| 10 | 201(A)1200 |
CLEARING AND GRUBBING | 1 | LSUM |
$25,000.00 |
$17,338.68 |
$15,000.00 |
| 20 | 202(A)2200 |
UNCLASSIFIED EXCAVATION | 40,571 | CY |
$8.00 |
$6.94 |
$6.00 |
| 30 | 205(A)6200 |
TYPE A-SALVAGED TOPSOIL | 1 | LSUM |
$75,000.00 |
$115,591.18 |
$100,000.00 |
| 40 | 221(B)2300 |
TEMPORARY SILT FENCE | 7,439 | LF |
$3.00 |
$1.71 |
$1.55 |
| 50 | 221(E)2600 |
TEMPORARY SILT DIKE | 2,840 | LF |
$8.00 |
$9.22 |
$8.35 |
| 60 | 230(A)7200 |
SOLID SLAB SODDING | 140,356 | SY |
$2.75 |
$1.71 |
$1.55 |
| 70 | 233(A)0200 |
VEGETATIVE MULCHING | 29 | AC |
$750.00 |
$577.96 |
$525.00 |
| 80 | 303(A)1210 |
AGGREGATE BASE TYPE A, PLANT MIXED | 18,290 | CY |
$50.00 |
$58.18 |
$65.00 |
| 90 | 326(B)1300 |
GEOGRID REINFORCEMENT | 58,889 | SY |
$1.85 |
$0.7700 |
$0.8500 |
| 100 | 402(E)2600 |
TRAFFIC BOUND SURFACE COURSE TYPE E | 5,226 | TON |
$28.00 |
$28.13 |
$32.00 |
| 110 | 407(B)7300 |
TACK COAT | 4,082 | GAL |
$3.00 |
$2.31 |
$2.50 |
| 120 | 408 8100 |
PRIME COAT | 14,721 | GAL |
$3.50 |
$3.47 |
$3.85 |
| 130 | 411(B)1330 |
SUPERPAVE, TYPE S3(PG 64-22 OK) | 9,313 | TON |
$90.00 |
$73.53 |
$82.00 |
| 140 | 411(C)1430 |
SUPERPAVE, TYPE S4(PG 64-22 OK) | 6,132 | TON |
$90.00 |
$72.41 |
$81.00 |
| 150 | 413(B)4300 |
RUMBLE STRIP-METHOD HMA-CYC GROUP | 3 | EAGP |
$1,250.00 |
$1,733.87 |
$1,500.00 |
| 160 | 509(D)0500 |
CLASS C CONCRETE | 20 | CY |
$400.00 |
$462.36 |
$350.00 |
| 170 | 601(B)1200 |
TYPE I PLAIN RIPRAP WITH FILTER BLANKET | 220 | TON |
$50.00 |
$56.64 |
$49.00 |
| 180 | 613(A)5358 |
28" X 18" R.C.PIPE ARCH CLASS A-III | 418 | LF |
$115.00 |
$127.15 |
$110.00 |
| 190 | 613(A)5370 |
43" X 26" R.C.PIPE ARCH CLASS A-III | 560 | LF |
$158.00 |
$208.06 |
$180.00 |
| 200 | 613(B)5612 |
28" X 20" CORR. GALV. STEEL PIPE ARCH | 471 | LF |
$39.00 |
$80.91 |
$70.00 |
| 210 | 613(EE)5960 |
(SP) 12" CORRUGATED POLYPROPYLENE PIPE | 75 | LF |
$25.00 |
$34.68 |
$30.00 |
| 220 | 613(M)6964 |
TYPE B4 CULVERT END TREATMENT | 24 | EA |
$1,400.00 |
$1,387.09 |
$1,200.00 |
| 230 | 613(M)6988 |
TYPE CC4 CULVERT END TREATMENT | 8 | EA |
$2,800.00 |
$2,889.78 |
$2,500.00 |
| 240 | 619(B)6352 |
REMOVAL OF FENCE | 6,860 | LF |
$1.60 |
$1.44 |
$1.00 |
| 250 | 619(B)6392 |
REMOVAL OF EXISTING STRUCTURES | 5 | EA |
$7,500.00 |
$5,779.56 |
$5,000.00 |
| 260 | 624(C)3410 |
FENCE-STYLE SWF (6 BARBED WIRE) | 23,839 | LF |
$6.75 |
$8.38 |
$7.60 |
| 270 | 629(D)7500 |
REMOVE AND RESET MAILBOX | 1 | EA |
$200.00 |
$231.18 |
$150.00 |
| 280 | 850(A)1200 |
SHEET ALUMINUM SIGNS | 58 | SF |
$26.00 |
$58.95 |
$52.00 |
| 290 | 851(C)2415 |
2" SQUARE TUBE POST | 99 | LF |
$10.50 |
$11.56 |
$11.00 |
| 300 | 856(A)8200 |
TRAFFIC STRIPE(MULTI-POLY.)(4" WIDE) | 9,102 | LF |
$0.9000 |
$1.01 |
$1.05 |
| 310 | 856(A)8212 |
TRAFFIC STRIPE(MULTI-POLY)(12" WIDE) | 11 | LF |
$5.00 |
$46.24 |
$42.00 |
| 320 | 880(B)6300 |
CONSTRUCTION SIGNS 0 TO 6.25 SF | 300 | SD |
$0.8000 |
$0.1700 |
$0.1800 |
| 330 | 880(B)6310 |
CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF | 4,200 | SD |
$0.5000 |
$0.1700 |
$0.1800 |
| 340 | 880(B)6320 |
CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF | 4,500 | SD |
$1.15 |
$1.44 |
$1.28 |
| 350 | 880(C)6410 |
CONSTRUCTION BARRICADES(TYPE III) | 3,900 | SD |
$0.5500 |
$0.3500 |
$0.3200 |
| 360 | 880(E)6600 |
WARNING LIGHTS(TYPE A) | 9,600 | SD |
$0.2500 |
$0.5800 |
$0.5500 |
| 370 | 642(B)3300 |
CONSTRUCTION STAKING LEVEL II | 1 | LSUM |
$20,000.00 |
$21,962.32 |
$49,000.00 |
| 380 | 220 1100 |
SWPPP DOCUMENTATION AND MANAGEMENT | 1 | LSUM |
$10,000.00 |
$2,889.78 |
$4,000.00 |
| 390 | 641 2110 |
MOBILIZATION | 1 | LSUM |
$225,000.00 |
$97,503.56 |
$200,000.00 |