RESURFACE (ASPHALT ) US-64: FROM 3.0 MILES WEST OF THE SH -14 JUNCTION, EXTEND EAST NEAR ALVA . PROJECT LENGTH = 5.840 MILES
- Let date
- Thursday, January 20, 2022
- Contract
- 220043
- J/P numbers
- 31766(04)
- District
- Division 6
- County
- Woods
- Highway
- Limits
- RESURFACE (ASPHALT ) US-64: FROM 3.0 MILES WEST OF THE SH -14 JUNCTION, EXTEND EAST NEAR ALVA . PROJECT LENGTH = 5.840 MILES
- Project number
- STP-CRRS(011)PM
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,456,080 | ||
| 1 | THE CUMMINS CONSTRUCTION CO., INC. Low bidder | $1,701,278 | +16.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 THE CUMMINS CON… |
|---|---|---|---|---|---|---|
| 10 | 202(D)2500 | UNCLASSIFIED BORROW | 900 | CY | $5.00 | $15.00 |
| 20 | 202(H)2900 | EARTHWORK | 1 | LSUM | $8,000.00 | $30,000.00 |
| 30 | 407(C)7400 | (SP) POLYMER MOD. CATIONIC RAPID SET - 1S | 25,500 | GAL | $2.50 | $2.95 |
| 40 | 411(C)1430 | SUPERPAVE, TYPE S4(PG 64-22 OK) | 11,400 | TON | $105.00 | $116.00 |
| 50 | 411(I)2000 | SUPERPAVE, TYPE S4(PATCH)(PG64-22OK) | 250 | TON | $125.00 | $232.00 |
| 60 | 412 3100 | COLD MILLING PAVEMENT | 1,700 | SY | $1.50 | $9.85 |
| 70 | 413(A)4210 | RUMBLE STRIP-CENTERLINE HMA-CON | 30,900 | LF | $0.2000 | $0.2500 |
| 80 | 413(B)4310 | RUMBLE STRIP-METHOD HMA-CYC | 62,000 | LF | $0.1500 | $0.2500 |
| 90 | 856(A)8200 | TRAFFIC STRIPE(MULTI-POLY.)(4" WIDE) | 99,500 | LF | $0.4000 | $0.4500 |
| 100 | 880(J)7100 | (SP) CONSTRUCTION TRAFFIC CONTROL | 35 | SD | $250.00 | $154.50 |
| 110 | 641 2110 | MOBILIZATION | 1 | LSUM | $85,000.00 | $112,000.00 |