| 10 | 201(A)1200 |
CLEARING AND GRUBBING | 1 | LSUM |
$85,000.00 |
$10,000.00 |
$7,890.81 |
| 20 | 202(A)2200 |
UNCLASSIFIED EXCAVATION | 24,175.37 | CY |
$10.00 |
$18.75 |
$13.36 |
| 30 | 202(D)2500 |
UNCLASSIFIED BORROW | 3,500 | CY |
$13.70 |
$1.00 |
$16.34 |
| 40 | 205(A)6200 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$45,000.00 |
$175,000.00 |
$7,077.11 |
| 50 | 221(B)2300 |
TEMPORARY SILT FENCE | 1,310 | LF |
$3.70 |
$2.99 |
$4.66 |
| 60 | 221(E)2600 |
TEMPORARY SILT DIKE | 392 | LF |
$15.00 |
$18.50 |
$19.12 |
| 70 | 221(G)2800 |
TEMPORARY FIBER LOG | 128 | LF |
$12.00 |
$7.50 |
$11.95 |
| 80 | 227 4120 |
(SP)TURF REINFORCEMENT MAT TYPE 4 | 4,033.33 | SY |
$28.00 |
$59.50 |
$30.70 |
| 90 | 228 5120 |
EROSION CONTROL MAT TYPE 4 | 11,648.89 | SY |
$5.00 |
$2.95 |
$4.84 |
| 100 | 230(A)7200 |
SOLID SLAB SODDING | 107,515.47 | SY |
$2.70 |
$2.75 |
$3.46 |
| 110 | 233(A)0200 |
VEGETATIVE MULCHING | 22.21 | AC |
$750.00 |
$1,110.00 |
$7.17 |
| 120 | 303(A)1200 |
AGGREGATE BASE TYPE A | 170.28 | CY |
$90.00 |
$90.00 |
$96.00 |
| 130 | 307(D)3500 |
LIME | 204.21 | TON |
$250.00 |
$359.27 |
$451.76 |
| 140 | 307(G)3800 |
LIME PRETREATMENT | 18,908.44 | SY |
$2.50 |
$3.21 |
$7.66 |
| 150 | 307(K)4200 |
STABILIZED SUBGRADE | 37,378.84 | SY |
$9.50 |
$7.26 |
$6.87 |
| 160 | 311(B)6300 |
PROCESS EXISTING BASE & SURFACE,METHOD B | 12,800 | LF |
$8.00 |
$5.85 |
$2.58 |
| 170 | 325 0100 |
SEPARATOR FABRIC | 536.74 | SY |
$7.00 |
$5.00 |
$1.44 |
| 180 | 402(E)2600 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 438.63 | TON |
$85.00 |
$45.00 |
$78.90 |
| 190 | 407(B)7300 |
TACK COAT | 3,445.34 | GAL |
$4.50 |
$6.38 |
$8.06 |
| 200 | 408 8100 |
PRIME COAT | 13,275.2 | GAL |
$4.50 |
$2.60 |
$9.60 |
| 210 | 411(B)1340 |
SUPERPAVE, TYPE S3(PG 58-28 OK) | 11,862.42 | TON |
$135.00 |
$135.01 |
$160.00 |
| 220 | 411(C)1430 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 3,686.21 | TON |
$150.00 |
$151.28 |
$178.50 |
| 230 | 501(A)1200 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 67.31 | CY |
$68.00 |
$35.00 |
$15.29 |
| 240 | 501(G)1810 |
CLSM BACKFILL | 20 | CY |
$360.00 |
$200.00 |
$265.52 |
| 250 | 509(A)0200 |
CLASS AA CONCRETE | 183.31 | CY |
$790.00 |
$706.53 |
$700.00 |
| 260 | 509(C)0400 |
CLASS A CONCRETE, SMALL STRUCTURES | 8.43 | CY |
$875.00 |
$500.00 |
$602.67 |
| 270 | 509(D)0500 |
CLASS C CONCRETE | 106.41 | CY |
$570.00 |
$472.50 |
$489.44 |
| 280 | 511(A)2200 |
REINFORCING STEEL | 20,994.06 | LB |
$1.80 |
$1.15 |
$1.39 |
| 290 | 601(A)1100 |
TYPE I PLAIN RIPRAP | 270 | TON |
$110.00 |
$63.50 |
$71.84 |
| 300 | 611(G)0354 |
INLET (SMD-TYPE 2) | 1 | EA |
$5,500.00 |
$3,500.00 |
$4,489.66 |
| 310 | 611(G)0358 |
INLET (SMD-TYPE 2A) | 1 | EA |
$5,800.00 |
$3,800.00 |
$4,556.62 |
| 320 | 611(L)1600 |
JUNCTION BOXES | 191.52 | CF |
$130.00 |
$182.00 |
$136.03 |
| 330 | 613(A)5220 |
30" R.C.PIPE CLASS III | 52 | LF |
$160.00 |
$225.00 |
$202.47 |
| 340 | 613(A)5244 |
66" R.C.PIPE CLASS III | 176 | LF |
$495.00 |
$659.00 |
$407.60 |
| 350 | 613(A)5350 |
22" X 13" R.C.PIPE ARCH CLASS A-III | 68 | LF |
$170.00 |
$156.00 |
$185.15 |
| 360 | 613(A)5358 |
28" X 18" R.C.PIPE ARCH CLASS A-III | 154 | LF |
$140.00 |
$146.50 |
$177.96 |
| 370 | 613(B)5604 |
21" X 15" CORR. GALV. STEEL PIPE ARCH | 310 | LF |
$58.00 |
$50.50 |
$85.70 |
| 380 | 613(EE)5969 |
18" CORRUGATED POLYPROPYLENE PIPE | 17 | LF |
$85.00 |
$112.75 |
$132.56 |
| 390 | 613(EE)5973 |
24" CORRUGATED POLYPROPYLENE PIPE | 58 | LF |
$110.00 |
$122.50 |
$150.95 |
| 400 | 613(EE)5977 |
30" CORRUGATED POLYPROPYLENE PIPE | 16 | LF |
$120.00 |
$162.50 |
$181.14 |
| 410 | 613(H)6200 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 500 | LF |
$25.00 |
$25.00 |
$24.22 |
| 420 | 613(I)6305 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 100 | LF |
$20.00 |
$25.00 |
$24.69 |
| 430 | 613(L)6608 |
21" X 15" PREFAB. CULVERT END SEC., ARCH | 12 | EA |
$600.00 |
$350.00 |
$1,078.83 |
| 440 | 613(L)6612 |
22" X 13" PREFAB. CULVERT END SEC., ARCH | 2 | EA |
$2,000.00 |
$1,350.00 |
$1,805.29 |
| 450 | 613(L)6716 |
24" PREFAB. CULVERT END SEC., ROUND | 2 | EA |
$1,200.00 |
$2,000.00 |
$2,053.79 |
| 460 | 613(L)6724 |
30" PREFAB. CULVERT END SEC., ROUND | 1 | EA |
$2,400.00 |
$2,500.00 |
$2,335.90 |
| 470 | 613(M)6904 |
TYPE B3 CULVERT END TREATMENT | 1 | EA |
$2,200.00 |
$2,500.00 |
$2,892.07 |
| 480 | 613(M)6924 |
TYPE BB3 CULVERT END TREATMENT | 2 | EA |
$4,000.00 |
$3,800.00 |
$2,907.04 |
| 490 | 613(M)6937 |
TYPE FF3 CULVERT END TREATMENT | 2 | EA |
$15,000.00 |
$8,000.00 |
$11,876.71 |
| 500 | 613(Q)7500 |
OUTLET LATERAL HEADWALL | 2 | EA |
$870.00 |
$1,000.00 |
$961.35 |
| 510 | 613(U)7950 |
PIPE UNDERDRAIN COVER MAT'L. | 250 | CY |
$65.00 |
$65.00 |
$58.62 |
| 520 | 613(V)8000 |
TRENCH EXCAVATION | 250 | CY |
$20.00 |
$20.00 |
$22.46 |
| 530 | 619(A)6200 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$24,000.00 |
$110,450.00 |
$6,037.19 |
| 540 | 619(C)6600 |
SAWING PAVEMENT | 22 | LF |
$20.00 |
$10.00 |
$12.93 |
| 550 | 624(C)3405 |
FENCE-STYLE SWF (5 BARBED WIRE) | 3,561.34 | LF |
$9.00 |
$11.80 |
$8.96 |
| 560 | 629(D)7500 |
REMOVE AND RESET MAILBOX | 1 | EA |
$575.00 |
$250.00 |
$298.67 |
| 570 | 202(A)2210 |
UNCLASSIFIED EXCAVATION | 3,544 | CY |
$7.50 |
$26.00 |
$11.18 |
| 580 | 202(D)2510 |
UNCLASSIFIED BORROW | 10 | CY |
$130.00 |
$1.00 |
$8.99 |
| 590 | 501(A)1210 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 310.22 | CY |
$45.00 |
$35.00 |
$17.14 |
| 600 | 509(A)0210 |
CLASS AA CONCRETE | 608.49 | CY |
$750.00 |
$706.53 |
$522.51 |
| 610 | 511(A)2210 |
REINFORCING STEEL | 85,153.8 | LB |
$1.10 |
$1.15 |
$1.21 |
| 620 | 601(A)1110 |
TYPE I PLAIN RIPRAP | 1,620 | TON |
$80.00 |
$70.00 |
$71.85 |
| 630 | 850(A)1200 |
SHEET ALUMINUM SIGNS | 31.08 | SF |
$70.00 |
$135.00 |
$59.73 |
| 640 | 853 5125 |
DELINEATORS(TYPE 2, CODE 3) | 12 | EA |
$85.00 |
$20.00 |
$59.73 |
| 650 | 856(A)8201 |
(SP) TRAFFIC STRIPE(MULTI-POLY.)(4" WIDE) | 45,500 | LF |
$1.00 |
$0.6000 |
$0.7200 |
| 660 | 880(B)6300 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 3,960 | SD |
$1.00 |
$0.1000 |
$0.3000 |
| 670 | 880(B)6310 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 1,080 | SD |
$2.50 |
$4.85 |
$5.97 |
| 680 | 880(B)6320 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 3,420 | SD |
$0.5000 |
$0.5000 |
$0.3000 |
| 690 | 880(C)6410 |
CONSTRUCTION BARRICADES(TYPE III) | 5,400 | SD |
$0.4000 |
$0.3500 |
$0.3000 |
| 700 | 880(E)6600 |
WARNING LIGHTS(TYPE A) | 5,400 | SD |
$0.2000 |
$0.9000 |
$0.3000 |
| 710 | 882(A)8210 |
PORT.CHANGEABLE MESSAGE SIGN | 388 | SD |
$25.00 |
$10.00 |
$11.95 |
| 720 | 642(B)3300 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$120,000.00 |
$46,000.00 |
$19,084.79 |
| 730 | 220 1100 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$25,000.00 |
$12,500.00 |
$2,986.73 |
| 740 | 641 2110 |
MOBILIZATION | 1 | LSUM |
$225,000.00 |
$182,250.00 |
$295,000.00 |