Bid tab 210206

Let Jul 15, 2021 · Division 3 · Garvin Sign up free

‹ Jul 2021 results

BRIDGE AND APPROACHES US-77: OVER WASHITA RIVER OVERFLOW AND UNNAMED CREEK , 1.4 MILES AND 1.6 MILES SOUTHEAST OF THE SH -29 JUNCTION NEAR WYNNEWOOD. PROJECT LENGTH = 0.995 MILE

Let date
Thursday, July 15, 2021
Contract
210206
J/P numbers
29544(04)
District
Division 3
County
Garvin
Highway
Limits
BRIDGE AND APPROACHES US-77: OVER WASHITA RIVER OVERFLOW AND UNNAMED CREEK , 1.4 MILES AND 1.6 MILES SOUTHEAST OF THE SH -29 JUNCTION NEAR WYNNEWOOD. PROJECT LENGTH = 0.995 MILE
Project number
STP-225C(085)PM

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$5,163,014
1 SEWELL BROS., INC. Low bidder $5,070,787 -1.8%
2 Silver Star Construction Company, Inc. $5,400,700 +4.6% +6.5%
3 OVERLAND CORPORATION $5,978,072 +15.8% +17.9%

Bid tab: unit prices 68 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 SEWELL BROS., I…#2 Silver Star Con…#3 OVERLAND CORPOR…
10201(A)1200 CLEARING AND GRUBBING1LSUM $75,000.00 $15,000.00 $84,901.50 $223,000.00
20202(A)2200 UNCLASSIFIED EXCAVATION39,380CY $7.00 $6.00 $9.00 $11.00
30202(D)2500 UNCLASSIFIED BORROW53,746CY $9.00 $7.50 $8.00 $13.50
40205(A)6200 TYPE A-SALVAGED TOPSOIL1LSUM $50,000.00 $20,000.00 $160,000.00 $90,000.00
50221(B)2300 TEMPORARY SILT FENCE11,745LF $2.50 $3.30 $3.15 $2.90
60221(E)2600 TEMPORARY SILT DIKE525LF $10.00 $20.00 $19.00 $13.00
70221(F)2700 TEMPORARY ROCK FILTER DAM TYPE 1336CY $150.00 $150.00 $69.45 $105.00
80230(A)7200 SOLID SLAB SODDING37,789SY $1.71 $3.20 $3.15 $2.60
90233(A)0200 VEGETATIVE MULCHING19.31AC $1,000.00 $1,100.00 $1,055.00 $100.00
100241 3100 MOWING16AC $150.00 $220.00 $211.00 $50.00
110242 4100 (PL)STABILIZED CONSTRUCTION EXIT4EA $3,500.00 $500.00 $2,430.00 $3,000.00
120303(A)1200 AGGREGATE BASE TYPE A9,531CY $50.00 $50.00 $41.60 $45.00
130307(K)4200 STABILIZED SUBGRADE43,831SY $5.50 $6.00 $5.10 $5.00
140326(A)1200 GEOTEXTILE REINFORCEMENT43,831SY $1.50 $2.00 $1.40 $1.25
150402(E)2600 TRAFFIC BOUND SURFACE COURSE TYPE E2,842TON $27.50 $27.00 $23.00 $25.00
160407(B)7300 TACK COAT12,320GAL $3.00 $2.75 $2.50 $0.5000
170408 8100 PRIME COAT26,808GAL $2.50 $3.30 $3.00 $3.50
180411(B)1330 SUPERPAVE, TYPE S3(PG 64-22 OK)15,283TON $70.00 $82.50 $67.80 $84.00
190411(C)1430 SUPERPAVE, TYPE S4(PG 64-22 OK)4,783TON $80.00 $105.00 $93.85 $90.00
200412 3100 COLD MILLING PAVEMENT1,007SY $3.00 $8.00 $12.00 $10.00
210501(A)1200 STRUCTURAL EXCAVATION UNCLASSIFIED298CY $25.00 $10.00 $22.00 $30.00
220509(A)0200 CLASS AA CONCRETE408CY $500.00 $375.00 $422.00 $515.00
230511(A)2200 REINFORCING STEEL60,910LB $1.25 $1.40 $1.30 $1.35
240610(B)5310 6" CONCRETE DRIVEWAY112SY $70.00 $55.00 $278.00 $145.00
250613(B)5508 18" CORR. GALV. STEEL PIPE187LF $40.00 $35.00 $47.50 $35.00
260613(B)5524 30" CORR. GALV. STEEL PIPE59LF $50.00 $60.00 $74.00 $57.00
270613(B)5528 36" CORR. GALV. STEEL PIPE71LF $60.00 $75.00 $90.00 $67.00
280613(B)5612 28" X 20" CORR. GALV. STEEL PIPE ARCH216LF $50.00 $50.00 $63.30 $46.00
290613(L)6624 28" X 20" PREFAB. CULVERT END SEC., ARCH10EA $389.51 $300.00 $530.00 $350.00
300613(L)6708 18" PREFAB. CULVERT END SEC., ROUND6EA $550.00 $255.00 $422.00 $275.00
310613(L)6724 30" PREFAB. CULVERT END SEC., ROUND2EA $1,250.00 $600.00 $844.00 $575.00
320613(L)6728 36" PREFAB. CULVERT END SEC., ROUND2EA $1,750.00 $825.00 $1,160.00 $800.00
330619(A)6200 REMOVAL OF STRUCTURES & OBSTRUCTIONS1LSUM $50,000.00 $20,000.00 $105,000.00 $50,000.00
340619(B)6300 REMOVAL OF HEADWALL2EA $1,000.00 $1,000.00 $600.00 $1,200.00
350619(B)6352 REMOVAL OF FENCE9,074LF $1.50 $1.00 $3.10 $1.75
360619(B)6364 REMOVAL OF ASPHALT PAVEMENT1,752SY $4.00 $6.00 $17.85 $5.00
370619(B)6376 REMOVAL OF CONC.PAV.W/ASPH.OVERLAY11,116SY $6.00 $8.00 $7.95 $10.00
380619(B)6396 REMOVAL OF GUARDRAIL1,000LF $4.00 $2.50 $6.00 $4.35
390619(B)6440 REMOVAL OF EXISTING PIPE445LF $12.00 $10.00 $22.00 $7.00
400624(A)3200 FENCE-STYLE WWF7,736LF $6.00 $6.85 $5.30 $7.00
410624(D)3500 GATE, GALVANIZED STEEL2EA $1,750.00 $1,100.00 $530.00 $1,000.00
420202(A)2210 UNCLASSIFIED EXCAVATION3,030CY $9.00 $6.00 $16.50 $9.00
430501(A)1210 STRUCTURAL EXCAVATION UNCLASSIFIED640CY $20.00 $10.00 $27.00 $30.00
440509(A)0210 CLASS AA CONCRETE720CY $625.00 $375.00 $412.00 $430.00
450511(A)2210 REINFORCING STEEL127,610LB $1.25 $1.40 $1.30 $1.35
460514(J)6100 TEMPORARY SHEET PILING1LSUM $20,000.00 $20,000.00 $85,000.00 $26,000.00
470619(D)6700 REMOVAL OF EXISTING BRIDGE STRUCTURE1LSUM $50,000.00 $25,000.00 $75,000.00 $100,000.00
480413(A)4200 RUMBLE STRIP-METHOD HMA-CON9,850LF $0.3000 $0.7000 $0.6000 $0.5000
490850(A)1200 SHEET ALUMINUM SIGNS176SF $25.00 $19.50 $28.50 $19.00
500851(C)2430 2 1/2" SQUARE TUBE POST296LF $10.00 $10.00 $8.45 $9.00
510854(A)6200 TRAFFIC STRIPE(PAINT)(4" WIDE)51,220LF $0.1800 $0.1300 $0.2000 $0.1100
520856(A)8200 TRAFFIC STRIPE(MULTI-POLY.)(4" WIDE)23,270LF $0.4200 $0.5200 $0.6500 $0.5000
530856(B)8304 TRAFFIC STRIPE(MULTI-POLY.)(ARROWS)3EA $200.00 $165.00 $211.00 $150.00
540857(C)9400 REMOVABLE PAVEMENT MARKING TAPE(4" WIDE)480LF $0.7000 $1.05 $3.35 $1.00
550871(B)2300 CONST.ZONE IMPACT ATTEN.765SD $7.00 $4.10 $6.50 $4.00
560877(B)4300 DELIVER PORTABLE LONGITUDINAL BARRIER1,000LF $25.00 $20.00 $22.00 $25.00
570877(C)4400 RELOCATION OF PORT. LONGITUDINAL BARRIER450LF $4.00 $3.00 $3.15 $11.00
580880(B)6300 CONSTRUCTION SIGNS 0 TO 6.25 SF5,370SD $0.4000 $0.3200 $0.8000 $0.3000
590880(B)6310 CONSTRUCTION SIGNS 6.26 SF TO 15.99 SF1,140SD $0.5500 $0.2700 $3.15 $0.2500
600880(B)6320 CONSTRUCTION SIGNS 16.0 SF TO 32.99 SF4,770SD $1.50 $0.2700 $3.15 $0.2500
610880(C)6410 CONSTRUCTION BARRICADES(TYPE III)840SD $0.8000 $1.05 $3.15 $1.00
620880(C)6420 WING BARRICADES600SD $1.80 $1.05 $0.0200 $1.00
630880(E)6600 WARNING LIGHTS(TYPE A)1,680SD $0.3500 $4.10 $0.4500 $4.00
640880(F)6700 DRUMS26,415SD $0.2500 $0.2700 $0.2000 $0.2500
650882(A)8210 PORT.CHANGEABLE MESSAGE SIGN600SD $12.00 $9.00 $12.65 $8.00
660642(B)3300 CONSTRUCTION STAKING LEVEL II1LSUM $50,000.00 $25,000.00 $52,000.00 $58,000.00
670220 1100 SWPPP DOCUMENTATION AND MANAGEMENT1LSUM $7,000.00 $3,000.00 $18,000.00 $20,000.00
680641 2100 MOBILIZATION1LSUM $274,586.70 $250,000.00 $279,000.00 $300,000.00