| 10 | 201(A)1200 |
CLEARING AND GRUBBING | 1 | LSUM |
$15,000.00 |
$17,500.00 |
$10,500.00 |
$35,000.00 |
$9,701.49 |
$7,500.00 |
$8,409.00 |
$12,000.00 |
$10,100.00 |
| 20 | 202(A)2200 |
UNCLASSIFIED EXCAVATION | 1,006 | CY |
$15.00 |
$18.75 |
$10.95 |
$19.25 |
$13.33 |
$15.00 |
$22.90 |
$15.00 |
$12.00 |
| 30 | 205(A)6200 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$15,000.00 |
$8,100.00 |
$10,500.00 |
$4,500.00 |
$9,317.09 |
$17,000.00 |
$10,595.00 |
$6,500.00 |
$6,500.00 |
| 40 | 221(B)2300 |
TEMPORARY SILT FENCE | 2,100 | LF |
$3.75 |
$3.59 |
$3.95 |
$4.00 |
$4.56 |
$5.00 |
$4.25 |
$3.59 |
$5.10 |
| 50 | 221(E)2600 |
TEMPORARY SILT DIKE | 168 | LF |
$18.00 |
$14.88 |
$16.37 |
$15.00 |
$18.89 |
$12.00 |
$19.80 |
$14.88 |
$18.90 |
| 60 | 230(A)7200 |
SOLID SLAB SODDING | 6,638 | SY |
$4.90 |
$3.62 |
$4.34 |
$4.30 |
$4.60 |
$5.00 |
$7.45 |
$3.62 |
$5.10 |
| 70 | 233(A)0200 |
VEGETATIVE MULCHING | 1.37 | AC |
$1,975.00 |
$100.00 |
$100.00 |
$250.00 |
$3,991.76 |
$3,500.00 |
$1,016.00 |
$3,144.00 |
$3,750.00 |
| 80 | 307(K)4200 |
STABILIZED SUBGRADE | 3,467 | SY |
$14.00 |
$8.00 |
$12.00 |
$11.00 |
$8.73 |
$10.00 |
$11.80 |
$8.00 |
$18.95 |
| 90 | 402(E)2600 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 43 | TON |
$60.00 |
$84.00 |
$61.00 |
$60.00 |
$66.81 |
$60.00 |
$147.50 |
$65.00 |
$55.00 |
| 100 | 408 8100 |
PRIME COAT | 1,214 | GAL |
$6.85 |
$5.00 |
$5.50 |
$5.00 |
$8.73 |
$8.00 |
$7.20 |
$5.00 |
$6.00 |
| 110 | 411(B)1330 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 705 | TON |
$164.00 |
$118.00 |
$140.50 |
$125.00 |
$118.63 |
$130.00 |
$136.50 |
$118.00 |
$165.00 |
| 120 | 411(C)1430 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 339 | TON |
$192.00 |
$150.00 |
$174.75 |
$160.00 |
$160.07 |
$160.00 |
$162.50 |
$150.00 |
$228.00 |
| 130 | 509(D)0500 |
CLASS C CONCRETE | 10 | CY |
$475.00 |
$550.00 |
$300.00 |
$350.00 |
$515.28 |
$650.00 |
$1,132.00 |
$350.00 |
$500.00 |
| 140 | 613(A)5220 |
30" R.C.PIPE CLASS III | 40 | LF |
$145.00 |
$154.50 |
$120.00 |
$128.00 |
$240.18 |
$225.00 |
$198.50 |
$40.00 |
$96.60 |
| 150 | 613(B)5604 |
21" X 15" CORR. GALV. STEEL PIPE ARCH | 100 | LF |
$67.50 |
$75.50 |
$49.75 |
$81.00 |
$82.44 |
$70.00 |
$43.00 |
$25.00 |
$65.00 |
| 160 | 613(L)6608 |
21" X 15" PREFAB. CULVERT END SEC., ARCH | 4 | EA |
$400.00 |
$817.50 |
$525.00 |
$550.00 |
$619.08 |
$500.00 |
$369.00 |
$400.00 |
$390.00 |
| 170 | 613(L)6724 |
30" PREFAB. CULVERT END SEC., ROUND | 2 | EA |
$1,725.00 |
$1,814.75 |
$1,700.00 |
$1,945.00 |
$2,690.90 |
$2,250.00 |
$2,695.00 |
$500.00 |
$1,655.00 |
| 180 | 619(A)6200 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$5,000.00 |
$7,000.00 |
$6,700.00 |
$2,500.00 |
$4,734.50 |
$5,000.00 |
$7,820.00 |
$5,000.00 |
$12,900.00 |
| 190 | 619(B)6364 |
REMOVAL OF ASPHALT PAVEMENT | 2,934 | SY |
$10.00 |
$11.60 |
$4.83 |
$12.00 |
$10.47 |
$8.00 |
$1.35 |
$3.50 |
$14.60 |
| 200 | 619(C)6600 |
SAWING PAVEMENT | 44 | LF |
$10.00 |
$10.00 |
$11.50 |
$10.00 |
$6.22 |
$5.00 |
$7.55 |
$20.00 |
$10.00 |
| 210 | 624(C)3405 |
FENCE-STYLE SWF (5 BARBED WIRE) | 568 | LF |
$13.25 |
$8.50 |
$11.50 |
$11.00 |
$10.79 |
$10.00 |
$9.10 |
$13.00 |
$14.00 |
| 220 | 202(A)2210 |
UNCLASSIFIED EXCAVATION | 424 | CY |
$18.00 |
$18.00 |
$9.20 |
$19.25 |
$19.28 |
$25.00 |
$27.00 |
$15.00 |
$10.00 |
| 230 | 501(A)1210 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 64 | CY |
$28.00 |
$50.00 |
$17.75 |
$45.00 |
$23.01 |
$45.00 |
$53.60 |
$40.00 |
$50.00 |
| 240 | 509(A)0210 |
CLASS AA CONCRETE | 152.06 | CY |
$925.00 |
$738.00 |
$832.50 |
$785.00 |
$824.15 |
$850.00 |
$1,050.00 |
$1,823.00 |
$810.00 |
| 250 | 511(A)2210 |
REINFORCING STEEL | 24,804.8 | LB |
$1.55 |
$1.50 |
$1.34 |
$1.15 |
$1.50 |
$2.50 |
$1.95 |
$1.25 |
$1.50 |
| 260 | 601(B)1230 |
TYPE I-A PLAIN RIPRAP | 40 | TON |
$90.00 |
$100.00 |
$90.15 |
$95.00 |
$77.85 |
$100.00 |
$114.50 |
$65.00 |
$125.00 |
| 270 | 619(D)6700 |
REMOVAL OF EXISTING BRIDGE STRUCTURE | 1 | LSUM |
$10,000.00 |
$10,000.00 |
$11,500.00 |
$8,500.00 |
$18,000.00 |
$10,000.00 |
$8,329.00 |
$15,000.00 |
$12,800.00 |
| 280 | 853 5125 |
DELINEATORS(TYPE 2, CODE 3) | 4 | EA |
$25.00 |
$31.00 |
$34.10 |
$31.00 |
$63.48 |
$300.00 |
$33.20 |
$31.00 |
$50.00 |
| 290 | 856(A)8200 |
TRAFFIC STRIPE(MULTI-POLY.)(4" WIDE) | 2,400 | LF |
$2.10 |
$1.75 |
$2.10 |
$2.00 |
$3.81 |
$2.55 |
$1.85 |
$1.75 |
$2.20 |
| 300 | 880(B)6310 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 1,800 | SD |
$1.00 |
$0.2500 |
$0.3000 |
$0.2500 |
$0.1300 |
$0.6000 |
$0.2700 |
$0.2500 |
$0.3500 |
| 310 | 880(B)6320 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 180 | SD |
$0.2500 |
$3.00 |
$3.30 |
$3.00 |
$1.27 |
$1.20 |
$3.20 |
$3.00 |
$3.00 |
| 320 | 880(C)6410 |
CONSTRUCTION BARRICADES(TYPE III) | 1,440 | SD |
$1.50 |
$1.00 |
$1.20 |
$1.00 |
$0.1300 |
$1.20 |
$1.05 |
$1.00 |
$1.30 |
| 330 | 880(E)6600 |
WARNING LIGHTS(TYPE A) | 3,600 | SD |
$0.0500 |
$0.5000 |
$0.6000 |
$0.5000 |
$0.1300 |
$0.3000 |
$0.5300 |
$0.5000 |
$0.8500 |
| 340 | 642(B)3300 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$8,000.00 |
$2,500.00 |
$8,000.00 |
$3,500.00 |
$10,157.15 |
$8,500.00 |
$9,978.00 |
$6,800.00 |
$13,650.00 |
| 350 | 220 1100 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$3,500.00 |
$2,000.00 |
$2,150.00 |
$8,500.00 |
$3,174.11 |
$3,500.00 |
$2,407.00 |
$2,500.00 |
$3,000.00 |
| 360 | 641 2100 |
MOBILIZATION | 1 | LSUM |
$60,000.00 |
$53,000.00 |
$57,000.00 |
$40,000.00 |
$55,000.00 |
$52,000.00 |
$50,346.82 |
$69,713.00 |
$52,850.00 |