RESURFACE (ASPHALT ) COUNTY ROAD (EW-155): FROM 10.0 MILES EAST OF THE SH-30 JUNCTION, EXTEND EAST NEAR GOULD . PROJECT LENGTH = 3.021 MILES
- Let date
- Thursday, February 17, 2022
- Contract
- 220059
- J/P numbers
- 33517(04)
- District
- Division 5
- County
- Harmon
- Highway
- Limits
- RESURFACE (ASPHALT ) COUNTY ROAD (EW-155): FROM 10.0 MILES EAST OF THE SH-30 JUNCTION, EXTEND EAST NEAR GOULD . PROJECT LENGTH = 3.021 MILES
- Project number
- STP-229C(018)CI
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $962,509 | ||
| 1 | Caswell Contracting, Inc. Low bidder | $908,314 | -5.6% | |
| 2 | T & G CONSTRUCTION, INC. | $1,032,187 | +7.2% | +13.6% |
| 3 | OVERLAND CORPORATION | $1,134,060 | +17.8% | +24.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Caswell Contrac… | #2 T & G CONSTRUCT… | #3 OVERLAND CORPOR… |
|---|---|---|---|---|---|---|---|---|
| 10 | 402(E)2600 | TRAFFIC BOUND SURFACE COURSE TYPE E | 284 | TON | $45.00 | $52.95 | $51.24 | $65.00 |
| 20 | 407(B)7300 | TACK COAT | 5,818 | GAL | $3.00 | $2.53 | $3.72 | $2.25 |
| 30 | 411(C)1430 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 8,870 | TON | $95.00 | $97.03 | $105.81 | $110.85 |
| 40 | 412 3100 | COLD MILLING PAVEMENT | 890 | SY | $12.50 | $4.11 | $16.59 | $13.00 |
| 50 | 880(J)7100 | (SP) CONSTRUCTION TRAFFIC CONTROL | 30 | SD | $100.00 | $107.68 | $34.50 | $90.00 |
| 60 | 642(A)3200 | CONSTRUCTION STAKING LEVEL I | 1 | LSUM | $7,500.00 | $1,835.43 | $5,175.00 | $25,000.00 |
| 70 | 641 2110 | MOBILIZATION | 1 | LSUM | $68,000.00 | $9,177.16 | $36,482.28 | $80,000.00 |