Bid tab 260185

Let Aug 13, 2026 · Division 5 · Custer

‹ Aug 2026 results

Let job

Let date
Thursday, August 13, 2026
Contract
260185 · job page
J/P numbers
24145(07)
District
Division 5
County
Custer
Highway
Classification
·
Project number
STP-120C(130)PM
Working days
240

Bidders 7

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$9,825,990
1 Caswell Contracting, Inc. Low bidder $8,341,112 -15.1%
2 CORNELL CONSTRUCTION COMPANY, INC. $9,095,564 -7.4% +9.0%
3 OVERLAND CORPORATION $9,150,523 -6.9% +9.7%
4 THE CUMMINS CONSTRUCTION CO., INC. $9,241,861 -5.9% +10.8%
5 J&R Constructors Group $9,470,818 -3.6% +13.5%
6 BRIDGECO CONTRACTORS, INC. $10,777,155 +9.7% +29.2%
7 Robinson Construction, LLC $11,943,976 +21.6% +43.2%

Bid tab: unit prices 73 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Caswell Contrac…#2 CORNELL CONSTRU…#3 OVERLAND CORPOR…#4 THE CUMMINS CON…#5 J&R Constructor…#6 BRIDGECO CONTRA…#7 Robinson Constr…
10201(A)1200 CLEARING AND GRUBBING1LSUM $50,000.00 $24,000.00 $139,476.01 $167,450.00 $124,630.00 $24,000.00 $89,000.00 $125,000.00
20202(A)2200 UNCLASSIFIED EXCAVATION184,542CY $8.60 $5.78 $5.02 $5.75 $5.35 $5.78 $6.62 $15.65
30205(A)6200 TYPE A-SALVAGED TOPSOIL1LSUM $50,000.00 $72,000.00 $110,000.00 $125,000.00 $113,300.00 $72,000.00 $107,000.00 $240,000.00
40221(B)2300 TEMPORARY SILT FENCE1,000LF $5.00 $2.87 $2.87 $2.87 $3.35 $2.87 $3.37 $3.60
50221(C)2410 REINFORCED SILT FENCE13,593LF $5.10 $4.00 $4.00 $4.00 $11.60 $4.00 $4.65 $7.50
60221(D)2500 TEMPORARY SEDIMENT BASIN2EA $6,550.00 $5,000.00 $2,335.59 $2,522.32 $7,085.00 $6,300.00 $1,450.00 $2,650.00
70221(E)2600 TEMPORARY SILT DIKE1,080LF $13.90 $10.70 $10.70 $10.70 $14.45 $10.70 $14.70 $9.80
80221(F)2700 TEMPORARY ROCK FILTER DAM TYPE 133CY $151.10 $114.00 $109.82 $536.42 $128.75 $195.00 $132.00 $65.00
90221(F)2710 TEMPORARY ROCK FILTER DAM TYPE 2120CY $172.65 $114.00 $141.93 $339.62 $149.35 $225.00 $132.00 $65.00
100221(F)2720 TEMPORARY ROCK FILTER DAM TYPE 328.4CY $167.10 $114.00 $127.83 $342.81 $164.80 $250.00 $165.00 $65.00
110221(G)2800 TEMPORARY FIBER LOG9,344LF $5.50 $2.20 $2.20 $2.20 $8.75 $2.20 $2.70 $7.20
120221(H)2900 (PL)TEMPORARY INLET SEDIMENT FILTER1EA $465.00 $300.00 $300.00 $300.00 $875.50 $300.00 $390.00 $540.00
130227 4105 (SP)TURF REINFORCEMENT MAT TYPE 16,500SY $15.00 $15.50 $15.50 $15.50 $5.70 $15.50 $17.10 $31.20
140230(A)7200 SOLID SLAB SODDING270,707SY $2.55 $2.96 $2.96 $2.96 $3.15 $2.96 $3.30 $3.66
150233(A)0200 VEGETATIVE MULCHING44.51AC $1,178.00 $505.00 $505.00 $505.00 $1,648.00 $505.00 $565.00 $960.00
160241 3100 MOWING147.8AC $250.00 $150.00 $150.00 $150.00 $206.00 $150.00 $210.00 $270.00
170307(K)4200 STABILIZED SUBGRADE54,034.48SY $8.85 $6.87 $4.38 $6.75 $3.10 $6.87 $6.24 $8.90
180402(E)2600 TRAFFIC BOUND SURFACE COURSE TYPE E1,071.37TON $45.50 $55.00 $44.83 $44.83 $46.20 $55.00 $48.00 $38.55
190407(B)7300 TACK COAT11,667.61GAL $3.70 $3.12 $2.79 $3.75 $4.00 $3.50 $2.40 $3.55
200408 8100 PRIME COAT26,509.66GAL $3.55 $0.0500 $0.0100 $4.50 $4.00 $4.00 $2.20 $3.60
210411(B)1330 SUPERPAVE, TYPE S3(PG 64-22 OK)20,311.6TON $105.05 $101.81 $117.35 $103.00 $99.35 $105.00 $128.75 $112.40
220411(C)1400 SUPERPAVE, TYPE S4(PG 76-28 OK)13,119.41TON $121.10 $106.30 $127.32 $120.00 $123.80 $130.00 $164.80 $118.65
230411(C)1430 SUPERPAVE, TYPE S4(PG 64-22 OK)1,604.37TON $143.00 $121.34 $129.88 $118.00 $106.45 $160.00 $152.25 $128.55
240412 3100 COLD MILLING PAVEMENT75,611.99SY $2.65 $0.8800 $0.9400 $2.75 $2.85 $1.25 $4.45 $3.80
250509(A)0200 CLASS AA CONCRETE496.14CY $737.40 $960.00 $960.00 $610.00 $686.45 $960.00 $825.00 $880.00
260509(D)0500 CLASS C CONCRETE185CY $466.35 $445.00 $445.00 $400.00 $412.00 $445.00 $456.43 $685.00
270511(A)2200 REINFORCING STEEL74,314LB $1.50 $1.50 $1.50 $1.35 $1.40 $1.50 $1.52 $1.60
280613(A)5208 18" R.C.PIPE CLASS III82LF $110.30 $101.00 $80.39 $80.39 $82.80 $101.00 $107.00 $98.00
290613(A)5216 24" R.C.PIPE CLASS III84LF $115.85 $140.00 $112.92 $112.92 $116.30 $140.00 $118.00 $122.00
300613(A)5220 30" R.C.PIPE CLASS III90LF $150.00 $173.00 $132.90 $132.90 $136.90 $173.00 $152.00 $142.80
310613(A)5358 28" X 18" R.C.PIPE ARCH CLASS A-III72LF $155.00 $165.00 $130.15 $130.15 $134.05 $165.00 $164.00 $124.60
320613(B)5508 18" CORR. GALV. STEEL PIPE1,150LF $55.00 $60.40 $44.19 $44.19 $45.55 $60.40 $46.00 $54.00
330613(B)5516 24" CORR. GALV. STEEL PIPE247LF $70.00 $95.00 $55.36 $55.36 $57.05 $95.00 $62.00 $84.00
340613(B)5524 30" CORR. GALV. STEEL PIPE68LF $80.00 $98.00 $63.72 $63.72 $65.65 $98.00 $77.00 $88.00
350613(B)5608 24" X 18" CORR. GALV. STEEL PIPE ARCH552LF $80.00 $77.00 $49.18 $49.18 $50.65 $77.00 $51.00 $112.50
360613(B)5612 28" X 20" CORR. GALV. STEEL PIPE ARCH44LF $75.00 $85.00 $56.37 $56.37 $58.05 $85.00 $75.00 $146.60
370613(B)5616 35" X 24" CORR. GALV. STEEL PIPE ARCH240LF $125.00 $99.50 $68.32 $68.32 $70.40 $99.50 $69.00 $255.00
380613(L)6724 30" PREFAB. CULVERT END SEC., ROUND2EA $2,000.00 $2,580.00 $1,882.00 $1,882.00 $1,940.00 $2,580.00 $2,750.00 $1,800.00
390613(M)6960 TYPE A4 CULVERT END TREATMENT2EA $2,000.00 $2,260.00 $2,260.00 $1,900.00 $1,957.00 $2,260.00 $2,750.00 $3,500.00
400613(M)6964 TYPE B4 CULVERT END TREATMENT2EA $2,500.00 $2,905.00 $2,905.00 $2,100.00 $2,163.00 $2,905.00 $3,000.00 $2,850.00
410613(M)6968 TYPE C4 CULVERT END TREATMENT2EA $3,000.00 $3,550.00 $3,550.00 $2,300.00 $2,369.00 $3,550.00 $3,250.00 $5,500.00
420613(M)7004 TYPE A6 CULVERT END TREATMENT34EA $2,400.00 $2,910.00 $2,910.00 $2,200.00 $2,266.00 $2,910.00 $2,980.00 $2,250.00
430613(M)7008 TYPE B6 CULVERT END TREATMENT7EA $2,900.00 $3,695.00 $3,695.00 $2,400.00 $2,472.00 $3,695.00 $3,400.00 $3,650.00
440613(M)7012 TYPE C6 CULVERT END TREATMENT2EA $4,000.00 $5,075.00 $5,075.00 $2,800.00 $2,884.00 $5,075.00 $3,600.00 $4,000.00
450613(M)7024 TYPE AA6 CULVERT END TREATMENT6EA $3,000.00 $4,675.00 $4,675.00 $3,200.00 $3,296.00 $4,675.00 $3,600.00 $3,865.00
460613(M)7028 TYPE BB6 CULVERT END TREATMENT4EA $5,500.00 $5,635.00 $5,635.00 $4,000.00 $4,120.00 $5,635.00 $4,950.00 $4,255.00
470619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $50,000.00 $125,000.00 $40,000.00 $45,549.00 $59,328.00 $125,000.00 $85,700.00 $72,000.00
480619(B)6364 REMOVAL OF ASPHALT PAVEMENT28,705SY $6.00 $1.40 $8.28 $8.14 $6.15 $5.00 $6.53 $9.20
490624(C)3410 FENCE-STYLE SWF (6 BARBED WIRE)38,443LF $7.50 $5.90 $5.85 $6.00 $6.25 $5.85 $6.51 $7.55
500857(A)9200 CONSTRUCTION TRAFFIC STR.(PAINT)(4" WIDE)197,120LF $0.2500 $0.1700 $0.1000 $0.1000 $0.1000 $0.1700 $0.2500 $0.2000
510857(F)9700 PAVEMENT MRKNG.REMOVAL(TRAF.STRP)134,550LF $0.2000 $0.1700 $0.0700 $0.0700 $0.1000 $0.1700 $0.2000 $0.2000
520857(F)9710 PAVEMENT MARKING REMOVAL(ARROWS)4EA $65.00 $50.00 $50.00 $50.00 $51.50 $50.00 $56.00 $60.00
530857(F)9720 PAVEMENT MARKING REMOVAL(WORDS)2EA $55.00 $75.00 $50.00 $50.00 $51.50 $75.00 $85.00 $90.00
540880(B)6300 CONSTRUCTION SIGNS 0 TO 6.25 SF17,280SD $0.2000 $0.0200 $0.0200 $0.0200 $0.0500 $0.0200 $0.0400 $0.0200
550880(B)6310 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF4,380SD $0.6000 $2.75 $3.50 $3.50 $3.60 $2.75 $2.93 $3.30
560880(B)6320 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF6,450SD $1.00 $0.2500 $0.1500 $0.1500 $0.1500 $0.2500 $0.2800 $0.3000
570880(C)6410 CONSTRUCTION BARRICADES(TYPE III)7,110SD $0.7000 $0.1500 $0.5000 $0.5000 $0.5500 $0.1500 $0.1700 $0.1800
580880(E)6600 WARNING LIGHTS(TYPE A)19,050SD $0.2500 $1.00 $1.00 $1.00 $1.05 $1.00 $1.08 $1.20
590880(F)6700 DRUMS22,350SD $0.2000 $0.6000 $0.2500 $0.2500 $0.2500 $0.6000 $0.6500 $0.7200
600880(G)6805 CHANNELIZER CONES40,350SD $0.4000 $0.6000 $1.60 $1.50 $1.55 $0.6000 $0.6500 $0.7200
610880(I)7000 FLAGGER60SD $110.00 $22.85 $45.00 $100.00 $175.00 $650.00 $295.00 $150.00
620882(A)8210 PORT.CHANGEABLE MESSAGE SIGN508SD $16.65 $8.00 $15.00 $15.00 $15.45 $8.00 $9.10 $9.60
630413(A)4200 RUMBLE STRIP-METHOD HMA-CON25,920LF $0.5000 $0.3700 $0.2600 $0.3500 $0.2000 $0.3700 $0.4100 $0.4500
640413(B)4310 RUMBLE STRIP-METHOD HMA-CYC50,800LF $0.3000 $0.2600 $0.2600 $0.3600 $0.2000 $0.2600 $0.2900 $0.3100
650805(A)3252 (PL)REMOVAL OF EXISTING SIGNS2EA $185.00 $185.00 $75.00 $75.00 $77.25 $185.00 $245.00 $222.00
660805(D)3528 (PL)REMOVE & RESET EXISTING SIGNS18EA $300.00 $250.00 $200.00 $200.00 $206.00 $250.00 $275.00 $300.00
670856(A)8207 (SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(6" WIDE)87,010LF $0.8500 $0.6200 $0.6100 $0.6100 $0.6500 $0.6200 $0.6800 $0.7400
680856(A)8215 (SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(12" WIDE)625LF $2.80 $2.35 $2.00 $2.00 $2.10 $2.35 $2.54 $2.82
690856(A)8219 (SP) TRAFFIC STRIPE(PLURAL-COMPONENT)(24" WIDE)96LF $17.70 $14.00 $10.00 $10.00 $10.30 $14.00 $15.30 $16.80
700856(B)8303 (SP) TRAF.STR.(PLURAL-COMPONENT)(SYM,WRD,ETC)6EA $1,105.00 $400.00 $200.00 $200.00 $206.00 $400.00 $430.00 $480.00
710642(B)3300 CONSTRUCTION STAKING LEVEL II1LSUM $50,000.00 $47,500.00 $15,000.00 $50,000.00 $87,550.00 $85,000.00 $122,000.00 $155,000.00
720220 1100 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $50,000.00 $5,711.34 $500.00 $75,000.00 $15,450.00 $30,000.00 $8,500.00 $4,500.00
730641 2110 MOBILIZATION1LSUM $458,039.59 $158,455.05 $427,000.00 $399,028.00 $673,787.72 $490,000.00 $434,250.00 $46,500.00