| 10 | 201(A)1200 |
CLEARING AND GRUBBING | 1 | LSUM |
$140,000.00 |
$98,716.43 |
$375,000.00 |
| 20 | 202(A)2200 |
UNCLASSIFIED EXCAVATION | 91,809 | CY |
$10.00 |
$10.60 |
$18.00 |
| 30 | 205(A)6200 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$215,000.00 |
$317,911.33 |
$75,000.00 |
| 40 | 221(B)2300 |
TEMPORARY SILT FENCE | 18,880 | LF |
$3.00 |
$2.05 |
$2.00 |
| 50 | 221(E)2600 |
TEMPORARY SILT DIKE | 2,912 | LF |
$6.00 |
$8.77 |
$9.00 |
| 60 | 221(G)2800 |
TEMPORARY FIBER LOG | 504 | LF |
$8.00 |
$5.11 |
$6.00 |
| 70 | 230(A)7200 |
SOLID SLAB SODDING | 221,350 | SY |
$3.00 |
$2.33 |
$2.00 |
| 80 | 232(B)9300 |
SEEDING METHOD B | 53 | AC |
$500.00 |
$515.26 |
$550.00 |
| 90 | 233(A)0200 |
VEGETATIVE MULCHING | 53 | AC |
$1,200.00 |
$515.26 |
$550.00 |
| 100 | 241 3100 |
MOWING | 106 | AC |
$250.00 |
$201.36 |
$200.00 |
| 110 | 303(A)1200 |
AGGREGATE BASE TYPE A | 19,560 | CY |
$70.00 |
$61.43 |
$60.00 |
| 120 | 307(K)4200 |
STABILIZED SUBGRADE | 90,631 | SY |
$6.00 |
$6.25 |
$8.00 |
| 130 | 326(A)1200 |
GEOTEXTILE REINFORCEMENT | 105,763 | SY |
$4.50 |
$1.85 |
$2.00 |
| 140 | 402(E)2600 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 16,188 | TON |
$35.00 |
$38.67 |
$20.00 |
| 150 | 407(B)7300 |
TACK COAT | 20,013 | GAL |
$4.00 |
$2.73 |
$3.00 |
| 160 | 408 8100 |
PRIME COAT | 18,903 | GAL |
$4.00 |
$4.73 |
$1.00 |
| 170 | 409(A)9200 |
FABRIC REINFORCEMENT | 21,242 | SY |
$4.00 |
$3.41 |
$2.00 |
| 180 | 411(B)1330 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 34,196 | TON |
$125.00 |
$92.15 |
$87.00 |
| 190 | 411(C)1430 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 15,329 | TON |
$150.00 |
$115.53 |
$100.00 |
| 200 | 412 3100 |
COLD MILLING PAVEMENT | 58,395 | SY |
$3.00 |
$2.97 |
$3.00 |
| 210 | 501(A)1200 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 218 | CY |
$30.00 |
$46.47 |
$30.00 |
| 220 | 509(A)0200 |
CLASS AA CONCRETE | 814 | CY |
$700.00 |
$702.16 |
$1,000.00 |
| 230 | 509(D)0500 |
CLASS C CONCRETE | 465 | CY |
$450.00 |
$428.53 |
$500.00 |
| 240 | 510(A)1200 |
RETAINING WALL | 258.89 | SY |
$600.00 |
$674.80 |
$800.00 |
| 250 | 511(A)2200 |
REINFORCING STEEL | 96,360 | LB |
$1.50 |
$1.55 |
$2.00 |
| 260 | 601(B)1220 |
TYPE I-A PLAIN RIPRAP | 6,675 | TON |
$50.00 |
$49.47 |
$35.00 |
| 270 | 601(C)1300 |
TYPE I-A FILTER BLANKET | 2,856 | TON |
$45.00 |
$37.63 |
$25.00 |
| 280 | 609(A)4230 |
CONC.CURB(6" BARRIER-INTEGRAL) | 435 | LF |
$15.00 |
$30.83 |
$5.00 |
| 290 | 609(B)4360 |
2'-8" COMB.CRB.& GUT.(6" BARRIER) | 3,548 | LF |
$32.00 |
$27.63 |
$32.00 |
| 300 | 610(B)5300 |
6" CONCRETE DRIVEWAY (H.E.S.) | 1,180 | SY |
$70.00 |
$75.32 |
$97.00 |
| 310 | 611(G)0354 |
INLET (SMD-TYPE 2) | 7 | EA |
$2,800.00 |
$4,723.83 |
$4,000.00 |
| 320 | 611(G)0362 |
INLET (SMD-TYPE 2B) | 1 | EA |
$3,100.00 |
$6,287.49 |
$6,081.60 |
| 330 | 611(G)7758 |
INLET CI DES. 2 (B) | 4 | EA |
$4,000.00 |
$8,071.99 |
$7,000.00 |
| 340 | 611(G)7786 |
INLET CI DES. 3 (STD) | 2 | EA |
$5,000.00 |
$8,242.04 |
$7,200.00 |
| 350 | 611(G)7930 |
INLET GPI TYPE 1 (DES. 1) | 1 | EA |
$3,000.00 |
$5,652.95 |
$5,500.00 |
| 360 | 611(H)0414 |
ADD'L DEPTH IN INLET CI DES. 2 | 3.96 | VF |
$500.00 |
$270.23 |
$500.00 |
| 370 | 611(H)0422 |
ADD'L DEPTH IN INLET CI DES. 3 | 9.94 | VF |
$500.00 |
$458.73 |
$700.00 |
| 380 | 611(H)0470 |
ADD'L DEPTH IN INLET GPI TYPE 1 | 3.6 | VF |
$500.00 |
$275.51 |
$400.00 |
| 390 | 613(A)5208 |
18" R.C.PIPE CLASS III | 799 | LF |
$100.00 |
$123.05 |
$100.00 |
| 400 | 613(A)5216 |
24" R.C.PIPE CLASS III | 292 | LF |
$120.00 |
$162.98 |
$130.00 |
| 410 | 613(A)5220 |
30" R.C.PIPE CLASS III | 24 | LF |
$160.00 |
$277.02 |
$145.00 |
| 420 | 613(A)5224 |
36" R.C.PIPE CLASS III | 192 | LF |
$200.00 |
$221.40 |
$195.00 |
| 430 | 613(A)5228 |
42" R.C.PIPE CLASS III | 48 | LF |
$250.00 |
$265.42 |
$235.00 |
| 440 | 613(A)5358 |
28" X 18" R.C.PIPE ARCH CLASS A-III | 462 | LF |
$150.00 |
$165.50 |
$160.00 |
| 450 | 613(B)5508 |
18" CORR. GALV. STEEL PIPE | 367 | LF |
$50.00 |
$84.46 |
$75.00 |
| 460 | 613(B)5524 |
30" CORR. GALV. STEEL PIPE | 51 | LF |
$80.00 |
$144.86 |
$120.00 |
| 470 | 613(H)6200 |
6" PERFORATED PIPE UNDERDRAIN ROUND | 1,000 | LF |
$30.00 |
$21.33 |
$5.00 |
| 480 | 613(I)6305 |
6" NON-PERF.PIPE UNDERDRAIN RND. | 500 | LF |
$30.00 |
$46.49 |
$5.00 |
| 490 | 613(J)6400 |
EDGE DRAIN CONDUIT-PERFORATED | 2,840 | LF |
$15.00 |
$21.33 |
$7.00 |
| 500 | 613(K)6500 |
EDGE DRAIN OUTLET LATERAL-NONPERFORATED | 90 | LF |
$30.00 |
$46.49 |
$7.00 |
| 510 | 613(L)6620 |
28" X 18" PREFAB. CULVERT END SEC., ARCH | 26 | EA |
$700.00 |
$1,571.61 |
$2,500.00 |
| 520 | 613(L)6708 |
18" PREFAB. CULVERT END SEC., ROUND | 6 | EA |
$600.00 |
$1,214.61 |
$1,500.00 |
| 530 | 613(L)6716 |
24" PREFAB. CULVERT END SEC., ROUND | 12 | EA |
$650.00 |
$1,195.93 |
$1,700.00 |
| 540 | 613(L)6724 |
30" PREFAB. CULVERT END SEC., ROUND | 2 | EA |
$1,500.00 |
$1,451.66 |
$2,000.00 |
| 550 | 613(L)6728 |
36" PREFAB. CULVERT END SEC., ROUND | 9 | EA |
$2,000.00 |
$2,080.91 |
$2,500.00 |
| 560 | 613(L)6732 |
42" PREFAB. CULVERT END SEC., ROUND | 2 | EA |
$2,500.00 |
$2,773.81 |
$3,500.00 |
| 570 | 613(Q)7500 |
OUTLET LATERAL HEADWALL | 7 | EA |
$900.00 |
$1,464.57 |
$1,000.00 |
| 580 | 619(A)6200 |
REMOVAL OF STRUCTURES & OBSTRUCTIONS | 1 | LSUM |
$150,000.00 |
$60,467.26 |
$97,000.00 |
| 590 | 619(B)6300 |
REMOVAL OF HEADWALL | 30 | EA |
$1,200.00 |
$2,177.90 |
$500.00 |
| 600 | 619(B)6356 |
REMOVAL OF CURB AND GUTTER | 160 | LF |
$15.00 |
$25.76 |
$5.00 |
| 610 | 619(B)6364 |
REMOVAL OF ASPHALT PAVEMENT | 25,737 | SY |
$6.00 |
$5.99 |
$5.00 |
| 620 | 619(B)6376 |
REMOVAL OF CONC.PAV.W/ASPH.OVERLAY | 1,630 | SY |
$8.00 |
$2.84 |
$10.00 |
| 630 | 619(B)6380 |
REMOVAL OF CONCRETE DRIVEWAY | 422 | SY |
$8.00 |
$10.28 |
$10.00 |
| 640 | 619(C)6600 |
SAWING PAVEMENT | 55,238 | LF |
$4.00 |
$2.73 |
$5.00 |
| 650 | 624(A)3200 |
FENCE-STYLE WWF | 5,146 | LF |
$9.00 |
$11.67 |
$11.00 |
| 660 | 624(C)3400 |
FENCE-STYLE SWF (4 BARBED WIRE) | 9,549 | LF |
$5.00 |
$9.29 |
$8.00 |
| 670 | 624(C)3405 |
FENCE-STYLE SWF (5 BARBED WIRE) | 7,633 | LF |
$6.00 |
$9.60 |
$9.00 |
| 680 | 624(C)3410 |
FENCE-STYLE SWF (6 BARBED WIRE) | 17,375 | LF |
$8.00 |
$9.91 |
$10.00 |
| 690 | 624(E)3625 |
FENCE-STYLE CLF (6'HIGH, CLASS B) | 245 | LF |
$30.00 |
$173.48 |
$65.00 |
| 700 | 629(A)7200 |
MAILBOX INSTALLATION-SINGLE | 5 | EA |
$110.00 |
$258.15 |
$275.00 |
| 710 | 629(B)7300 |
MAILBOX INSTALLATION-MULTIPLE | 3 | EA |
$210.00 |
$516.30 |
$550.00 |
| 720 | 629(C)7400 |
REMOVAL OF MAILBOX INSTALLATION | 12 | EA |
$20.00 |
$51.63 |
$55.00 |
| 730 | 629(E)7600 |
MAILBOX | 12 | EA |
$35.00 |
$51.63 |
$55.00 |
| 740 | 303(A)1200 |
AGGREGATE BASE TYPE A | 29 | CY |
$100.00 |
$48.53 |
$65.00 |
| 750 | 402(E)2600 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 13 | TON |
$70.00 |
$32.34 |
$30.00 |
| 760 | 411(B)1330 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 7 | TON |
$150.00 |
$363.01 |
$300.00 |
| 770 | 411(C)1430 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 4 | TON |
$180.00 |
$415.60 |
$600.00 |
| 780 | 501(G)1810 |
CLSM BACKFILL | 66 | CY |
$200.00 |
$196.19 |
$120.00 |
| 790 | 611(A)7210 |
MANHOLE (4' DIA.) | 12 | EA |
$2,500.00 |
$4,595.05 |
$9,500.00 |
| 800 | 611(A)7215 |
MANHOLE (5' DIA.) | 1 | EA |
$5,000.00 |
$14,466.65 |
$12,000.00 |
| 810 | 611(B)7300 |
ADD'L.DEPTH IN MANHOLE (4' DIA.) | 22 | VF |
$300.00 |
$712.49 |
$500.00 |
| 820 | 611(B)7305 |
ADD'L.DEPTH IN MANHOLE (5' DIA.) | 20 | VF |
$400.00 |
$1,022.27 |
$600.00 |
| 830 | 612(B)3310 |
CONNECT TO EXISTING MANHOLE | 1 | EA |
$2,500.00 |
$3,097.79 |
$7,000.00 |
| 840 | 613(T)7800 |
STANDARD BEDDING MATERIAL, CLASS C | 119 | CY |
$65.00 |
$92.93 |
$75.00 |
| 850 | 613(V)8000 |
TRENCH EXCAVATION | 826 | CY |
$20.00 |
$20.65 |
$35.00 |
| 860 | 615(A)1220 |
8" POLYVINYL CHLORIDE (PVC) PIPE | 520 | LF |
$150.00 |
$41.30 |
$105.00 |
| 870 | 615(A)1228 |
12" POLYVINYL CHLORIDE (PVC) PIPE | 170 | LF |
$170.00 |
$61.96 |
$160.00 |
| 880 | 615(A)1240 |
15" POLYVINYL CHLORIDE (PVC) PIPE | 270 | LF |
$270.00 |
$123.91 |
$170.00 |
| 890 | 616(I)3330 |
20" STEEL CASING | 20 | LF |
$200.00 |
$361.41 |
$275.00 |
| 900 | 616(I)3333 |
24" STEEL CASING | 40 | LF |
$220.00 |
$351.08 |
$300.00 |
| 910 | 616(J)3435 |
BORE AND JACK 20" CASING | 177 | LF |
$400.00 |
$621.62 |
$500.00 |
| 920 | 616(J)3440 |
BORE AND JACK 24" CASING | 122 | LF |
$500.00 |
$747.60 |
$700.00 |
| 930 | 619(B)6372 |
REMOVAL OF MANHOLES | 8 | EA |
$800.00 |
$1,579.87 |
$800.00 |
| 940 | 303(A)1200 |
AGGREGATE BASE TYPE A | 140 | CY |
$80.00 |
$39.24 |
$65.00 |
| 950 | 402(E)2600 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 49 | TON |
$50.00 |
$32.37 |
$30.00 |
| 960 | 613(T)7800 |
STANDARD BEDDING MATERIAL, CLASS C | 32 | CY |
$65.00 |
$28.91 |
$75.00 |
| 970 | 613(V)8000 |
TRENCH EXCAVATION | 248 | CY |
$20.00 |
$24.78 |
$35.00 |
| 980 | 616(D)2642 |
4" GATE VALVE | 6 | EA |
$2,100.00 |
$1,817.37 |
$1,500.00 |
| 990 | 616(D)2646 |
6" GATE VALVE | 7 | EA |
$2,600.00 |
$1,920.63 |
$2,300.00 |
| 1,000 | 616(D)2800 |
STANDARD VALVE BOX | 13 | EA |
$350.00 |
$413.04 |
$500.00 |
| 1,010 | 616(D)2804 |
VALVE BOX EXTENSION | 6 | EA |
$300.00 |
$216.85 |
$250.00 |
| 1,020 | 616(G)3100 |
FIRE HYDRANTS | 3 | EA |
$6,000.00 |
$6,071.66 |
$7,000.00 |
| 1,030 | 616(J)3415 |
BORE AND JACK 12" CASING | 208 | LF |
$150.00 |
$413.04 |
$350.00 |
| 1,040 | 616(J)3425 |
BORE AND JACK 16" CASING | 312 | LF |
$200.00 |
$567.93 |
$400.00 |
| 1,050 | 616(N)3800 |
SERVICE CONNECTION (SHORT) | 1 | EA |
$2,000.00 |
$1,548.89 |
$2,500.00 |
| 1,060 | 616(O)3905 |
FITTINGS | 10 | EA |
$1,500.00 |
$1,270.09 |
$300.00 |
| 1,070 | 616(O)3960 |
4" FIITTING | 13 | EA |
$500.00 |
$722.82 |
$300.00 |
| 1,080 | 616(O)3975 |
6" 11 1/4 DEGREE FITTING | 2 | EA |
$500.00 |
$867.38 |
$600.00 |
| 1,090 | 616(O)3985 |
6" 45 DEGREE FITTING | 15 | EA |
$500.00 |
$867.38 |
$600.00 |
| 1,100 | 616(O)3990 |
6" 90 DEGREE FITTING | 2 | EA |
$600.00 |
$908.68 |
$600.00 |
| 1,110 | 616(P)4128 |
4" HDPE PIPE | 361 | LF |
$65.00 |
$20.65 |
$67.00 |
| 1,120 | 616(P)4136 |
6" HDPE PIPE | 515 | LF |
$75.00 |
$35.11 |
$107.00 |
| 1,130 | 616(R)4324 |
6" X 4" REDUCER | 2 | EA |
$500.00 |
$826.08 |
$600.00 |
| 1,140 | 616(T)4535 |
6" X 6" X 6" TEE | 3 | EA |
$900.00 |
$1,321.72 |
$800.00 |
| 1,150 | 619(B)6448 |
REMOVAL OF FIRE HYDRANT | 3 | EA |
$500.00 |
$815.75 |
$1,200.00 |
| 1,160 | 202(A)2210 |
UNCLASSIFIED EXCAVATION | 4,380 | CY |
$15.00 |
$10.33 |
$30.00 |
| 1,170 | 501(A)1210 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 385 | CY |
$25.00 |
$36.14 |
$50.00 |
| 1,180 | 508 9100 |
REMOVAL OF CULVERT END | 2 | EA |
$20,000.00 |
$10,325.95 |
$25,000.00 |
| 1,190 | 509(A)0210 |
CLASS AA CONCRETE | 922.8 | CY |
$500.00 |
$542.11 |
$1,000.00 |
| 1,200 | 511(A)2210 |
REINFORCING STEEL | 140,320 | LB |
$1.50 |
$1.55 |
$2.00 |
| 1,210 | 520(A)1200 |
PREPARATION OF CRACKS, ABOVE WATER | 50 | LF |
$60.00 |
$51.63 |
$50.00 |
| 1,220 | 520(C)1400 |
EPOXY RESIN, ABOVE WATER | 5 | GAL |
$100.00 |
$206.52 |
$165.00 |
| 1,230 | 521(A)2200 |
PNEUMATICALLY PLACED MORTAR | 5 | SY |
$1,500.00 |
$1,290.74 |
$1,500.00 |
| 1,240 | 202(A)2210 |
UNCLASSIFIED EXCAVATION | 3,080 | CY |
$15.00 |
$10.33 |
$30.00 |
| 1,250 | 501(A)1210 |
STRUCTURAL EXCAVATION UNCLASSIFIED | 390 | CY |
$25.00 |
$36.14 |
$50.00 |
| 1,260 | 508 9100 |
REMOVAL OF CULVERT END | 2 | EA |
$20,000.00 |
$10,325.95 |
$25,000.00 |
| 1,270 | 509(A)0210 |
CLASS AA CONCRETE | 914.2 | CY |
$500.00 |
$542.11 |
$1,000.00 |
| 1,280 | 511(A)2210 |
REINFORCING STEEL | 140,210 | LB |
$1.50 |
$1.55 |
$2.00 |
| 1,290 | 520(A)1200 |
PREPARATION OF CRACKS, ABOVE WATER | 50 | LF |
$60.00 |
$51.63 |
$50.00 |
| 1,300 | 520(C)1400 |
EPOXY RESIN, ABOVE WATER | 5 | GAL |
$100.00 |
$206.52 |
$165.00 |
| 1,310 | 521(A)2200 |
PNEUMATICALLY PLACED MORTAR | 5 | SY |
$1,500.00 |
$1,290.74 |
$1,500.00 |
| 1,320 | 857(A)9200 |
CONSTRUCTION TRAFFIC STR.(PAINT)(4" WIDE) | 78,000 | LF |
$0.1500 |
$0.1500 |
$0.2000 |
| 1,330 | 857(C)9400 |
REMOVABLE PAVEMENT MARKING TAPE(4" WIDE) | 3,000 | LF |
$1.50 |
$2.07 |
$2.00 |
| 1,340 | 857(E)9600 |
(PL)CONSTRUCTION ZONE PAVEMENT MARKERS | 2,000 | EA |
$1.00 |
$2.07 |
$2.00 |
| 1,350 | 857(F)9700 |
PAVEMENT MRKNG.REMOVAL(TRAF.STRP) | 1,000 | LF |
$1.00 |
$2.07 |
$2.00 |
| 1,360 | 871(B)2300 |
CONST.ZONE IMPACT ATTEN. | 180 | SD |
$12.00 |
$20.65 |
$25.00 |
| 1,370 | 877(B)4300 |
DELIVER PORTABLE LONGITUDINAL BARRIER | 2,000 | LF |
$25.00 |
$13.26 |
$32.00 |
| 1,380 | 877(C)4400 |
RELOCATION OF PORT. LONGITUDINAL BARRIER | 2,000 | LF |
$12.00 |
$3.91 |
$10.00 |
| 1,390 | 880(B)6300 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 30,300 | SD |
$0.5000 |
$0.2600 |
$0.3000 |
| 1,400 | 880(B)6310 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 20,500 | SD |
$0.5000 |
$0.3600 |
$0.4000 |
| 1,410 | 880(B)6320 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 8,000 | SD |
$0.5000 |
$4.13 |
$4.50 |
| 1,420 | 880(C)6410 |
CONSTRUCTION BARRICADES(TYPE III) | 25,000 | SD |
$0.2500 |
$0.2600 |
$0.3000 |
| 1,430 | 880(C)6420 |
WING BARRICADES | 1,440 | SD |
$5.50 |
$1.03 |
$2.00 |
| 1,440 | 880(D)6500 |
VERTICAL PANELS | 5,300 | SD |
$0.3000 |
$0.2600 |
$0.5000 |
| 1,450 | 880(E)6600 |
WARNING LIGHTS(TYPE A) | 66,270 | SD |
$0.1000 |
$0.1000 |
$0.1500 |
| 1,460 | 880(F)6700 |
DRUMS | 108,130 | SD |
$0.2000 |
$0.1500 |
$0.2000 |
| 1,470 | 880(G)6800 |
TUBE CHANNELIZERS | 1,650 | SD |
$0.4000 |
$2.07 |
$3.00 |
| 1,480 | 880(G)6805 |
CHANNELIZER CONES | 1,000 | SD |
$1.10 |
$2.07 |
$3.00 |
| 1,490 | 880(I)7000 |
FLAGGER | 420 | SD |
$200.00 |
$304.91 |
$150.00 |
| 1,500 | 880(W)7700 |
PILOT CAR | 1 | LSUM |
$20,000.00 |
$26,298.98 |
$25,000.00 |
| 1,510 | 882(A)8210 |
PORT.CHANGEABLE MESSAGE SIGN | 720 | SD |
$20.00 |
$20.65 |
$30.00 |
| 1,520 | 413(B)4310 |
RUMBLE STRIP-METHOD HMA-CYC | 49,334 | LF |
$0.3000 |
$0.4500 |
$0.4500 |
| 1,530 | 805(A)3252 |
(PL)REMOVAL OF EXISTING SIGNS | 38 | EA |
$100.00 |
$103.26 |
$120.00 |
| 1,540 | 805(D)3536 |
(PL)REMOVE & RESET GROUND MOUNTED SIGN | 9 | EA |
$500.00 |
$258.15 |
$300.00 |
| 1,550 | 850(A)1200 |
SHEET ALUMINUM SIGNS | 288.12 | SF |
$30.00 |
$27.88 |
$30.00 |
| 1,560 | 851(C)2415 |
2" SQUARE TUBE POST | 140 | LF |
$12.00 |
$14.46 |
$15.00 |
| 1,570 | 851(C)2420 |
2 1/4" SQUARE TUBE POST | 414 | LF |
$15.00 |
$15.49 |
$16.00 |
| 1,580 | 856(A)8204 |
TRAFFIC STRIPE(MULTI-POLY.)(6" WIDE) | 89,230 | LF |
$0.6500 |
$0.7700 |
$1.00 |
| 1,590 | 856(A)8216 |
TRAFFIC STRIPE(MULTI-POLY.)(24" WIDE) | 235 | LF |
$10.00 |
$25.81 |
$30.00 |
| 1,600 | 856(B)8304 |
TRAFFIC STRIPE(MULTI-POLY.)(ARROWS) | 2 | EA |
$260.00 |
$387.23 |
$400.00 |
| 1,610 | 857(F)9700 |
PAVEMENT MRKNG.REMOVAL(TRAF.STRP) | 500 | LF |
$1.00 |
$2.07 |
$3.00 |
| 1,620 | 642(B)3300 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$99,000.00 |
$134,784.04 |
$190,000.00 |
| 1,630 | 220 1100 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$10,000.00 |
$31,470.96 |
$25,000.00 |
| 1,640 | 640(A)1210 |
FIELD OFFICE | 1 | EA |
$14,000.00 |
$30,255.45 |
$15,000.00 |
| 1,650 | 641 2110 |
MOBILIZATION | 1 | LSUM |
$690,000.00 |
$600,543.61 |
$808,000.00 |