Bridge Repair
- Let date
- Thursday, August 7, 2025
- Contract
- 250191 · job page
- J/P numbers
- 38187(04)
- District
- Division 7
- County
- Carter, Jefferson, Stephens
- Highway
- COUNTY ROADS
- Limits
- COUNTY ROADS: OVER TIVIS CREEK
- Classification
- Bridge Repair ·
- Project number
- BRO-210F(117)CB
- Working days
- 80
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $419,200 | ||
| 1 | B & B CONSTRUCTION SERVICE J.T., INC. Low bidder | $208,190 | -50.3% | |
| 2 | K & R BUILDERS, INC. | $268,633 | -35.9% | +29.0% |
| 3 | LOGOS CONSTRUCTION CO., LLC | $371,745 | -11.3% | +78.6% |
| 4 | Built Right Construction, LLC | $394,950 | -5.8% | +89.7% |
| 5 | BRIDGECO CONTRACTORS, INC. | $635,820 | +51.7% | +205.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 B & B CONSTRUCT… | #2 K & R BUILDERS,… | #3 LOGOS CONSTRUCT… | #4 Built Right Con… | #5 BRIDGECO CONTRA… |
|---|---|---|---|---|---|---|---|---|---|---|
| 10 | 201 1100 | (PL)REMOVE DRIFT AND SILT | 1 | LSUM | $10,000.00 | $1,300.00 | $9,750.00 | $9,500.00 | $75,000.00 | $16,000.00 |
| 20 | 501(G)1800 | CLSM BACKFILL | 4 | CY | $1,500.00 | $1,200.00 | $1,435.00 | $325.00 | $500.00 | $7,500.00 |
| 30 | 601(A)1110 | TYPE I PLAIN RIPRAP | 340 | TON | $200.00 | $107.00 | $73.00 | $215.50 | $150.00 | $138.00 |
| 40 | 613(Z)8400 | DEWATERING | 4 | DAY | $1,000.00 | $550.00 | $400.00 | $460.00 | $500.00 | $500.00 |
| 50 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $8,000.00 | $3,500.00 | $7,250.00 | $8,900.00 | $15,000.00 | $12,500.00 |
| 60 | 501(G)1800 | CLSM BACKFILL | 9 | CY | $1,500.00 | $800.00 | $1,400.00 | $325.00 | $500.00 | $4,000.00 |
| 70 | 601(A)1110 | TYPE I PLAIN RIPRAP | 140 | TON | $200.00 | $107.00 | $90.00 | $215.50 | $150.00 | $240.00 |
| 80 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $10,000.00 | $1,900.00 | $7,250.00 | $8,900.00 | $15,000.00 | $16,500.00 |
| 90 | 501(G)1800 | CLSM BACKFILL | 10 | CY | $1,200.00 | $800.00 | $1,325.00 | $325.00 | $500.00 | $3,900.00 |
| 100 | 601(A)1110 | TYPE I PLAIN RIPRAP | 100 | TON | $200.00 | $107.00 | $94.00 | $215.50 | $150.00 | $270.00 |
| 110 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $8,000.00 | $1,900.00 | $8,500.00 | $8,900.00 | $15,000.00 | $16,500.00 |
| 120 | 601(A)1110 | TYPE I PLAIN RIPRAP | 30 | TON | $200.00 | $120.00 | $147.50 | $215.50 | $120.00 | $775.00 |
| 130 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $10,000.00 | $1,900.00 | $10,000.00 | $8,900.00 | $15,000.00 | $16,000.00 |
| 140 | 426(A)1200 | CORED HOLES | 6 | EA | $200.00 | $500.00 | $227.50 | $260.00 | $350.00 | $2,850.00 |
| 150 | 501(G)1800 | CLSM BACKFILL | 8 | CY | $1,500.00 | $1,000.00 | $1,375.00 | $325.00 | $500.00 | $4,000.00 |
| 160 | 601(A)1110 | TYPE I PLAIN RIPRAP | 95 | TON | $200.00 | $107.00 | $102.50 | $215.50 | $120.00 | $290.00 |
| 170 | 613(Z)8400 | DEWATERING | 4 | DAY | $1,000.00 | $550.00 | $430.00 | $460.00 | $500.00 | $500.00 |
| 180 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $8,000.00 | $3,000.00 | $8,750.00 | $8,900.00 | $15,000.00 | $12,000.00 |
| 190 | 501(G)1800 | CLSM BACKFILL | 4 | CY | $1,500.00 | $800.00 | $1,540.00 | $325.00 | $500.00 | $5,000.00 |
| 200 | 601(A)1110 | TYPE I PLAIN RIPRAP | 80 | TON | $200.00 | $107.00 | $109.50 | $215.50 | $120.00 | $340.00 |
| 210 | 201(A)1200 | CLEARING AND GRUBBING | 1 | LSUM | $10,000.00 | $1,900.00 | $6,650.00 | $8,900.00 | $15,000.00 | $16,000.00 |
| 220 | 601(A)1110 | TYPE I PLAIN RIPRAP | 115 | TON | $200.00 | $107.00 | $122.00 | $215.50 | $150.00 | $300.00 |
| 230 | 501(G)1800 | CLSM BACKFILL | 15 | CY | $1,500.00 | $800.00 | $1,125.00 | $325.00 | $500.00 | $2,000.00 |
| 240 | 601(A)1110 | TYPE I PLAIN RIPRAP | 150 | TON | $200.00 | $120.00 | $96.00 | $215.50 | $150.00 | $320.00 |
| 250 | 880(J)7110 | CONSTRUCTION TRAFFIC CONTROL | 1 | LSUM | $24,000.00 | $4,500.00 | $18,000.00 | $23,850.00 | $7,500.00 | $12,200.00 |
| 260 | 641 2100 | MOBILIZATION | 1 | LSUM | $40,000.00 | $23,000.00 | $24,000.00 | $37,230.00 | $40,000.00 | $42,000.00 |