6.00 |
$9.00 |
| 150 | 411(B)1330 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 1,312 | TON |
$150.00 |
$182.26 |
$142.00 |
$175.00 |
$195.00 |
$135.00 |
$180.00 |
| 160 | 411(C)1430 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 386 | TON |
$175.00 |
$208.00 |
$195.00 |
$207.50 |
$230.00 |
$165.00 |
$265.00 |
| 170 | 509(D)0500 |
CLASS C CONCRETE | 30 | CY |
$500.00 |
$578.00 |
$500.00 |
$450.00 |
$376.00 |
$500.00 |
$600.00 |
| 180 | 611(G)7930 |
INLET GPI TYPE 1 (DES. 1) | 3 | EA |
$5,000.00 |
$6,430.00 |
$5,000.00 |
$7,055.00 |
$6,850.00 |
$6,500.00 |
$5,000.00 |
| 190 | 613(A)5208 |
18" R.C.PIPE CLASS III | 96 | LF |
$101.00 |
$125.07 |
$63.00 |
$129.25 |
$157.00 |
$150.00 |
$150.00 |
| 200 | 613(B)5508 |
18" CORR. GALV. STEEL PIPE | 112 | LF |
$53.00 |
$58.32 |
$47.00 |
$80.00 |
$92.00 |
$100.00 |
$120.00 |
| 210 | 613(M)7004 |
TYPE A6 CULVERT END TREATMENT | 4 | EA |
$2,880.00 |
$3,890.00 |
$3,148.00 |
$3,475.00 |
$2,140.00 |
$2,500.00 |
$3,000.00 |
| 220 | 619(B)6352 |
REMOVAL OF FENCE | 1,599 | LF |
$3.00 |
$2.20 |
$2.50 |
$0.5500 |
$1.10 |
$10.00 |
$3.00 |
| 230 | 619(B)6360 |
REMOVAL OF CONCRETE PAVEMENT | 75 | SY |
$15.00 |
$50.00 |
$30.00 |
$15.00 |
$37.50 |
$15.00 |
$50.00 |
| 240 | 619(B)6364 |
REMOVAL OF ASPHALT PAVEMENT | 3,077 | SY |
$12.00 |
$13.24 |
$4.00 |
$15.00 |
$8.20 |
$15.00 |
$30.00 |
| 250 | 619(B)6396 |
REMOVAL OF GUARDRAIL | 460 | LF |
$8.00 |
$8.00 |
$4.00 |
$5.00 |
$9.38 |
$4.00 |
$5.00 |
| 260 | 624(C)3410 |
FENCE-STYLE SWF (6 BARBED WIRE) | 1,410 | LF |
$15.00 |
$9.20 |
$6.20 |
$6.50 |
$8.58 |
$10.00 |
$12.00 |
| 270 | 629(D)7500 |
REMOVE AND RESET MAILBOX | 1 | EA |
$450.00 |
$450.00 |
$500.00 |
$300.00 |
$500.00 |
$500.00 |
$650.00 |
| 280 | 202(A)2210 |
UNCLASSIFIED EXCAVATION | 1,800 | CY |
$12.00 |
$10.10 |
$8.00 |
$8.00 |
$10.09 |
$15.00 |
$25.00 |
| 290 | 501(A)1210 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 470 | CY |
$40.00 |
$21.00 |
$30.00 |
$40.00 |
$17.95 |
$50.00 |
$25.00 |
| 300 | 502 3101 |
TEMPORARY EARTH RETAINAGE | 26 | LF |
$800.00 |
$768.00 |
$5,629.30 |
$957.00 |
$1,167.50 |
$500.00 |
$250.00 |
| 310 | 509(A)0210 |
CLASS AA CONCRETE | 604.7 | CY |
$810.00 |
$654.66 |
$624.77 |
$687.95 |
$819.00 |
$1,200.00 |
$900.00 |
| 320 | 511(A)2210 |
REINFORCING STEEL | 105,600 | LB |
$1.80 |
$1.56 |
$1.00 |
$1.50 |
$1.59 |
$2.00 |
$4.00 |
| 330 | 601(A)1110 |
TYPE I PLAIN RIPRAP | 90 | TON |
$90.00 |
$85.00 |
$90.00 |
$90.00 |
$94.25 |
$125.00 |
$150.00 |
| 340 | 619(D)6700 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$30,000.00 |
$51,800.00 |
$45,000.00 |
$25,000.00 |
$51,000.00 |
$50,000.00 |
$45,000.00 |
| 350 | 823 6100 |
(SP)PORTABLE TRAFFIC SIGNAL SYSTEM | 180 | SD |
$250.00 |
$130.00 |
$135.00 |
$130.00 |
$148.50 |
$150.00 |
$200.00 |
| 360 | 857(A)9205 |
CONSTRUCTION TRAFFIC STR.(PAINT)(6" WIDE) | 14,273 | LF |
$0.6500 |
$0.5400 |
$0.3000 |
$0.5200 |
$0.3300 |
$0.5000 |
$0.4000 |
| 370 | 857(F)9700 |
PAVEMENT MRKNG.REMOVAL(TRAF.STRP) | 10,882 | LF |
$0.6000 |
$0.7900 |
$0.1400 |
$0.7500 |
$0.1500 |
$0.2000 |
$0.2500 |
| 380 | 871(B)2300 |
CONST.ZONE IMPACT ATTEN. | 432 | SD |
$30.00 |
$6.61 |
$10.00 |
$6.10 |
$11.00 |
$15.00 |
$12.00 |
| 390 | 877(B)4300 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 840 | LF |
$30.50 |
$31.00 |
$33.00 |
$25.00 |
$33.60 |
$35.00 |
$40.00 |
| 400 | 877(C)4400 |
RELOCATION OF PORT. LONGITUDINAL BARRIER | 840 | LF |
$8.00 |
$7.50 |
$5.50 |
$6.00 |
$6.60 |
$10.00 |
$12.00 |
| 410 | 880(B)6300 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 3,888 | SD |
$1.00 |
$0.0400 |
$0.2500 |
$0.0300 |
$0.2800 |
$0.3500 |
$0.4000 |
| 420 | 880(B)6310 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 4,500 | SD |
$1.50 |
$0.0400 |
$0.1000 |
$0.0300 |
$0.1100 |
$0.2000 |
$0.1500 |
| 430 | 880(B)6320 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 5,076 | SD |
$3.10 |
$0.0400 |
$0.0500 |
$0.0300 |
$0.0500 |
$0.1000 |
$0.0600 |
| 440 | 880(C)6410 |
CONSTRUCTION BARRICADES(TYPE III) | 1,368 | SD |
$3.00 |
$0.0400 |
$0.2500 |
$0.0300 |
$0.2800 |
$0.3500 |
$0.3500 |
| 450 | 880(E)6607 |
WARNING LIGHTS(TYPE B) | 7,848 | SD |
$0.6500 |
$0.0400 |
$0.0500 |
$0.0300 |
$0.0500 |
$0.1000 |
$0.0600 |
| 460 | 880(G)6805 |
CHANNELIZER CONES | 10,224 | SD |
$0.5500 |
$0.5000 |
$0.2500 |
$5.00 |
$0.2800 |
$0.3500 |
$0.3500 |
| 470 | 882(A)8210 |
PORT.CHANGEABLE MESSAGE SIGN | 504 | SD |
$20.00 |
$3.27 |
$10.00 |
$3.10 |
$11.00 |
$12.00 |
$12.00 |
| 480 | 850(A)1200 |
SHEET ALUMINUM SIGNS | 79 | SF |
$50.00 |
$67.00 |
$28.00 |
$63.00 |
$31.00 |
$32.00 |
$35.00 |
| 490 | 851(C)2420 |
2 1/4" SQUARE TUBE POST | 60 | LF |
$18.00 |
$8.90 |
$11.00 |
$8.10 |
$12.00 |
$15.00 |
$15.00 |
| 500 | 853 5155 |
DELINEATORS(TYPE 2, CODE 3, FLEXIBLE) | 4 | EA |
$90.00 |
$89.00 |
$75.00 |
$81.00 |
$82.50 |
$100.00 |
$100.00 |
| 510 | 856(A)8207 |
(SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(6" WIDE) | 9,840 | LF |
$0.9500 |
$1.15 |
$0.9000 |
$1.10 |
$1.00 |
$1.00 |
$1.20 |
| 520 | 856(A)8215 |
(SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(12" WIDE) | 189 | LF |
$2.25 |
$2.70 |
$1.50 |
$2.55 |
$1.65 |
$1.75 |
$2.00 |
| 530 | 856(A)8219 |
(SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(24" WIDE) | 36 | LF |
$15.00 |
$13.00 |
$15.00 |
$12.00 |
$16.50 |
$20.00 |
$20.00 |
| 540 | 857(F)9700 |
PAVEMENT MRKNG.REMOVAL(TRAF.STRP) | 5,567 | LF |
$0.5500 |
$0.8700 |
$0.2500 |
$1.00 |
$0.2800 |
$0.3500 |
$0.3500 |
| 550 | 642(B)3300 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$10,000.00 |
$21,600.00 |
$8,500.00 |
$2,500.00 |
$8,500.00 |
$25,000.00 |
$20,000.00 |
| 560 | 220 1100 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$5,000.00 |
$3,500.00 |
$8,000.00 |
$5,000.00 |
$4,575.00 |
$23,000.00 |
$5,500.00 |
| 570 | 641 2110 |
MOBILIZATION | 1 | LSUM |
$105,000.00 |
$81,250.00 |
$152,277.00 |
$103,000.00 |
$100,000.00 |
$125,000.00 |
$125,000.00 |